← Back
Two family frame
225 CONKLIN AVENUE
BROOKLYN · BIN 3229710
💬 Discuss this project
1925Year Built
2Stories
B2Building Class
R4-1Zoning
2,200 sfGross Floor Area
2Units
1 Open Violation ▸FDNY Report ↗
Two family frame · 2,750 sf lot · 0.8 FAR built · Flood zone X
Locations of Work
Plumbing
Floor 21p · 1 filing · 6 docs
Floor 1
Cellar4p · 1 filing · 6 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
OMFPE CONSULTING PLLC207/18/2022
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
CITY CONSULTANT ENGINEERING403/21/2026
Building Lifecycle
All (13)Filed (2)Violation (1)Objection (2)Special Inspection (8)
08/03/2022
Special inspection requirement — Maintenance information
08/03/2022
Special inspection requirement — Fire-Resistant Penetrations and Joints
08/03/2022
Special inspection requirement — Energy Code Compliance Inspections
08/03/2022
Special inspection requirement — HVAC-R and service water piping design and insulation
07/29/2022
Objection resolved — Addressed
07/23/2022
Objection raised — Other
07/18/2022
Filed — Alteration
REMOVE ONE (1) EXISTING WATER HEATER SERVING 2 RESIDENTIAL APARTMENTS. PROVIDE 2 NEW WATER HEATERS, ONE TO SERVE FIRST FLOOR APARTMENT AND THE OTHER TO SERVE SECOND FLOOR APARTMENT, RESPECTIVELY
B00577803-P1
07/15/2022
Special inspection requirement — Fire-Resistant Penetrations and Joints
07/15/2022
Special inspection requirement — Energy Code Compliance Inspections
07/15/2022
Special inspection requirement — HVAC-R and service water piping design and insulation
07/15/2022
Special inspection requirement — Maintenance information
09/12/2021
Filed — Alteration
REMOVE ONE (1) EXISTING WATER HEATER SERVING 2 RESIDENTIAL APARTMENTS. PROVIDE 2 NEW WATER HEATERS, ONE TO SERVE FIRST FLOOR APARTMENT AND THE OTHER TO SERVE SECOND FLOOR APARTMENT, RESPECTIVELY
B00577803-I1
12/30/2017
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
Nothing on file for this building.
1 project · most recent 07/18/2022
Gas
FiledStatusContractorScope
07/18/2022——Gas
▾Special Inspection Requirements (DOB NOW) — 8
DateRequirementInspectorRole
08/03/2022Maintenance information—energy_progress
08/03/2022Fire-Resistant Penetrations and Joints—special
08/03/2022Energy Code Compliance Inspections—progress
08/03/2022HVAC-R and service water piping design and insulation—energy_progress
07/15/2022Fire-Resistant Penetrations and Joints—special
07/15/2022Energy Code Compliance Inspections—progress
07/15/2022HVAC-R and service water piping design and insulation—energy_progress
07/15/2022Maintenance information—energy_progress
▾Documents — 6 on file (BIS + DOB NOW)
▸Plans & Drawings2
▸DOB NOWPlans/Sketch2
09/01/2026B00577803-I1Request digital key ↗
08/15/2026B00577803-P1Request digital key ↗
▸Seals & Professional Certifications2
▸DOB NOWDPL-1: Design Professional Seal & Signature2
09/01/2026B00577803-P1Open ↗
09/01/2026B00577803-I1Open ↗
▸Environmental & Asbestos2
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
09/01/2026B00577803-I1Open ↗
08/15/2026B00577803-P1Open ↗