| Owner | Filings | Most Recent |
|---|---|---|
| TAJCO CONSTRUCTION | 8 | 09/13/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 04/14/2025 | $720K | — | Private party → 2243 SCHENECTADY AVE LLC | $459/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| SCALAR ARCHITECTURE PC | 3 | 08/19/2026 |
| MCHENERY TESTING LAB | 1 | 07/14/2026 |
| Representative | Filings | Most Recent |
|---|---|---|
| AE DESIGN SOLUTION | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| TAJCO CONSTRUCTION CORP | General Contractor | 4 | 08/20/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| DAVID KATZ, P.E. | 6087 | 2 | 06/15/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Construction Fence | Permit Issued | TAJCO CONSTRUCTION CORP | 08/19/2026 |
| DOB NOW | Foundation | Permit Issued | TAJCO CONSTRUCTION CORP | 08/14/2026 |
| DOB NOW | Construction Fence | Permit Issued | TAJCO CONSTRUCTION CORP | 07/15/2026 |
| DOB NOW | Foundation | Permit Issued | TAJCO CONSTRUCTION CORP | 07/08/2026 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/23/2026 | Permit Issued | JKL ELECTRIC LLC | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/19/2026 | Permit Issued | TAJCO CONSTRUCTION CORP | 1 scope_items |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/14/2026 | Permit Issued | TAJCO CONSTRUCTION CORP | Fence |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 06/24/2026 | Structural Stability – Alterations of existing buildings | David Katz | special |
| 06/24/2026 | Fire-Resistant Penetrations and Joints | David Katz | special |
| 06/24/2026 | Exterior Insulation and Finish Systems (EIFS) | David Katz | special |
| 06/24/2026 | Final | David Katz | progress |
| 06/24/2026 | Fire-Resistance Rated Construction | David Katz | progress |
| 06/24/2026 | Energy Code Compliance Inspections | David Katz | progress |
| 06/24/2026 | Footing and Foundation | David Katz | progress |
| 06/24/2026 | Interior lighting power | David Katz | energy_progress |
| 06/24/2026 | Air barrier - visual inspection | David Katz | energy_progress |
| 06/24/2026 | Fenestration and door U-factor and product ratings | David Katz | energy_progress |
| 06/24/2026 | Fenestration air leakage | David Katz | energy_progress |
| 06/24/2026 | Fenestration areas | David Katz | energy_progress |
| 06/24/2026 | Insulation placement and R values | David Katz | energy_progress |
| 06/24/2026 | Permanent certificate | David Katz | energy_progress |
| 06/12/2026 | Exterior Insulation and Finish Systems (EIFS) | David Katz | special |
| 06/12/2026 | Fire-Resistant Penetrations and Joints | David Katz | special |
| 06/12/2026 | Structural Stability – Alterations of existing buildings | David Katz | special |
| 06/12/2026 | Energy Code Compliance Inspections | David Katz | progress |
| 06/12/2026 | Final | David Katz | progress |
| 06/12/2026 | Fire-Resistance Rated Construction | David Katz | progress |
| 06/12/2026 | Footing and Foundation | David Katz | progress |
| 06/12/2026 | Fenestration areas | David Katz | energy_progress |
| 06/12/2026 | Insulation placement and R values | David Katz | energy_progress |
| 06/12/2026 | Interior lighting power | David Katz | energy_progress |
| 06/12/2026 | Fenestration and door U-factor and product ratings | David Katz | energy_progress |