← Back
Two stories - detached, small or mid-size
221-07 EDMORE AVENUE
QUEENS · Queens Village · BIN 4230084
💬 Discuss this project
1915Year Built
2.5Stories
A1Building Class
R3AZoning
1,440 sfGross Floor Area
1Units
Two stories - detached, small or mid-size · 3,800 sf lot · 0.38 FAR built · Flood zone X
Locations of Work
ElectricalPlumbingGeneral
Permit Issued — active, not yet Signed-off
RoofUnder Construction1 filing · 8 docs
Floor 2Under Construction1p · 1 filing · 8 docs
Floor 1
Cellar3p · 1 filing · 8 docs
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
02/28/2019$620K—— → —$431/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
TRINITY SOLAR LLC111/20/2025
LEE ENGINEERING, P.C.203/10/2022
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
ACA ASSOCIATES103/21/2026
LEE ENGINEERING P C403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
REDLINE ELECTRIC INCElectrical103/22/2026
TRINITY SOLAR LLCGeneral Contractor104/09/2026
C.R.U. MECHAN & HEAT INCPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
BITOPI CONSULTANTS LLC7036111/20/2025
LEE ENGINEERING, P.C.2157203/10/2022
Building Lifecycle
All (19)Filed (3)Permit Issued (2)Inspection (7)Special Inspection (7)
11/24/2025
Permit issued — Solar
Q01320182-I1-SL
11/20/2025
Filed — Alteration
Q01320182-I1
11/17/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
KAMRUL AHSAN
11/17/2025
Special inspection requirement — Final
Ayracon Almaraz
11/17/2025
Special inspection requirement — Air barrier - visual inspection
Ayracon Almaraz
11/17/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
KAMRUL AHSAN
11/17/2025
Special inspection requirement — Energy Code Compliance Inspections
Ayracon Almaraz
07/26/2022
Inspection — Fail-Final PL - Up to 3 Requested Floors
Fail
View inspection ↗
07/06/2022
Inspection — Fail-Final PL - Up to 3 Requested Floors
Fail
View inspection ↗
05/27/2022
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
05/27/2022
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
04/05/2022
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
03/23/2022
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
03/23/2022
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
03/10/2022
Filed — Alteration
TO CONVERT OIL BOILER TO GAS BOILER. NO CHANGE IN OCCUPANCY, USE, OR EGRESS IS UNDER THIS APPLICATION.
Q00653710-P1
02/24/2022
Special inspection requirement — Energy Code Compliance Inspections
YEON LEE
02/24/2022
Special inspection requirement — Fire-Resistant Penetrations and Joints
YEON LEE
02/07/2022
Permit issued — Plumbing
Q00653710-I1-PL
02/03/2022
Filed — Alteration
TO CONVERT OIL BOILER TO GAS BOILER. NO CHANGE IN OCCUPANCY, USE, OR EGRESS IS UNDER THIS APPLICATION.
Q00653710-I1
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarPermit IssuedTRINITY SOLAR LLC11/24/2025
DOB NOWPlumbingPermit IssuedC.R.U. MECHAN & HEAT INC02/07/2022
1 project · most recent 03/10/2022
Gas
FiledStatusContractorScope
03/10/2022Permit IssuedC.R.U. MECHAN & HEAT INCGas
1 project · most recent 11/17/2025
FiledStatusContractorScope
11/17/2025CancelledREDLINE ELECTRIC INC—
▾Field Inspections (DOB CAP) — 7
DateTypeResultReport
07/26/2022Fail-Final PL - Up to 3 Requested FloorsFailView ↗
07/06/2022Fail-Final PL - Up to 3 Requested FloorsFailView ↗
05/27/2022Certified Gas-Gas-Piping-RoughingCertifiedView ↗
05/27/2022Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
04/05/2022Pass-Final PL - Up to 3 Requested FloorsPassView ↗
03/23/2022Certified Gas-Gas-Piping-RoughingCertifiedView ↗
03/23/2022Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 7
DateRequirementInspectorRole
11/17/2025Structural Stability – Alterations of existing buildingsKAMRUL AHSANspecial
11/17/2025FinalAyracon Almarazprogress
11/17/2025Air barrier - visual inspectionAyracon Almarazenergy_progress
11/17/2025Fire-Resistant Penetrations and JointsKAMRUL AHSANspecial
11/17/2025Energy Code Compliance InspectionsAyracon Almarazprogress
02/24/2022Energy Code Compliance InspectionsYEON LEEprogress
02/24/2022Fire-Resistant Penetrations and JointsYEON LEEspecial
▾Documents — 16 on file (BIS + DOB NOW)
▸Plans & Drawings3
▸DOB NOWPlans/Sketch3
08/26/2026Q00653710-I1Request digital key ↗
08/26/2026Q00653710-P1Request digital key ↗
08/18/2026Q01320182-I1Request digital key ↗
▸Seals & Professional Certifications10
▸DOB NOWProgress Inspector Seal & Signature4
09/22/2026Q01320182-I1Open ↗
09/22/2026Q01320182-I1Open ↗
09/22/2026Q01320182-I1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature3
08/26/2026Q00653710-P1Open ↗
08/26/2026Q00653710-I1Open ↗
08/18/2026Q01320182-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature3
09/22/2026Q01320182-I1Open ↗
09/22/2026Q01320182-I1Open ↗
09/01/2026Q00653710-P1Open ↗
▸Environmental & Asbestos3
▸DOB NOWDEP ACP-5: Asbestos Assessment Report3
08/26/2026Q00653710-P1Open ↗
08/26/2026Q00653710-I1Open ↗
08/18/2026Q01320182-I1Open ↗