← Back
Cape Cod
223-29 114 ROAD
QUEENS · BIN 4242464
💬 Discuss this project
1960Year Built
1.5Stories
A0Building Class
R2AZoning
840 sfGross Floor Area
1Units
Cape Cod · 3,400 sf lot · 0.25 FAR built · Flood zone X
Locations of Work
General
Floor 21p · 1 filing · 20 docs
Floor 1
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
01/27/2025$540K—Private party → Private party$643/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
TRINITY SOLAR LLC302/28/2026
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
ACA ASSOCIATES303/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
TRINITY SOLAR LLCGeneral Contractor303/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
IKRA CONSULTING LLC7032302/28/2026
Building Lifecycle
All (18)Filed (3)Permit Issued (1)Signed Off (1)Special Inspection (13)
03/06/2026
Signed off — Alteration
Installation of solar system on the roof as per plan. No change in use, egress or occupancy
Q01247709-I1
03/02/2026
Special inspection requirement — Air barrier - visual inspection
Ayracon Almaraz
03/02/2026
Special inspection requirement — Final
Ayracon Almaraz
03/02/2026
Special inspection requirement — Energy Code Compliance Inspections
Ayracon Almaraz
03/02/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
MD MOSTAFA
02/28/2026
Filed — Alteration
Installation of solar system on the roof as per plan. No change in use, egress or occupancy
Q01247709-P2
02/28/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
MD MOSTAFA
02/28/2026
Special inspection requirement — Energy Code Compliance Inspections
Ayracon Almaraz
02/28/2026
Special inspection requirement — Final
Ayracon Almaraz
02/28/2026
Special inspection requirement — Air barrier - visual inspection
Ayracon Almaraz
07/03/2025
Filed — Alteration
Installation of solar system on the roof as per plan. No change in use, egress or occupancy
Q01247709-P1
07/03/2025
Special inspection requirement — Air barrier - visual inspection
Ayracon Almaraz
07/03/2025
Special inspection requirement — Final
Ayracon Almaraz
07/03/2025
Special inspection requirement — Energy Code Compliance Inspections
Ayracon Almaraz
07/03/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
MD MOSTAFA
07/03/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
MD MOSTAFA
07/01/2025
Permit issued — Solar
Q01247709-I1-SL
06/27/2025
Filed — Alteration
Installation of solar system on the roof as per plan. No change in use, egress or occupancy
Q01247709-I1
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offTRINITY SOLAR LLC07/01/2025
1 project · most recent 08/11/2025
FiledStatusContractorScope
08/11/2025CompleteREDLINE ELECTRIC INC—
▾Special Inspection Requirements (DOB NOW) — 13
DateRequirementInspectorRole
03/02/2026Air barrier - visual inspectionAyracon Almarazenergy_progress
03/02/2026FinalAyracon Almarazprogress
03/02/2026Energy Code Compliance InspectionsAyracon Almarazprogress
03/02/2026Fire-Resistant Penetrations and JointsMD MOSTAFAspecial
02/28/2026Fire-Resistant Penetrations and JointsMD MOSTAFAspecial
02/28/2026Energy Code Compliance InspectionsAyracon Almarazprogress
02/28/2026FinalAyracon Almarazprogress
02/28/2026Air barrier - visual inspectionAyracon Almarazenergy_progress
07/03/2025Air barrier - visual inspectionAyracon Almarazenergy_progress
07/03/2025FinalAyracon Almarazprogress
07/03/2025Energy Code Compliance InspectionsAyracon Almarazprogress
07/03/2025Structural Stability – Alterations of existing buildingsMD MOSTAFAspecial
07/03/2025Fire-Resistant Penetrations and JointsMD MOSTAFAspecial
▾Documents — 23 on file (BIS + DOB NOW)
▸Plans & Drawings3
▸DOB NOWPlans/Sketch3
08/19/2026Q01247709-P2Request digital key ↗
08/19/2026Q01247709-P1Request digital key ↗
08/19/2026Q01247709-I1Request digital key ↗
▸Seals & Professional Certifications16
▸DOB NOWProgress Inspector Seal & Signature9
09/21/2026Q01247709-I1Open ↗
09/21/2026Q01247709-I1Open ↗
09/21/2026Q01247709-I1Open ↗
Showing 3 of 9 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature4
09/21/2026Q01247709-I1Open ↗
08/29/2026Q01247709-P1Open ↗
08/29/2026Q01247709-P1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature3
08/13/2026Q01247709-I1Open ↗
08/13/2026Q01247709-P1Open ↗
08/13/2026Q01247709-P2Open ↗
▸Environmental & Asbestos3
▸DOB NOWDEP ACP-5: Asbestos Assessment Report3
08/13/2026Q01247709-P1Open ↗
08/13/2026Q01247709-I1Open ↗
08/13/2026Q01247709-P2Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/13/2026Q01247709-I1Open ↗