Two family frame
225-16 146 AVENUE
💬 Discuss this project
1997Year Built
2Stories
B2Building Class
R3-1Zoning
1,848 sfGross Floor Area
2Units
0 Open ViolationsFDNY Report ↗
Two family frame · 2,900 sf lot · 0.64 FAR built · Flood zone X500
Locations of Work
Plumbing
Cellar6p · 1 filing · 8 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
DAVID TURNER ARCHITECT PC304/27/2022
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
JUST PLBG & HTG INCPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
DAVID TURNER ARCHITECT PC3829304/27/2022
Building Lifecycle
All (30)Filed (3)Permit Issued (1)Violation (22)Special Inspection (4)
04/28/2022
Special inspection requirement — Fire-Resistant Penetrations and Joints
DAVID TURNER
04/27/2022
Filed — Alteration
Cellar plumbing
Q00551995-P1
04/27/2022
Special inspection requirement — Fire-Resistant Penetrations and Joints
DAVID TURNER
04/26/2022
Filed — Alteration
Cellar plumbing
Q00551995-S1
09/24/2021
Permit issued — Plumbing
Q00551995-I1-PL
07/10/2021
Filed — Alteration
Cellar plumbing
Q00551995-I1
07/03/2021
Special inspection requirement — Fire-Resistant Penetrations and Joints
DAVID TURNER
07/03/2021
Special inspection requirement — Maintenance information
DAVID TURNER
06/21/2021
Violation issued (ECB, closed)
Construction
05/21/2021
Violation issued (ECB, closed)
Construction
04/01/2021
Violation issued (ECB, closed)
Construction
03/09/2021
Violation issued (ECB, closed)
Construction
12/10/2020
Violation issued (ECB, closed)
Construction
12/03/2020
Violation issued (ECB, closed)
Construction
09/24/2020
Violation issued (ECB, closed)
Construction
09/24/2020
Violation issued (ECB, closed)
Construction
02/11/2020
Violation issued (ECB, closed)
Construction
02/11/2020
Violation issued (ECB, closed)
Construction
12/07/2019
Violation issued (ECB, closed)
Construction
12/07/2019
Violation issued (ECB, closed)
Construction
10/05/2019
Violation issued (ECB, closed)
Construction
10/04/2019
Violation issued (ECB, closed)
Construction
08/15/2019
Violation issued (ECB, closed)
Construction
08/15/2019
Violation issued (ECB, closed)
Construction
05/29/2019
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
05/29/2019
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
05/20/2019
Violation issued (ECB, closed)
Construction
05/20/2019
Violation issued (ECB, closed)
Construction
03/04/2019
Violation issued (ECB, closed)
Construction
03/04/2019
Violation issued (ECB, closed)
Construction
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingPermit IssuedMOHAMED ABDELRAZEK09/24/2021
BISOTISSUEDN/A07/30/2021
BISOTISSUEDSUNRUN INSTALLATION SVC02/25/2019
BISPLISSUEDACCURATE MECHANICAL INC04/18/1997
BISEQISSUEDNA03/11/1997
BIS—ISSUEDNA03/11/1997
1 project · most recent 04/27/2022
Water/Sanitary
FiledStatusContractorScope
04/27/2022Permit IssuedAMM GEN'L CONTRACTING INCWater/Sanitary
1 project · most recent 02/26/2019
FiledStatusContractorScope
02/26/2019CompleteSUNRUN SOLAR ELECTL CORP—
▾Special Inspection Requirements (DOB NOW) — 4
DateRequirementInspectorRole
04/28/2022Fire-Resistant Penetrations and JointsDAVID TURNERspecial
04/27/2022Fire-Resistant Penetrations and JointsDAVID TURNERspecial
07/03/2021Fire-Resistant Penetrations and JointsDAVID TURNERspecial
07/03/2021Maintenance informationDAVID TURNERenergy_progress
▾Documents — 54 on file (BIS + DOB NOW)
▸Plans & Drawings3
▸DOB NOWPlans/Sketch3
08/26/2026Q00551995-I1Request digital key ↗
08/26/2026Q00551995-P1Request digital key ↗
08/26/2026Q00551995-S1Request digital key ↗
▸Applications & Permits7
▸BISPLAN / WORK APPROVAL APPLICATION4
04/28/2021440657228Open ↗
01/07/2021440657228Open ↗
06/26/2019421921442Open ↗
Showing 3 of 4 on file for this type
▸BISWORK PERMIT APPLICATION3
09/13/2021440657228Open ↗
06/26/2019421921442Open ↗
02/19/2019440536172Open ↗
▸Zoning, Tax Lot & Property Records1
▸BISRESTRICTION: RESTRICTIVE DECLARATION1
06/26/2019421921442Open ↗
▸Seals & Professional Certifications11
▸DOB NOWDPL-1: Design Professional Seal & Signature3
08/13/2026Q00551995-I1Open ↗
08/13/2026Q00551995-P1Open ↗
08/13/2026Q00551995-S1Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY2
01/07/2021440657228Open ↗
02/19/2019440536172Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT1
02/19/2019440536172Open ↗
▸BISAPPLICANT OWNER SIGNATURE1
01/07/2021440657228Open ↗
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION1
06/26/2019421921442Open ↗
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION1
02/19/2019440536172Open ↗
▸DOB NOWProgress Inspector Seal & Signature1
08/29/2026Q00551995-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature1
08/29/2026Q00551995-I1Open ↗
▸Trade Schedules & Equipment1
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE1
06/26/2019421921442Open ↗
▸Safety & Tenant Protection2
▸BISTENANT PROTECTION PLAN AND NOTES2
02/19/2019440536172Open ↗
06/26/2019421921442Open ↗
▸Environmental & Asbestos1
▸BISASBESTOS: CERTIFICATION (DEP ACP5)1
06/26/2019421921442Open ↗
▸Energy Compliance10
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY3
06/21/2021440657228Open ↗
04/23/2019440536172Open ↗
02/19/2019440536172Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS2
01/07/2021440657228Open ↗
02/19/2019440536172Open ↗
▸BISNYCECC ANALYSIS1
02/19/2019440536172Open ↗
▸BISPTA4: SOLAR TAX ABATEMENT APPLICATION (PRELIMINARY)1
02/19/2019440536172Open ↗
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS1
06/26/2019421921442Open ↗
▸BISAS-BUILT ENERGY ANALYSIS1
04/23/2019440536172Open ↗
▸BISSOLAR TAX ABATEMENT APPLICATION1
04/23/2019440536172Open ↗
▸Inspections & Test Reports3
▸BISTECHNICAL REPORT: RESPONSIBILITY2
04/23/2019440536172Open ↗
02/19/2019440536172Open ↗
▸BISDIR-14 ID OF RESPONSIBILITY (TR1)1
07/21/2021440657228Open ↗
▸Approvals, Objections & Sign-offs5
▸BISLETTERS - SUPPORTING DOCUMENTATION2
04/23/2019440536172Open ↗
02/19/2019440536172Open ↗
▸BISFINAL1
06/28/2021440657228Open ↗
▸BISUtility Company PV System Interconnection Acknowledgement Letter1
04/23/2019440536172Open ↗
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST1
04/23/2019440536172Open ↗
▸Cost, Insurance & Ownership5
▸BISCOST AFFIDAVIT4
01/07/2021440657228Open ↗
06/26/2019421921442Open ↗
04/23/2019440536172Open ↗
Showing 3 of 4 on file for this type
▸BISWC-DB-100 (Replaces Form C-105-21)Affidavit for NY Entities And Any Out of State Entities with no employees1
06/28/2021440657228Open ↗
▸Filing & Intake Forms5
▸BISEFILING JOB APPLICATION COVER SHEET2
01/07/2021440657228Open ↗
02/19/2019440536172Open ↗
▸BISADDITIONAL INFORMATION2
06/02/2021440657228Open ↗
05/04/2021440657228Open ↗
▸BISEFILING COVER SHEET1
06/26/2019421921442Open ↗