← Back
Public elementary, junior or senior high
I.S. 24 Myra S. Barnes
225 DURANT AVENUE · BIN 5065854
💬 Discuss this project
1971Year Built
4Stories
W1Building Class
R3AZoning
505,000 sfGross Floor Area
1Units
18 Open Violations 0 unresolved · 18 paperwork only ▸FDNY Report ↗
Public elementary, junior or senior high · Owner of record: NYC DEPARTMENT OF EDUCATION · 165,000 sf lot · 3.06 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbingGeneralOther
Roof11p · 2 filings · 20 docs
Bulkhead1p · 1 filing · 16 docs
Floor 425p · 2 filings · 20 docs
Floor 33p · 1 filing · 15 docs
Floor 24p · 2 filings · 20 docs
Floor 13p · 3 filings · 20 docs
Cellar4p · 2 filings · 20 docs
Sub-Cellar1p · 1 filing · 20 docs
5 jobs · most recent 07/02/2026
Air Conditioning Systems Ventilation Systems Associated Ducts and Piping
FiledStatusContractorScopeMake / Model / Capacity
07/02/2026——Ventilation Systems—
06/15/2026——Air Conditioning Systems
Cooling
Lg LG ZRNU363SRAA 35,000 BTU · Vrf Indoor ×6
LG ZRUM121BTE6 119,700 BTU · Vrf Outdoor ×2
06/02/2026——Ventilation Systems
Ventilation
Titus 350RL 300 CFM · Exhaust Fan ×2
01/15/2026——Air Conditioning Systems
Cooling
Mitsubishi Electric TPKA0A0181LA10A 18,000 BTU · Vrf Indoor ×1
TPKA0A0241KA80A 24,000 BTU · Vrf Indoor ×1
TRUYA0181HA70NA 18,000 BTU · Vrf Outdoor ×1
TRUYA0241HA70NA 24,000 BTU · Split System ×1
05/19/2025Signed-offZIAUR BHUIYANAir Conditioning Systems, Associated Ducts and Piping
Cooling
Mitsubishi Electric PUY-A24NHA4 24 BTU · Split System ×1
Ducts & Piping
Mitsubishi Electric PKA-A24KA4 1 tons · Vrf Indoor ×1
4 jobs · most recent 07/02/2026
Water/Sanitary Storm
FiledStatusContractorScope
07/02/2026——Water/Sanitary
06/02/2026——Water/Sanitary
01/15/2026——Storm
05/19/2025Signed-offMAR-SAL PLBG & HTG, INCStorm, Water/Sanitary
23 jobs · most recent 07/24/2026
General Wiring Lighting
FiledStatusContractorScope
07/24/2026Permit IssuedA & S ELECTRIC INC.General Wiring
11/06/2025CompleteURBAN ELECTRICAL CORPGeneral Wiring
06/23/2025CompleteCANDELA SYSTEMS CORP DBALighting
06/16/2025CompleteGEMINI ELECTRIC CO., INC.—
01/29/2024CompleteRICHARD NEU—
07/12/2023CompleteGEMINI ELECTRIC CO., INC.—
10/21/2022CompleteGEMINI ELECTRIC CO., INC.—
05/19/2022CompleteMNBC ELECTRICAL CORPGeneral Wiring
01/10/2022CompleteKLK ELECTRIC, INCGeneral Wiring, Lighting
10/04/2021Permit IssuedGEMINI ELECTRIC CO., INC.General Wiring
05/07/2021CompleteCHARAN ELEC'L ENTERP'S IN—
05/04/2021Permit IssuedGEMINI ELECTRIC CO., INC.General Wiring
09/30/2020CompleteCHARAN ELEC'L ENTERP'S IN—
08/25/2020CompleteANCO ELECTL CONTCTNG INCGeneral Wiring
06/09/2020Permit IssuedA & S ELECTRIC INC.General Wiring
2 jobs · most recent 01/15/2026
Masonry Concrete
FiledStatusContractorScope
01/15/2026——Concrete, Masonry
05/19/2025Signed-offZIAUR BHUIYANMasonry
Building Lifecycle
All (172)Filed (22)Permit Issued (16)Signed Off (8)Violation (60)Inspection (1)Objection (35)Special Inspection (30)
09/14/2026
Objection resolved — Open
08/21/2026
Special inspection requirement — Energy Code Compliance Inspections
08/21/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
08/21/2026
Special inspection requirement — Energy Code Compliance Inspections
08/17/2026
Objection raised — Other
08/10/2026
Filed — Alteration
R024_ CTF_ Path of Travel work is limited to the door replacement in the unisex toilet room #234. No change in use, egress, or occupancy is proposed under this application.
S01441750-I1
08/07/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
08/07/2026
Special inspection requirement — Fire-Resistance Rated Construction
08/05/2026
Objection resolved — Addressed
07/28/2026
Objection resolved — Addressed
07/28/2026
Objection resolved — Resolved
07/28/2026
Objection resolved — Resolved
07/28/2026
Special inspection requirement — Interior lighting power
07/28/2026
Special inspection requirement — Maintenance information
07/28/2026
Special inspection requirement — Lighting controls
07/21/2026
Signed off — Alteration
Re-install two existing HVAC rooftop units on new support systems and made modifications to associated ductwork/piping systems.
S07994898-S2
07/15/2026
Objection raised — Other
07/15/2026
Objection raised — Other
07/15/2026
Objection raised — Other
07/15/2026
Objection raised — Other
07/07/2026
Objection resolved — Resolved
07/07/2026
Objection resolved — Addressed
07/06/2026
Signed off — Alteration
Re-install two existing HVAC rooftop units on new support systems and made modifications to associated ductwork/piping systems.
S07994898-I1
07/06/2026
Signed off — Alteration
Re-install two existing HVAC rooftop units on new support systems and made modifications to associated ductwork/piping systems.
S07994898-S1
07/02/2026
Filed — Alteration
remove 6 sinks, including associated plumbing piping and valves for room 211. remove 36 sinks and 4 eye wash stations with associated plumbing piping/valves for room 419,421,426 & 428.
S01419829-S2
07/02/2026
Filed — Alteration
remove 6 sinks, including associated plumbing piping and valves for room 211. remove 36 sinks and 4 eye wash stations with associated plumbing piping/valves for room 419,421,426 & 428.
S01419829-S1
07/02/2026
Filed — Alteration
remove 6 sinks, including associated plumbing piping and valves for room 211. remove 36 sinks and 4 eye wash stations with associated plumbing piping/valves for room 419,421,426 & 428.
S01419829-S3
07/02/2026
Special inspection requirement — Final
07/02/2026
Special inspection requirement — Post-installed Anchors
07/02/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
07/02/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
06/30/2026
Filed — Alteration
remove 6 sinks, including associated plumbing piping and valves for room 211. remove 36 sinks and 4 eye wash stations with associated plumbing piping/valves for room 419,421,426 & 428.
S01419829-I1
06/29/2026
Objection raised — Scope
06/29/2026
Objection raised — Other
06/24/2026
Special inspection requirement — Mechanical Systems
06/24/2026
Special inspection requirement — Final
06/22/2026
Special inspection requirement — Fire-Resistance Rated Construction
06/22/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
06/15/2026
Filed — Alteration
THE SCOPE OF WORK INCLUDES ALL LABOR, MATERIALS, AND EQUIPMENT NECESSARY TO COMPLETE INSTALLATION OF THE SUPPLEMENTAL COOLING SYSTEM IN THE 1ST FLOOR KITCHEN AND SERVING LINE.
S01393775-I1
06/10/2026
Objection raised — Other
06/09/2026
Objection raised — Other
06/09/2026
Objection raised — Other
06/02/2026
Filed — Alteration
IS24R:General construction propose renovation & upgrade of existing science room, including removal of perimeter cabinetry; new furniture, demo tables; new flooring; and new closets. No change in use, egress, or occupancy. All as per plans filed herewith.
S01393262-S1
06/02/2026
Filed — Alteration
IS24R:General construction propose renovation & upgrade of existing science room, including removal of perimeter cabinetry; new furniture, demo tables; new flooring; and new closets. No change in use, egress, or occupancy. All as per plans filed herewith.
S01393262-S3
06/02/2026
Filed — Alteration
IS24R:General construction propose renovation & upgrade of existing science room, including removal of perimeter cabinetry; new furniture, demo tables; new flooring; and new closets. No change in use, egress, or occupancy. All as per plans filed herewith.
S01393262-I1
05/07/2026
Special inspection requirement — Interior lighting power
05/07/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
05/07/2026
Special inspection requirement — Mechanical Systems
05/07/2026
Special inspection requirement — Smoke Control Systems Testing
05/07/2026
Special inspection requirement — Final
05/07/2026
Special inspection requirement — Maintenance information
05/07/2026
Special inspection requirement — Lighting controls
04/28/2026
Signed off — Alteration
ST/PS24R FOR REPAIR OF DAMAGED FOUNDATION WALL CORNER IN CRAWL SPACE, SUBMITTING ON BEHALF OF CONTRACTOR. IN CONJUNCTION WITH S07994898 NO CHANGE IN USE, OCCUPANCY OR EGRESS
S01167010-I1
04/28/2026
Special inspection requirement — HVAC-R and service water heating system controls
Asma Hashmi
04/28/2026
Special inspection requirement — HVAC-R and service water heating equipment
Asma Hashmi
04/28/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
Asma Hashmi
04/28/2026
Special inspection requirement — Energy Code Compliance Inspections
Asma Hashmi
04/28/2026
Special inspection requirement — Final
Asma Hashmi
04/28/2026
Special inspection requirement — Post-installed Anchors
Asma Hashmi
04/28/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Asma Hashmi
Latest 60 of 172 events.
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
NYC SCHOOL CONSTRUCTION AUTHORITY5209/13/2026
NYC DEPARTMENT OF EDUCATION103/22/2026
DOE IS 241703/22/2026
DEPARTMENT OF EDUCATION803/22/2026
D.O.E. 0203/22/2026
D.O.E 1 04103/22/2026
DOE IS 24 040903/22/2026
DEPT OF EDU 1203/22/2026
DEPT OF EDUCATION IS 24203/22/2026
IS24 DOE 040103/22/2026
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
LGML GROUP503/21/2026
NYC SCHOOL CONSTRUCTION AUTHORITY303/21/2026
AK CONSULTING SERVICES603/21/2026
DSENY ENGINEERING SERVICES403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
ZIAUR BHUIYANGeneral Contractor1907/08/2026
CHAPMAN & EVANS INCGeneral Contractor204/09/2026
ANCO ELECTL CONTCTNG INCElectrical203/22/2026
MAR-SAL PLBG & HTG, INCPlumbing107/05/2026
MNBC ELECTRICAL CORPElectrical103/22/2026
FRANCIS RICHARDSElectrical103/21/2026
GEMINI ELECTRIC CO., INC.Electrical103/22/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
JPC LOGISTICS DBA JPCL EN351106/15/2026
TWIN PEAKS INC.317201/15/2026
MUNICIPAL TESTING LABORAT230502/06/2025
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWStructuralSigned-offZIAUR BHUIYAN06/20/2025
DOB NOWProtection and Mechanical MethodsSigned-offZIAUR BHUIYAN05/29/2025
DOB NOWStructuralSigned-offZIAUR BHUIYAN05/29/2025
DOB NOWMechanical SystemsSigned-offCHAPMAN EVANS01/08/2025
DOB NOWGeneral ConstructionSigned-offZIAUR BHUIYAN11/29/2024
DOB NOWSupported ScaffoldSigned-offZIAUR BHUIYAN11/27/2024
DOB NOWSidewalk ShedSigned-offZIAUR BHUIYAN11/27/2024
DOB NOWConstruction FenceSigned-offZIAUR BHUIYAN11/27/2024
DOB NOWStructuralSigned-offZIAUR BHUIYAN11/27/2024
DOB NOWPlumbingSigned-offMAR-SAL PLBG & HTG, INC03/13/2024
DOB NOWMechanical SystemsSigned-offCHAPMAN EVANS02/07/2024
DOB NOWGeneral ConstructionSigned-offZIAUR BHUIYAN02/05/2024
DOB NOWGeneral ConstructionSigned-offZIAUR BHUIYAN02/05/2024
DOB NOWSupported ScaffoldSigned-offZIAUR BHUIYAN01/31/2024
DOB NOWSidewalk ShedSigned-offZIAUR BHUIYAN01/30/2024
DOB NOWConstruction FenceSigned-offZIAUR BHUIYAN01/26/2024
BISOTISSUEDARCHINOVA BUILDERS LLC03/26/2024
BISOTISSUED2 SAAB CONSTRUCTION INC10/25/2023
BISPLISSUEDMAR-SAL PLBG & HTG, INC07/20/2023
BISOTISSUEDFIRST CONSTRUCTION GROUP07/20/2023
BISOTISSUED2 SAAB CONSTRUCTION INC04/28/2023
BISOTISSUED2 SAAB CONSTRUCTION INC04/28/2023
BISOTISSUEDARCHINOVA BUILDERS LLC03/21/2023
BISOTISSUED2 SAAB CONSTRUCTION INC08/19/2022
BISOTISSUED2 SAAB CONSTRUCTION INC08/19/2022
BISOTISSUED2 SAAB CONSTRUCTION INC08/18/2022
BISPLISSUEDMAR-SAL PLBG & HTG, INC06/16/2022
BISOTISSUEDARCHINOVA BUILDERS LLC06/09/2022
BISOTISSUEDFIRST CONSTRUCTION GROUP02/24/2022
BISOTISSUED2 SAAB CONSTRUCTION INC12/03/2021
BISOTISSUED2 SAAB CONSTRUCTION INC12/03/2021
BISPLISSUEDMAR-SAL PLBG & HTG, INC04/02/2021
BISOTISSUED2 SAAB CONSTRUCTION INC01/07/2021
BISOTISSUED2 SAAB CONSTRUCTION INC12/21/2020
BISOTISSUED2 SAAB CONSTRUCTION INC12/21/2020
BISOTISSUED2 SAAB CONSTRUCTION INC10/16/2020
BISOTISSUED2 SAAB CONSTRUCTION INC10/16/2020
BISOTISSUEDFLORACON LLC11/13/2019
BISOTISSUED2 SAAB CONSTRUCTION INC09/24/2019
BISOTISSUED2 SAAB CONSTRUCTION INC09/24/2019
+ 26 more permits on file
▾Field Inspections (DOB CAP) — 1
DateTypeResultReport
02/10/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
▾Special Inspection Requirements (DOB NOW) — 57
DateRequirementInspectorRole
08/21/2026Energy Code Compliance Inspections—progress
08/21/2026HVAC-R and service water piping design and insulation—energy_progress
08/21/2026Energy Code Compliance Inspections—progress
08/07/2026Fire-Resistant Penetrations and Joints—special
08/07/2026Fire-Resistance Rated Construction—progress
07/28/2026Interior lighting power—energy_progress
07/28/2026Maintenance information—energy_progress
07/28/2026Lighting controls—energy_progress
07/02/2026Final—progress
07/02/2026Post-installed Anchors—special
07/02/2026Fire-Resistant Penetrations and Joints—special
07/02/2026Fire-Resistant Penetrations and Joints—special
06/24/2026Mechanical Systems—special
06/24/2026Final—progress
06/22/2026Fire-Resistance Rated Construction—progress
06/22/2026Fire-Resistant Penetrations and Joints—special
05/07/2026Interior lighting power—energy_progress
05/07/2026Fire-Resistant Penetrations and Joints—special
05/07/2026Mechanical Systems—special
05/07/2026Smoke Control Systems Testing—special
05/07/2026Final—progress
05/07/2026Maintenance information—energy_progress
05/07/2026Lighting controls—energy_progress
04/28/2026HVAC-R and service water heating system controlsAsma Hashmienergy_progress
04/28/2026HVAC-R and service water heating equipmentAsma Hashmienergy_progress
Latest 25 of 57.
▾Documents — 159 on file (BIS + DOB NOW)
▸Plans & Drawings16
▸DOB NOWPlans/Sketch16
08/20/2026S01167010-I1Request digital key ↗
08/20/2026S01167010-S1Request digital key ↗
08/19/2026S07994898-P2Request digital key ↗
Showing 3 of 16 on file for this type
▸Applications & Permits4
▸BISWORK PERMIT APPLICATION2
07/31/2009520013226Open ↗
07/31/2009520013226Open ↗
▸BISPLAN / WORK APPROVAL APPLICATION1
07/28/2009520013226Open ↗
▸BISAFTER-HOUR WORK PERMIT APPLICATION1
08/05/2009520013226Open ↗
▸Seals & Professional Certifications34
▸DOB NOWDPL-1: Design Professional Seal & Signature19
08/19/2026S07994898-P2Open ↗
08/19/2026S07994898-P1Open ↗
08/19/2026S07994898-S2Open ↗
Showing 3 of 19 on file for this type
▸DOB NOWProgress Inspector Seal & Signature7
09/28/2026S07994898-S1Open ↗
09/28/2026S07994898-S1Open ↗
08/29/2026S01167010-I1Open ↗
Showing 3 of 7 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature4
09/28/2026S07994898-S1Open ↗
08/29/2026S01167010-I1Open ↗
08/28/2026S07994898-P1Open ↗
Showing 3 of 4 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION2
01/18/2012520013226Open ↗
07/28/2009520013226Open ↗
▸BISPROFESSIONAL CERTIFIED CHECKLIST1
07/28/2009520013226Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM1
07/28/2009520013226Open ↗
▸Safety & Tenant Protection3
▸DOB NOWNYCSCA - Approved Site Safety Plans3
08/13/2026S00954278-I1Open ↗
08/13/2026S00954281-I1Open ↗
08/13/2026S00954285-I1Open ↗
▸Environmental & Asbestos5
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form3
08/19/2026S07994898-S1Open ↗
08/19/2026S07994898-S2Open ↗
08/14/2026S07994898-I1Open ↗
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER1
07/28/2009520013226Open ↗
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/13/2026S01167010-I1Open ↗
▸Energy Compliance1
▸DOB NOWEN2: As Built Energy Analysis1
08/14/2026S07994898-I1Open ↗
▸Approvals, Objections & Sign-offs54
▸DOB NOWDesign Commission Approval City Owned (Exterior Work)21
08/16/2026S01441750-I1Open ↗
08/15/2026S01419829-S1Open ↗
08/15/2026S01419829-S3Open ↗
Showing 3 of 21 on file for this type
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter16
08/16/2026S01441750-I1Open ↗
08/15/2026S01419829-S1Open ↗
08/15/2026S01419829-S3Open ↗
Showing 3 of 16 on file for this type
▸DOB NOWDesign Commission Sign Off City Owned (Exterior Work)11
08/20/2026S01167010-S1Open ↗
08/20/2026S01167010-I1Open ↗
08/13/2026S01346117-S2Open ↗
Showing 3 of 11 on file for this type
▸DOB NOWDEP Variance (V5) letter3
08/13/2026S07994898-S2Open ↗
08/13/2026S07994898-S1Open ↗
08/13/2026S07994898-I1Open ↗
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST2
08/18/2011520013226Open ↗
01/06/2010520013226Open ↗
▸BISADMINISTRATIVE OBJECTIONS1
07/28/2009520013226Open ↗
▸Cost, Insurance & Ownership2
▸BISCOST AFFIDAVIT2
01/18/2012520013226Open ↗
07/28/2009520013226Open ↗
▸Filing & Intake Forms3
▸BISADDITIONAL INFORMATION2
01/19/2012520013226Open ↗
07/28/2009520013226Open ↗
▸BISEFILING COVER SHEET1
07/28/2009520013226Open ↗
▸Other Documents37
▸DOB NOWNYCSCA - BCC Plan Examination Transmittal21
08/16/2026S01441750-I1Open ↗
08/15/2026S01419829-S1Open ↗
08/15/2026S01419829-S3Open ↗
Showing 3 of 21 on file for this type
▸DOB NOWNYCSCA Exhibit 28
08/20/2026S01167010-I1Open ↗
08/20/2026S01167010-S1Open ↗
08/19/2026S07994898-S2Open ↗
Showing 3 of 8 on file for this type
▸DOB NOWFee Exempt Supporting Document - DOF Property Tax Assessment Roll5
08/13/2026S00954285-I1Open ↗
08/13/2026S00954278-I1Open ↗
08/13/2026S01346117-S2Open ↗
Showing 3 of 5 on file for this type
▸BISPLOT DIAGRAM1
07/28/2009520013226Open ↗
▸DOB NOWWaiver Document1
08/13/2026S07994898-S2Open ↗
▸DOB NOWProof of Historic Building1
08/13/2026S01346117-I1Open ↗