← Back
Over six families without stores
Fiorentino Plaza-3
2211 PITKIN AVENUE · BIN 3328465
💬 Discuss this project
1970Year Built
4Stories
C1Building Class
R7AZoning
73,900 sfGross Floor Area
16Units
LL97 CoveredRent Stabilized2 Open Violations ▸FDNY Report ↗
Over six families without stores · Owner of record: BOULEVARD TOGETHER OWNER LLC · 35,000 sf lot · 2.11 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbing
Roof8p · 4 filings · 20 docs
Bulkhead1p · 1 filing · 20 docs
Floor 414p · 3 filings · 20 docs
Floor 314p · 3 filings · 20 docs
Floor 214p · 3 filings · 20 docs
Floor 19p · 4 filings · 20 docs
Cellar22p · 4 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
NYCHA407/08/2026
NEW YORK CITY HOUSING AUTHORITY3507/08/2026
BOULEVARD TOGETHER DEVELOPER1907/08/2026
N.Y.C. HOUSING AUTHORITY103/22/2026
NYC HOUSING AUTHORITY 9103/22/2026
SKYWORX CONTRCTING INC803/22/2026
BROADWAY BUILDERS103/22/2026
BOULEVARD TOGETHER OWNER LLC103/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
PETER CLEMENTS ARCHITECT1207/02/2025
M. HAMDI GUNAL, PE, P. C.402/04/2025
EP ENGINEERING LLC809/09/2024
ASHRAF CORP309/27/2023
JOEL PHAGOO P.E. PLLC308/18/2023
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
BETRO DESIGN GROUP2403/21/2026
RENNON CONSTRUCTION603/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
A.M.K. CONTRACTING CORPGeneral Contractor1907/08/2026
RENNON CONSTRUCTION CORPGeneral Contractor403/21/2026
SKYLINE RESTORATION INCGeneral Contractor307/08/2026
NEELAM CONSTRUCTION CORPGeneral Contractor107/08/2026
GILSTON ELEC'L CONTR. CORElectrical103/22/2026
M & M PIPING AND HEATINGPlumbing107/08/2026
THANASI ELECTRICAL, LLCElectrical103/22/2026
MNK ENTERPRISES LLCGeneral Contractor107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
AMARACON TESTING & INSPEC58421305/30/2025
EP INSPECTIONS AND COMMIS70791805/30/2025
M. HAMDI GUNAL, PE, P.C.3000110/15/2021
Building Lifecycle
All (170)Filed (30)Permit Issued (16)Signed Off (10)Violation (60)Inspection (8)Objection (16)Special Inspection (30)
03/17/2026
Signed off — Alteration
INSTALL NEW LOUVER AND CEILING EXHAUST FANS, INSTALL NEW RADIATOR COVERS AND REPLACE EXISTING GRILLE AS PER PLANS FILED.
B00539310-I1
09/04/2025
Signed off — Alteration
REMOVAL & INSTALL ALL WALL, FLOOR & CEILING FINISHES, KITCHEN APPLIANCES & CABINETS, DOORS & FRAMES TO BE DEMOLISHED & REPLACED AS PER PLANS FILED.
B00741274-I1
08/28/2025
Special inspection requirement — Lighting in dwelling units
Christopher Burgess
08/28/2025
Special inspection requirement — Final
Christopher Burgess
08/28/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
CONNIE PISANI
08/28/2025
Special inspection requirement — Insulation placement and R values
Christopher Burgess
08/28/2025
Special inspection requirement — Energy Code Compliance Inspections
Christopher Burgess
08/28/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Christopher Burgess
08/26/2025
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
08/22/2025
Objection resolved — Addressed
08/21/2025
Objection raised — Scope
08/21/2025
Objection resolved — Addressed
07/29/2025
Violation issued (HPD, closed)
B
07/29/2025
Violation issued (HPD, closed)
B
07/23/2025
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
07/09/2025
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
07/02/2025
Filed — Alteration CO
B00569207-P1
06/25/2025
Signed off — Alteration
REMOVE AND RECONSTRUCT BUILDING PARAPET WALL ALONG PERIMETER INCLUDING STAIR BULKHEAD WITH NEW PRECAST COPING AND SISTER EXISTING JOISTS AT AREAS OF DETERIORATION AND PROVIDE NEW OR SISTER MEMBERS AS NEEDED. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
B00596495-I1
06/20/2025
Signed off — Alteration
ROOF AND PARAPET RECONSTRUCTRION, WINDOW REPLACEMENT, WINDOW LINTEL WHERE DAMAGED OR DETERIORATED, BRICK POINTING AND REPLACEMENT WHERE CRACKED OR DAMAGED AND FIRE ESCAPE REPAIR / RECONSTRUCTION WHERE DAMAGED OR DETERIORATED AS PER PLANS FILED.
B00527287-I1
06/14/2025
Signed off — Alteration
B00355479-I1
06/13/2025
Signed off — Alteration
INSTALLATION OF TEMPORARY SIDEWALK SHED AS PER PLANS. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE 2022 NYC BUILDING CODE. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
B00920412-I1
06/11/2025
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
06/03/2025
Signed off — Alteration
REPLACEMENT OF ALL FIXTURES THROUGHOUT WITHIN EXISTING ROUGHING AT FLOORS 1 THRU 4 & ROOF AS PER PLANS FILED.
B00534820-I1
05/30/2025
Filed — Alteration
ROOF AND PARAPET RECONSTRUCTRION, WINDOW REPLACEMENT, WINDOW LINTEL WHERE DAMAGED OR DETERIORATED, BRICK POINTING AND REPLACEMENT WHERE CRACKED OR DAMAGED AND FIRE ESCAPE REPAIR / RECONSTRUCTION WHERE DAMAGED OR DETERIORATED AS PER PLANS FILED.
B00527287-P5
05/20/2025
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
05/14/2025
Signed off — Alteration
Installation of temporary supported scaffold per plan submitted. Work shall comply with 2014 building codes chapter 33. No change in use, egress and/or occupancy with this application.
B00902771-I1
05/08/2025
Objection raised — Scope
05/01/2025
Filed — Alteration
REMOVAL & INSTALL ALL WALL, FLOOR & CEILING FINISHES, KITCHEN APPLIANCES & CABINETS, DOORS & FRAMES TO BE DEMOLISHED & REPLACED AS PER PLANS FILED.
B00741274-P3
03/07/2025
Inspection — Pass-Final PL - Up to 9 Requested Floors
Pass
View inspection ↗
02/07/2025
Permit issued — Structural
B00596495-I1-ST
02/06/2025
Special inspection requirement — Final
Mehmet Gunal
02/06/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Christopher Burgess
02/06/2025
Special inspection requirement — Structural Cold-Formed Steel
Mehmet Gunal
02/06/2025
Special inspection requirement — Structural Steel - Welding
Mehmet Gunal
02/06/2025
Special inspection requirement — Structural Steel - Details
Mehmet Gunal
02/06/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
Mehmet Gunal
02/06/2025
Special inspection requirement — Structural Wood Frame
Mehmet Gunal
02/06/2025
Special inspection requirement — Masonry
Mehmet Gunal
02/04/2025
Filed — Alteration
REMOVE AND RECONSTRUCT BUILDING PARAPET WALL ALONG PERIMETER INCLUDING STAIR BULKHEAD WITH NEW PRECAST COPING AND SISTER EXISTING JOISTS AT AREAS OF DETERIORATION AND PROVIDE NEW OR SISTER MEMBERS AS NEEDED. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
B00596495-P3
01/29/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
01/27/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Christopher Burgess
01/27/2025
Special inspection requirement — Masonry
CONNIE PISANI
01/27/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
CONNIE PISANI
01/27/2025
Special inspection requirement — Structural Cold-Formed Steel
CONNIE PISANI
01/27/2025
Special inspection requirement — Final
CONNIE PISANI
01/27/2025
Special inspection requirement — Structural Steel - Welding
CONNIE PISANI
01/27/2025
Special inspection requirement — Structural Wood Frame
CONNIE PISANI
01/27/2025
Special inspection requirement — Structural Steel - Details
CONNIE PISANI
01/23/2025
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
01/07/2025
Permit issued — Plumbing
B00534820-I1-PL
12/18/2024
Permit issued — Mechanical Systems
B00539310-I1-MS
12/18/2024
Permit issued — General Construction
B00741274-I1-GC
10/18/2024
Signed off — Alteration
Installation of temporary supported scaffold per plan submitted. Work shall comply with 2014 building codes chapter 33. No change in use, egress and/or occupancy with this application.
B00902771-S1
09/23/2024
Filed — Alteration
REMOVAL & INSTALL ALL WALL, FLOOR & CEILING FINISHES, KITCHEN APPLIANCES & CABINETS, DOORS & FRAMES TO BE DEMOLISHED & REPLACED AS PER PLANS FILED.
B00741274-P2
09/09/2024
Filed — Alteration
REPLACEMENT OF ALL FIXTURES THROUGHOUT WITHIN EXISTING ROUGHING AT FLOORS 1 THRU 4 & ROOF AS PER PLANS FILED.
B00534820-P3
09/09/2024
Filed — Alteration
INSTALL NEW LOUVER AND CEILING EXHAUST FANS, INSTALL NEW RADIATOR COVERS AND REPLACE EXISTING GRILLE AS PER PLANS FILED.
B00539310-P3
09/09/2024
Filed — Alteration
REMOVE AND RECONSTRUCT BUILDING PARAPET WALL ALONG PERIMETER INCLUDING STAIR BULKHEAD WITH NEW PRECAST COPING AND SISTER EXISTING JOISTS AT AREAS OF DETERIORATION AND PROVIDE NEW OR SISTER MEMBERS AS NEEDED. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
B00596495-P2
09/09/2024
Permit issued — General Construction
B00527287-I1-GC
09/09/2024
Permit issued — General Construction
B00527287-I1-ST
09/06/2024
Special inspection requirement — Wood – Seismic Resistance
Latest 60 of 170 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWStructuralSigned-offA.M.K. CONTRACTING CORP02/07/2025
DOB NOWPlumbingSigned-offM & M PIPING AND HEATING01/07/2025
DOB NOWMechanical SystemsSigned-offA.M.K. CONTRACTING CORP12/18/2024
DOB NOWGeneral ConstructionSigned-offA.M.K. CONTRACTING CORP12/18/2024
DOB NOWGeneral ConstructionSigned-offA.M.K. CONTRACTING CORP09/09/2024
DOB NOWGeneral ConstructionSigned-offA.M.K. CONTRACTING CORP09/09/2024
DOB NOWGeneral ConstructionPermit IssuedA.M.K. CONTRACTING CORP08/07/2024
DOB NOWConstruction FenceSigned-offSKYLINE RESTORATION INC02/20/2024
DOB NOWGeneral ConstructionSigned-offA.M.K. CONTRACTING CORP09/12/2023
DOB NOWStructuralSigned-offA.M.K. CONTRACTING CORP09/12/2023
DOB NOWSidewalk ShedSigned-offMNK ENTERPRISES LLC08/18/2023
DOB NOWConstruction FenceSigned-offSKYLINE RESTORATION INC08/18/2023
DOB NOWGeneral ConstructionPermit IssuedA.M.K. CONTRACTING CORP08/18/2023
DOB NOWProtection and Mechanical MethodsSigned-offRENNON CONSTRUCTION CORP08/11/2023
DOB NOWSupported ScaffoldSigned-offRENNON CONSTRUCTION CORP07/25/2023
DOB NOWConstruction FenceSigned-offNEELAM CONSTRUCTION CORP06/12/2020
BISEQISSUEDSKYWORX CONTRACTING INC05/03/2022
BISEQISSUEDSKYWORX CONTRACTING INC03/19/2021
BISEQISSUEDSKYWORX CONTRACTING INC02/26/2020
BISPLISSUEDROCON CORP09/19/2019
BISEQISSUEDSKYWORX CONTRACTING INC03/04/2019
BISEQISSUEDSKYWORX CONTRACTING INC03/08/2018
BISEQISSUEDSKYWORX CONTRACTING INC03/07/2017
4 projects · most recent 04/02/2026
General Wiring
FiledStatusContractorScope
04/02/2026CompleteTHANASI ELECTRICAL, LLCGeneral Wiring
05/13/2021Permit IssuedAMIN ELECTRICAL CORP—
12/18/2019CompleteTRU-VAL ELECTRIC CORP.General Wiring
01/10/2019CompleteGILSTON ELEC'L CONTR. CORGeneral Wiring
▾Field Inspections (DOB CAP) — 8
DateTypeResultReport
08/26/2025Pass-Final CND-Occupancy InspectionPassView ↗
07/23/2025Pass-Final CND-Occupancy InspectionPassView ↗
07/09/2025Pass-Final CND-Occupancy InspectionPassView ↗
06/11/2025Pass-Final CND-Occupancy InspectionPassView ↗
05/20/2025Pass-Final CND-Occupancy InspectionPassView ↗
03/07/2025Pass-Final PL - Up to 9 Requested FloorsPassView ↗
01/29/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
01/23/2025Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 109
DateRequirementInspectorRole
08/28/2025Energy Code Compliance InspectionsChristopher Burgessprogress
08/28/2025FinalChristopher Burgessprogress
08/28/2025Lighting in dwelling unitsChristopher Burgessenergy_progress
08/28/2025Insulation placement and R valuesChristopher Burgessenergy_progress
08/28/2025Structural Stability – Alterations of existing buildingsCONNIE PISANIspecial
08/28/2025Fire-Resistant Penetrations and JointsChristopher Burgessspecial
02/06/2025Structural Steel - DetailsMehmet Gunalspecial
02/06/2025Fire-Resistant Penetrations and JointsChristopher Burgessspecial
02/06/2025MasonryMehmet Gunalspecial
02/06/2025Structural Stability – Alterations of existing buildingsMehmet Gunalspecial
02/06/2025FinalMehmet Gunalprogress
02/06/2025Structural Wood FrameMehmet Gunalprogress
02/06/2025Structural Cold-Formed SteelMehmet Gunalspecial
02/06/2025Structural Steel - WeldingMehmet Gunalspecial
01/27/2025Structural Steel - DetailsCONNIE PISANIspecial
01/27/2025Structural Steel - WeldingCONNIE PISANIspecial
01/27/2025FinalCONNIE PISANIprogress
01/27/2025Structural Wood FrameCONNIE PISANIprogress
01/27/2025Structural Stability – Alterations of existing buildingsCONNIE PISANIspecial
01/27/2025MasonryCONNIE PISANIspecial
01/27/2025Fire-Resistant Penetrations and JointsChristopher Burgessspecial
01/27/2025Structural Cold-Formed SteelCONNIE PISANIspecial
09/06/2024Wood – Seismic Resistance—special
08/26/2024Fire-Resistant Penetrations and JointsChristopher Burgessspecial
08/26/2024Mechanical SystemsChristopher Burgessspecial
Latest 25 of 109.
▾Documents — 192 on file (BIS + DOB NOW)
▸Plans & Drawings30
▸DOB NOWPlans/Sketch29
09/01/2026B00527287-P2Request digital key ↗
09/01/2026B00527287-P1Request digital key ↗
09/01/2026B00527287-P5Request digital key ↗
Showing 3 of 29 on file for this type
▸DOB NOWPlans/Sketch - Construction Fence1
09/02/2026B00355479-I1Request digital key ↗
▸Applications & Permits9
▸BISWORK PERMIT APPLICATION6
05/07/2022340476416Open ↗
09/23/2019321070513Open ↗
03/06/2019340476416Open ↗
Showing 3 of 6 on file for this type
▸BISPLAN / WORK APPROVAL APPLICATION3
06/18/2025340476416Open ↗
10/30/2018321070513Open ↗
02/24/2017340476416Open ↗
▸Seals & Professional Certifications83
▸DOB NOWDPL-1: Design Professional Seal & Signature30
09/01/2026B00527287-P2Open ↗
09/01/2026B00527287-P1Open ↗
09/01/2026B00527287-P3Open ↗
Showing 3 of 30 on file for this type
▸DOB NOWProgress Inspector Seal & Signature26
09/03/2026B00527287-P1Open ↗
09/03/2026B00527287-P1Open ↗
09/01/2026B00539310-P3Open ↗
Showing 3 of 26 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature22
09/01/2026B00539310-P3Open ↗
09/01/2026B00596495-P3Open ↗
09/01/2026B00596495-P3Open ↗
Showing 3 of 22 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION2
09/23/2019321070513Open ↗
10/30/2018321070513Open ↗
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION1
02/24/2017340476416Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT1
02/24/2017340476416Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
02/24/2017340476416Open ↗
▸Trade Schedules & Equipment1
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE1
10/30/2018321070513Open ↗
▸Safety & Tenant Protection5
▸BISTENANT PROTECTION PLAN AND NOTES2
02/24/2017340476416Open ↗
10/30/2018321070513Open ↗
▸DOB NOWStreet Tree Checklist2
08/21/2026B00569207-P1Open ↗
08/21/2026B00569207-I1Open ↗
▸DOB NOWTenant Protection Plan1
08/13/2026B00355479-I1Open ↗
▸Environmental & Asbestos6
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form5
09/01/2026B00527287-I1Open ↗
09/01/2026B00534820-I1Open ↗
09/01/2026B00596495-I1Open ↗
Showing 3 of 5 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)1
09/11/2019321070513Open ↗
▸Energy Compliance8
▸DOB NOWEN2: As Built Energy Analysis.3
08/13/2026B00539310-I1Open ↗
08/13/2026B00527287-I1Open ↗
08/13/2026B00741274-I1Open ↗
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS2
09/23/2019321070513Open ↗
10/30/2018321070513Open ↗
▸BISELECTRICAL APPLICATION FOR SIDEWALK SHED LIGHTING1
02/24/2017340476416Open ↗
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY1
03/04/2021321070513Open ↗
▸BISAS-BUILT ENERGY ANALYSIS (EN2)1
03/04/2021321070513Open ↗
▸Inspections & Test Reports2
▸BISTECHNICAL REPORT: RESPONSIBILITY2
03/04/2021321070513Open ↗
02/24/2017340476416Open ↗
▸Approvals, Objections & Sign-offs35
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter25
09/01/2026B00527287-P1Open ↗
09/01/2026B00527287-P3Open ↗
09/01/2026B00527287-P5Open ↗
Showing 3 of 25 on file for this type
▸DOB NOWDesign Commission Sign Off City Owned (Exterior Work)4
08/13/2026B00569207-I1Open ↗
08/13/2026B00534820-I1Open ↗
08/13/2026B00527287-I1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWDesign Commission Approval City Owned (Exterior Work)4
08/13/2026B00539310-P3Open ↗
08/13/2026B00539310-I1Open ↗
08/13/2026B00539310-P2Open ↗
Showing 3 of 4 on file for this type
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST1
05/18/2021321070513Open ↗
▸DOB NOWDEP Variance (V5) letter1
09/01/2026B00527287-I1Open ↗
▸Cost, Insurance & Ownership2
▸BISCOST AFFIDAVIT1
10/30/2018321070513Open ↗
▸BISCOST AFFIDAVIT (FINAL): PW31
05/18/2021321070513Open ↗
▸Filing & Intake Forms3
▸BISBOROUGH INTAKE FORM1
03/22/2021340476416Open ↗
▸BISEFILING COVER SHEET1
10/30/2018321070513Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET1
02/24/2017340476416Open ↗
▸Other Documents8
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone6
08/13/2026B00527287-P5Open ↗
08/13/2026B00527287-P3Open ↗
08/13/2026B00527287-P4Open ↗
Showing 3 of 6 on file for this type
▸BISWALL PERFORMANCE ELIGIBILITY REQUIRED1
03/22/2021340476416Open ↗
▸DOB NOWFinal Survey1
08/13/2026B00569207-I1Open ↗