← Back
Public elementary, junior or senior high
Kipp Freedom Charter School
2246 JEROME AVENUE · BIN 2014062
💬 Discuss this project
1927Year Built
2Stories
W1Building Class
R7AZoning
33,400 sfGross Floor Area
1Units
LL97 Covered2 Open Violations 1 unresolved · 1 paperwork only ▸FDNY Report ↗
Public elementary, junior or senior high · Owner of record: 2246 MANAGER TIC LLC · 16,700 sf lot · 2 FAR built · Flood zone X
Locations of Work
MechanicalPlumbing
Roof10p · 2 filings · 20 docs
Floor 101p · 1 filing · 4 docs
Floor 9
Floor 8
Floor 7
Floor 6
Floor 5
Floor 4
Floor 3
Floor 212p · 4 filings · 20 docs
Floor 110p · 2 filings · 16 docs
Cellar1p · 1 filing · 17 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
JASCO807/08/2026
ROCKOWER MANAGEMENT607/08/2026
2246 MANAGER TIC LLC103/22/2026
2246 JEROME AVE ASSOC303/22/2026
DEPARTMENT OF EDUCATION203/22/2026
D.O.E. P.S.315 0203/22/2026
DOE PS 315 040103/22/2026
DOE 040303/22/2026
DEPT OF EDUCATION PS.315203/22/2026
DEPT. OF EDUCATION 0103/22/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
06/04/2018$1.4M—— → —$43/sf building
03/02/2017$9.4M—— → —$283/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
JT ENGINEERING, PC610/12/2022
ENTHINK ENGINEERS LLC205/09/2022
JAJ ENGINEERING PLLC110/25/2021
JOEL PHAGOO P.E. PLLC208/25/2021
DM ENGINEERS PLLC311/20/2019
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
EFG CONSULTING603/21/2026
A1 EXPEDITING SERVICE403/21/2026
ANTHONY BONSIGNORE RA203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
ROCKLEDGE SCAFFOLD CORPGeneral Contractor707/08/2026
JASCO, INCGeneral Contractor407/08/2026
THE ELITE GROUP OF NYC INGeneral Contractor303/21/2026
DELUXE CONSTRUCTIONGeneral Contractor203/21/2026
SAMUEL & SONS P & H INCPlumbing207/08/2026
M. MELNICK & COMPANY INCGeneral Contractor107/08/2026
SMITH, STEPHENElectrical103/21/2026
J. SIBAJA KITCHEN AND VE*General Contractor107/08/2026
BETANCOURT, JOHNElectrical103/21/2026
L.L.G. PLBG & HTG INCPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
ENVIRONMENTAL CODE CONSUL5516210/12/2022
JT ENGINEERING, PC7840308/21/2022
JAJ ENGINEERING PLLC930110/25/2021
JOEL PHAGOO ,PE, PLLC2416108/25/2021
CL ENGINEERING P.C.6781210/30/2019
Building Lifecycle
All (132)Filed (14)Permit Issued (13)Signed Off (7)Violation (55)Inspection (1)Objection (12)Special Inspection (30)
07/21/2026
Violation issued (ECB, open)
Construction
02/02/2026
Violation issued (FDNY_NOV, closed)
09/08/2025
Violation issued (ECB, closed)
Construction
09/08/2025
Violation issued (ECB, closed)
Construction
09/08/2025
Violation issued (ECB, closed)
Construction
09/08/2025
Violation issued (ECB, closed)
Construction
07/19/2025
Violation issued (FDNY_NOV, closed)
01/30/2025
Violation issued (FDNY_ORDER, closed)
01/30/2025
Violation issued (FDNY_ORDER, closed)
10/17/2024
Violation issued (ECB, closed)
Construction
10/17/2024
Violation issued (ECB, closed)
Construction
02/08/2024
Violation issued (FDNY_NOV, closed)
06/14/2023
Violation issued (ECB, closed)
Construction
02/17/2023
Violation issued (FDNY_NOV, closed)
01/13/2023
Signed off — Alteration
X00575834-I1
01/13/2023
Signed off — Alteration
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER DRAWINGS. PIPE SCAFFOLD SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
X00574131-I1
01/09/2023
Signed off — Alteration
X00608536-I1
10/19/2022
Signed off — Alteration
INSTALLATION OF A NEW TYPE I KITCHEN HOOD, (1)GREASE EXHAUST FAN AND (1) NON-HEATED MAKE-UP AIR UNIT.
X00564249-I1
10/12/2022
Filed — Alteration
INSTALLATION OF A NEW TYPE I KITCHEN HOOD, (1)GREASE EXHAUST FAN AND (1) NON-HEATED MAKE-UP AIR UNIT.
X00564249-P1
09/13/2022
Signed off — Alteration
PROPOSED INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. WORK SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY, OR EGRESS UNDER THIS APPLICATION.
X00731580-I1
09/13/2022
Signed off — Alteration
X00726824-I1
08/24/2022
Permit issued — Supported Scaffold
X00574131-I1-SF
08/24/2022
Permit issued — Protection and Mechanical Methods
X00575834-I1-PM
08/22/2022
Special inspection requirement — Fire-Resistant Penetrations and Joints
Jafet Tavarez
08/22/2022
Special inspection requirement — Maintenance information
Jafet Tavarez
08/21/2022
Filed — Alteration
INSTALLATION OF (4) COMMERCIAL COOKING APPLIANCES, ASSOCIATED GAS PIPING & ACCESORIES AND EMERGENGY FIRE SUPRESSION VALVE.
X00579316-P2
07/12/2022
Special inspection requirement — Final
CHRISTOPHER COMPTON
07/12/2022
Special inspection requirement — Shutoff dampers
CHRISTOPHER COMPTON
07/12/2022
Special inspection requirement — Fire-Resistant Penetrations and Joints
CHRISTOPHER COMPTON
07/12/2022
Special inspection requirement — HVAC-R and service water piping design and insulation
CHRISTOPHER COMPTON
07/12/2022
Special inspection requirement — Maintenance information
CHRISTOPHER COMPTON
07/12/2022
Special inspection requirement — Mechanical Systems
CHRISTOPHER COMPTON
06/14/2022
Filed — Alteration
INSTALLATION OF (4) COMMERCIAL COOKING APPLIANCES, ASSOCIATED GAS PIPING & ACCESORIES AND EMERGENGY FIRE SUPRESSION VALVE.
X00579316-P1
05/10/2022
Permit issued — Supported Scaffold
X00731580-I1-SF
05/09/2022
Filed — Alteration
PROPOSED INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. WORK SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY, OR EGRESS UNDER THIS APPLICATION.
X00731580-I1
05/04/2022
Special inspection requirement — Final
Sunil Saigal
04/29/2022
Filed — Alteration
X00726824-I1
04/29/2022
Permit issued — Sidewalk Shed
X00726824-I1-SH
04/29/2022
Violation issued (FDNY_NOV, closed)
04/27/2022
Special inspection requirement — Final
Sunil Saigal
04/12/2022
Permit issued — General Construction
X00608536-I1-GC
02/24/2022
Special inspection requirement — Fire-Resistant Penetrations and Joints
Jafet Tavarez
02/24/2022
Special inspection requirement — Maintenance information
Jafet Tavarez
11/04/2021
Permit issued — General Construction
X00608536-I1-GC
11/04/2021
Permit issued — Plumbing
X00579316-I1-PL
10/25/2021
Filed — Alteration
X00608536-I1
10/05/2021
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
08/26/2021
Permit issued — Supported Scaffold
X00574131-I1-SF
08/26/2021
Permit issued — Protection and Mechanical Methods
X00575834-I1-PM
08/25/2021
Filed — Alteration
X00575834-I1
08/25/2021
Filed — Alteration
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER DRAWINGS. PIPE SCAFFOLD SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
X00574131-I1
08/24/2021
Permit issued — Plumbing
X00579316-I1-PL
08/18/2021
Filed — Alteration
INSTALLATION OF (4) COMMERCIAL COOKING APPLIANCES, ASSOCIATED GAS PIPING & ACCESORIES AND EMERGENGY FIRE SUPRESSION VALVE.
X00579316-I1
08/06/2021
Permit issued — Mechanical Systems
X00564249-I1-MS
07/31/2021
Filed — Alteration
INSTALLATION OF A NEW TYPE I KITCHEN HOOD, (1)GREASE EXHAUST FAN AND (1) NON-HEATED MAKE-UP AIR UNIT.
X00564249-I1
07/31/2021
Filed — Alteration
X00564525-I1
05/11/2021
Violation issued (ECB, closed)
Construction
02/24/2020
Signed off — Alteration
Replace and install new gas piping lines to Indoor Gas fired Duct Heaters as shown on drawings filed herewith.
X00266150-I1
01/08/2020
Permit issued — Plumbing
X00266150-I1-PL
11/29/2019
Objection raised — Other
Latest 60 of 132 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSupported ScaffoldSigned-offROCKLEDGE SCAFFOLD CORP08/24/2022
DOB NOWProtection and Mechanical MethodsSigned-offROCKLEDGE SCAFFOLD CORP08/24/2022
DOB NOWSupported ScaffoldSigned-offJASCO, INC05/10/2022
DOB NOWSidewalk ShedSigned-offJASCO, INC04/29/2022
DOB NOWGeneral ConstructionSigned-offDELUXE CONSTRUCTION04/12/2022
DOB NOWGeneral ConstructionSigned-offM. MELNICK & COMPANY INC11/04/2021
DOB NOWPlumbingSigned-offSAMUEL & SONS P & H INC11/04/2021
DOB NOWSupported ScaffoldSigned-offROCKLEDGE SCAFFOLD CORP08/26/2021
DOB NOWProtection and Mechanical MethodsSigned-offROCKLEDGE SCAFFOLD CORP08/26/2021
DOB NOWPlumbingSigned-offSAMUEL & SONS P & H INC08/24/2021
DOB NOWMechanical SystemsSigned-offJ. SIBAJA KITCHEN AND VE*08/06/2021
DOB NOWPlumbingSigned-offL.L.G. PLBG & HTG INC01/08/2020
DOB NOWMechanical SystemsPermit IssuedTHE ELITE GROUP OF NYC11/21/2019
BIS—ISSUEDMUNICIPAL BUILDING CONSULTANTS02/20/2003
BISEQISSUEDCOLGATE SCAFFOLDING01/31/1994
1 project · most recent 10/30/2019
Air Conditioning Systems Heating Systems
FiledStatusContractorScopeMake / Model / Capacity
10/30/2019Permit IssuedTHE ELITE GROUP OF NYC INAir Conditioning Systems, Heating Systems
Cooling
Trane ×2
Heating
Trane ×5
1 project · most recent 08/21/2022
Gas
FiledStatusContractorScope
08/21/2022Signed-offSAMUEL & SONS P & H INCGas
1 project · most recent 04/28/2022
FiledStatusContractorScope
04/28/2022CompleteRICHARD NEU—
▾Field Inspections (DOB CAP) — 1
DateTypeResultReport
10/05/2021Pass-Final PL - Up to 3 Requested FloorsPassView ↗
▾Special Inspection Requirements (DOB NOW) — 32
DateRequirementInspectorRole
08/22/2022Fire-Resistant Penetrations and JointsJafet Tavarezspecial
08/22/2022Maintenance informationJafet Tavarezenergy_progress
07/12/2022FinalCHRISTOPHER COMPTONprogress
07/12/2022Shutoff dampersCHRISTOPHER COMPTONenergy_progress
07/12/2022Fire-Resistant Penetrations and JointsCHRISTOPHER COMPTONspecial
07/12/2022HVAC-R and service water piping design and insulationCHRISTOPHER COMPTONenergy_progress
07/12/2022Maintenance informationCHRISTOPHER COMPTONenergy_progress
07/12/2022Mechanical SystemsCHRISTOPHER COMPTONspecial
05/04/2022FinalSunil Saigalprogress
04/27/2022FinalSunil Saigalprogress
02/24/2022Fire-Resistant Penetrations and JointsJafet Tavarezspecial
02/24/2022Maintenance informationJafet Tavarezenergy_progress
10/29/2019FinalCHRISTIAN LOZADAprogress
10/29/2019Energy Code Compliance InspectionsCHRISTIAN LOZADAprogress
10/29/2019Electrical motorsCHRISTIAN LOZADAenergy_progress
10/29/2019HVAC insulation and sealing CHRISTIAN LOZADAenergy_progress
10/29/2019HVAC and service water heating equipment CHRISTIAN LOZADAenergy_progress
10/29/2019HVAC and service water heating system controls CHRISTIAN LOZADAenergy_progress
10/29/2019Maintenance informationCHRISTIAN LOZADAenergy_progress
10/29/2019Shutoff dampersCHRISTIAN LOZADAenergy_progress
10/29/2019Mechanical SystemsCHRISTIAN LOZADAspecial
10/29/2019Fire-Resistant Penetrations and JointsCHRISTIAN LOZADAspecial
10/15/2019Fire-Resistant Penetrations and JointsCHRISTIAN LOZADAspecial
10/15/2019FinalCHRISTIAN LOZADAprogress
10/15/2019Energy Code Compliance InspectionsCHRISTIAN LOZADAprogress
Latest 25 of 32.
▾Tenants in the building
TenantSpaceFloorsRenovation projects
Freedom Kipp SchoolEducationFloor 10
Project X00579316 Alteration · Permit Entire · 08/18/2021
Project X00564525 Alteration · Approved · 07/31/2021
Kipp : NYC Public SchoolsEducationFloors 1, 2, Roof
Project X00254805 Alteration · Permit Entire · 10/30/2019
Read from each project’s drawing title blocks and cover sheets and checked twice; a name appears only when it is the occupant, never the owner, landlord or designer.
▾Documents — 72 on file (BIS + DOB NOW)
▸Plans & Drawings14
▸DOB NOWPlans/Sketch11
08/25/2026X00564525-I1Request digital key ↗
08/25/2026X00564249-P1Request digital key ↗
08/25/2026X00564249-I1Request digital key ↗
Showing 3 of 11 on file for this type
▸DOB NOWPlans/Sketch - Mechanical Systems2
08/26/2026X00245951-I1Request digital key ↗
08/15/2026X00254805-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Plumbing1
08/14/2026X00266150-I1Request digital key ↗
▸Seals & Professional Certifications40
▸DOB NOWProgress Inspector Seal & Signature18
08/30/2026X00254805-I1Open ↗
08/30/2026X00254805-I1Open ↗
08/30/2026X00254805-I1Open ↗
Showing 3 of 18 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature14
08/26/2026X00245951-I1Open ↗
08/26/2026X00254805-I1Open ↗
08/25/2026X00564525-I1Open ↗
Showing 3 of 14 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature8
08/30/2026X00254805-I1Open ↗
08/30/2026X00254805-I1Open ↗
08/29/2026X00579316-P1Open ↗
Showing 3 of 8 on file for this type
▸Environmental & Asbestos10
▸DOB NOWDEP ACP-5: Asbestos Assessment Report7
08/25/2026X00564525-I1Open ↗
08/25/2026X00608536-I1Open ↗
08/24/2026X00579316-P1Open ↗
Showing 3 of 7 on file for this type
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form3
08/26/2026X00245951-I1Open ↗
08/26/2026X00254805-I1Open ↗
08/13/2026X00266150-I1Open ↗
▸Energy Compliance1
▸DOB NOWEN2: As Built Energy Analysis.1
08/13/2026X00564249-I1Open ↗
▸Approvals, Objections & Sign-offs7
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter7
08/25/2026X00564525-I1Open ↗
08/13/2026X00579316-I1Open ↗
08/13/2026X00579316-P2Open ↗
Showing 3 of 7 on file for this type