| Owner | Filings | Most Recent |
|---|---|---|
| RJ CAPITAL CONSTRUCTION | 25 | 07/08/2026 |
| SS DEV PARTNERS | 8 | 03/21/2026 |
| 18 HUNTINGTON REALTY | 8 | 03/21/2026 |
| RJ CAPITAL HOLDINGS | 6 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| NEW YORK ENGINEERS LLC | 6 | 11/29/2023 |
| WEXLER ASSOCIATES | 2 | 08/24/2022 |
| TAHIR DEMIRCIOGLU ARCHITECT PLLC | 1 | 12/23/2021 |
| Representative | Filings | Most Recent |
|---|---|---|
| BOYD CONSULTING | 18 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| RJ CAPITAL CONSTRUCTION L | General Contractor | 13 | 07/08/2026 |
| MORDECHAI LUNGER | Electrical | 7 | 03/21/2026 |
| EQUAL ELECTRICAL CONT INC 004850 | General Contractor | 7 | 03/22/2026 |
| MEJ PLUMBING LLC | Plumbing | 2 | 07/08/2026 |
| EQUAL ELECTRICAL CONT INC | Electrical | 1 | 03/22/2026 |
| TAHIR DEMIRCIOGLU | Electrical | 1 | 03/21/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| S&S CONCRETE & SOIL TESTI | 1008 | 7 | 11/29/2023 |
| NEW YORK ENGINEERS, P.C. | 3868 | 1 | 06/26/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | KAY PLUMBING INC | 11/13/2023 |
| DOB NOW | Mechanical Systems | Signed-off | RJ CAPITAL CONSTRUCTION L | 12/01/2022 |
| DOB NOW | Structural | Signed-off | RJ CAPITAL CONSTRUCTION L | 11/30/2022 |
| DOB NOW | Construction Fence | Signed-off | RJ CAPITAL CONSTRUCTION L | 11/28/2022 |
| DOB NOW | Plumbing | Signed-off | KAY PLUMBING INC | 04/19/2022 |
| DOB NOW | Structural | Signed-off | RJ CAPITAL CONSTRUCTION L | 01/27/2022 |
| DOB NOW | Construction Fence | Signed-off | RJ CAPITAL CONSTRUCTION L | 01/07/2022 |
| BIS | — | ISSUED | RJ CAPITAL CONSTRUCTION L | 11/28/2022 |
| BIS | — | ISSUED | RJ CAPITAL CONSTRUCTION L | 11/28/2022 |
| BIS | — | ISSUED | RJ CAPITAL CONSTRUCTION L | 01/31/2022 |
| BIS | — | ISSUED | RJ CAPITAL CONSTRUCTION L | 01/28/2022 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/06/2024 | Complete | EQUAL ELECTRICAL CONT INC | General Wiring |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 11/16/2023 | Heating Systems | GLEN LANGER | special |
| 11/16/2023 | Mechanical Systems | GLEN LANGER | special |
| 11/16/2023 | Final | GLEN LANGER | progress |
| 11/16/2023 | Permanent certificate | GLEN LANGER | energy_progress |
| 11/16/2023 | Shutoff dampers | GLEN LANGER | energy_progress |
| 11/16/2023 | HVAC insulation and sealing | GLEN LANGER | energy_progress |
| 11/16/2023 | Maintenance information | GLEN LANGER | energy_progress |
| 11/02/2023 | Shutoff dampers | GLEN LANGER | energy_progress |
| 11/02/2023 | Heating Systems | GLEN LANGER | special |
| 11/02/2023 | Mechanical Systems | GLEN LANGER | special |
| 11/02/2023 | Final | GLEN LANGER | progress |
| 11/02/2023 | Maintenance information | GLEN LANGER | energy_progress |
| 11/02/2023 | Permanent certificate | GLEN LANGER | energy_progress |
| 11/02/2023 | HVAC insulation and sealing | GLEN LANGER | energy_progress |
| 06/21/2023 | HVAC insulation and sealing | GLEN LANGER | energy_progress |
| 06/21/2023 | Permanent certificate | GLEN LANGER | energy_progress |
| 06/21/2023 | Final | GLEN LANGER | progress |
| 06/21/2023 | Shutoff dampers | GLEN LANGER | energy_progress |
| 06/21/2023 | Maintenance information | GLEN LANGER | energy_progress |
| 06/21/2023 | Mechanical Systems | GLEN LANGER | special |
| 06/21/2023 | Heating Systems | GLEN LANGER | special |
| 06/15/2023 | Post-installed Anchors | GLEN LANGER | special |
| 06/15/2023 | Fire-Resistant Penetrations and Joints | GLEN LANGER | special |
| 09/16/2022 | Structural Cold-Formed Steel | GLEN LANGER | special |
| 09/16/2022 | Structural Steel - Welding | GLEN LANGER | special |