Walk-up apt, over six families with stores · Owner of record: CITYWIDE PRESERVATION LLC · 3,120 sf lot · 5.05 FAR built · Flood zone X
Locations of Work
Plumbing
Floor 11p · 1 filing · 19 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
CHATSWORTH BUILDERS807/08/2026
CITYWIDE PREVESERVATION LLC403/22/2026
MN-13 ASSOCIATES803/21/2026
MN-13C ASSOCIATES103/21/2026
PWB CONSTRUCTION103/21/2026
2252 5 AVE DELI GROCERY103/21/2026
LMN203/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
A.S.III DESIGN STUDIO310/21/2021
PETER ROSEN, PE212/16/2019
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
W J PROFESSIONAL EXPEDITING COMPANY403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
L & M BUILDERS GROUP LLCGeneral Contractor203/21/2026
G.B. & SON, INCPlumbing207/08/2026
LACLAIR, KEVINElectrical103/21/2026
N Y WATER MAIN & SEWER SEElectrical103/21/2026
CHETRAM, RISHIRAMElectrical103/21/2026
WAYDE GILSTONElectrical103/21/2026
A.GOLDNER INCPlumbing107/08/2026
QUINTANA, DAVIDElectrical103/21/2026
KHAIT, SElectrical103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
M. HAMDI GUNAL, PE, P.C.3000310/21/2021
RICHMOND TESTING LAB263112/16/2019
Building Lifecycle
All (78)Filed (5)Permit Issued (4)Signed Off (3)Violation (60)Special Inspection (6)
04/29/2026
Violation issued (HPD, open)
A
04/18/2026
Violation issued (HPD, open)
B
04/18/2026
Violation issued (HPD, open)
B
04/18/2026
Violation issued (HPD, open)
B
04/18/2026
Violation issued (HPD, open)
A
04/18/2026
Violation issued (HPD, open)
B
04/18/2026
Violation issued (HPD, open)
B
11/12/2025
Violation issued (HPD, closed)
C
11/12/2025
Violation issued (HPD, open)
A
08/26/2025
Violation issued (HPD, open)
A
08/26/2025
Violation issued (HPD, open)
B
08/26/2025
Violation issued (HPD, open)
B
08/26/2025
Violation issued (HPD, open)
B
08/26/2025
Violation issued (HPD, open)
C
08/30/2024
Violation issued (HPD, open)
B
08/30/2024
Violation issued (HPD, closed)
A
08/30/2024
Violation issued (HPD, open)
B
08/30/2024
Violation issued (HPD, open)
B
08/30/2024
Violation issued (HPD, open)
C
08/30/2024
Violation issued (HPD, open)
A
08/30/2024
Violation issued (HPD, open)
B
08/30/2024
Violation issued (HPD, open)
A
08/30/2024
Violation issued (HPD, open)
C
08/30/2024
Violation issued (HPD, open)
B
08/30/2024
Violation issued (HPD, open)
B
08/30/2024
Violation issued (HPD, open)
C
08/30/2024
Violation issued (HPD, open)
B
08/12/2024
Violation issued (HPD, open)
A
08/12/2024
Violation issued (HPD, open)
C
06/26/2023
Signed off — Alteration
INSTALL NEW GAS METER IN CELLAR METER ROOM AND REPLACE EXISTING 2" GAS PIPE TO 1ST FLOOR COMMERCIAL SPACE WITH NEW 2" GAS PIPE.
M00429585-I1
04/27/2023
Violation issued (HPD, open)
A
04/27/2023
Violation issued (HPD, open)
C
10/11/2022
Violation issued (HPD, open)
B
10/11/2022
Violation issued (HPD, open)
A
10/11/2022
Violation issued (HPD, open)
B
10/11/2022
Violation issued (HPD, open)
B
10/11/2022
Violation issued (HPD, closed)
A
10/11/2022
Violation issued (HPD, open)
B
10/11/2022
Violation issued (HPD, open)
B
10/11/2022
Violation issued (HPD, open)
B
06/10/2022
Violation issued (HPD, closed)
B
06/10/2022
Violation issued (HPD, open)
A
06/10/2022
Violation issued (HPD, closed)
B
06/10/2022
Violation issued (HPD, closed)
A
06/10/2022
Violation issued (HPD, closed)
B
06/10/2022
Violation issued (HPD, closed)
B
06/10/2022
Violation issued (HPD, closed)
B
06/10/2022
Violation issued (HPD, closed)
B
06/10/2022
Violation issued (HPD, closed)
B
11/18/2021
Permit issued — Plumbing
M00429585-I1-PL
10/22/2021
Special inspection requirement — Fire-Resistant Penetrations and Joints
Mehmet Gunal
10/22/2021
Special inspection requirement — Fire-Resistance Rated Construction
Mehmet Gunal
10/22/2021
Special inspection requirement — Energy Code Compliance Inspections
Mehmet Gunal
10/21/2021
Filed — Alteration
INSTALL NEW GAS METER IN CELLAR METER ROOM AND REPLACE EXISTING 2" GAS PIPE TO 1ST FLOOR COMMERCIAL SPACE WITH NEW 2" GAS PIPE.
M00429585-P2
10/21/2021
Special inspection requirement — Fire-Resistant Penetrations and Joints
Mehmet Gunal
10/21/2021
Special inspection requirement — Energy Code Compliance Inspections
Mehmet Gunal
10/21/2021
Special inspection requirement — Fire-Resistance Rated Construction
Mehmet Gunal
08/10/2021
Filed — Alteration
INSTALL NEW GAS METER IN CELLAR METER ROOM AND REPLACE EXISTING 2" GAS PIPE TO 1ST FLOOR COMMERCIAL SPACE WITH NEW 2" GAS PIPE.
M00429585-P1
02/12/2021
Permit issued — Plumbing
M00429585-I1-PL
11/30/2020
Filed — Alteration
INSTALL NEW GAS METER IN CELLAR METER ROOM AND REPLACE EXISTING 2" GAS PIPE TO 1ST FLOOR COMMERCIAL SPACE WITH NEW 2" GAS PIPE.
M00429585-I1
Latest 60 of 78 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingSigned-offG.B. & SON, INC11/18/2021
DOB NOWPlumbingSigned-offG.B. & SON, INC02/12/2021
DOB NOWPlumbingSigned-offA.GOLDNER INC01/02/2020
DOB NOWMechanical SystemsSigned-offL & M BUILDERS GROUP LLC12/26/2019
BISOTISSUEDFRAZIER & SONS CONSTRUCTI01/29/2021
BISOTISSUEDL & M BUILDERS GROUP LLC08/29/2019
BISOTISSUEDAPEX BUILDING COMPANY INC04/06/2018
BISOTISSUEDL & M BUILDERS GROUP LLC01/22/2018
BISEQISSUEDAPEX BUILDING COMPANY INC08/25/2017
BISOTISSUEDAPEX BUILDING COMPANY INC08/25/2017
BISPLISSUEDBEST PLUMBING & HVAC INC04/15/2015
BISFPISSUEDUNIQUE FIRE SYSTEMS INC10/15/2013
BISPLISSUEDBEST PLUMBING & HVAC INC06/20/2013
BISMHISSUEDBCS CONSTRUCTION SERVICES03/15/2013
BISOTISSUEDBCS CONSTRUCTION SERVICES03/15/2013
BISOTISSUEDBCS CONSTRUCTION SERVICES02/25/2013
BISBLISSUEDSTUART N SCHWARTZ12/06/2012
BISPLISSUEDTRADELINE PLUMBING INC12/06/2012
BISEQISSUEDROCKLEDGE SCAFFOLD CORP08/17/2012
BISFPISSUEDCITYWIDE FIRE SYS PLBG EN08/01/2011
BISFPISSUEDMASTER FIRE SYSTEMS, INC07/30/2008
BISMHISSUEDEASTERN 2000 INC09/28/2007
BISEQISSUEDEASTERN 2000 INC09/28/2007
BISEQISSUEDTWIN SCAFFOLDING06/13/2000
BISFPISSUEDIDEAL FIRE CONTROL01/07/1997
BISPLISSUEDBEST PLUMBING & HVAC INC04/11/1996
BISFPISSUEDMASTER FIRE PREVENTION SYSTEMS02/13/1996
BISPLISSUEDMAGOR PLUMBING HEATING12/18/1995
BISPLISSUEDBEST PLUMBING & HVAC INC12/15/1995
BISFPISSUEDWKL CONSTR. CO.12/08/1995
BISOTISSUEDSAID AUEL /AQUEL SHEET METAL11/29/1995
BIS—RE-ISSUEDCROSS CONST/5TH AVE INC07/12/1995
BISPLISSUEDAL BERMAN PLUMBING AND AVENEU12/05/1994
BISEQISSUEDCOLGATE SCAFFOLDING09/14/1994
BISEQISSUEDCROSS CONST/5TH AVE INC08/23/1994
BIS—ISSUEDCROSS CONST/5TH AVE INC08/23/1994
BISFPISSUEDMASTER FIRE PREVENTION SYSTEMS05/13/1992
1 project · most recent 02/08/2021
General Wiring
FiledStatusContractorScope
02/08/2021CompleteGILSTON BROTHERS ELECT'LGeneral Wiring
▾Special Inspection Requirements (DOB NOW) — 6
DateRequirementInspectorRole
10/22/2021Fire-Resistant Penetrations and JointsMehmet Gunalspecial
10/22/2021Fire-Resistance Rated ConstructionMehmet Gunalprogress
10/22/2021Energy Code Compliance InspectionsMehmet Gunalprogress
10/21/2021Fire-Resistant Penetrations and JointsMehmet Gunalspecial
10/21/2021Energy Code Compliance InspectionsMehmet Gunalprogress
10/21/2021Fire-Resistance Rated ConstructionMehmet Gunalprogress
▾Documents — 230 on file (BIS + DOB NOW)
▸Plans & Drawings5
▸DOB NOWPlans/Sketch - Plumbing4
09/05/2026M00260483-I1Request digital key ↗
09/04/2026M00429585-I1Request digital key ↗
09/04/2026M00429585-P2Request digital key ↗
Showing 3 of 4 on file for this type
▸DOB NOWPlans/Sketch - Mechanical Systems1
09/05/2026M00260442-I1Request digital key ↗
▸Applications & Permits36
▸BISPLAN / WORK APPROVAL APPLICATION20
11/13/2023140979733Open ↗
11/20/2020140979733Open ↗
08/28/2019140865543Open ↗
Showing 3 of 20 on file for this type
▸BISWORK PERMIT APPLICATION16
01/29/2021140979733Open ↗
08/29/2019140865543Open ↗
05/01/2018123296655Open ↗
Showing 3 of 16 on file for this type
▸Seals & Professional Certifications49
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION20
02/21/2020123296655Open ↗
02/21/2020123296655Open ↗
02/06/2020123296655Open ↗
Showing 3 of 20 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST6
01/22/2018123190082Open ↗
08/22/2017123104880Open ↗
07/05/2017123296655Open ↗
Showing 3 of 6 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT5
11/20/2020140979733Open ↗
08/28/2019140865543Open ↗
01/22/2018123190082Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature5
09/05/2026M00260442-I1Open ↗
09/04/2026M00429585-I1Open ↗
09/04/2026M00429585-P2Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWProgress Inspector Seal & Signature4
08/28/2026M00429585-I1Open ↗
08/28/2026M00429585-I1Open ↗
08/28/2026M00429585-P2Open ↗
Showing 3 of 4 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM3
02/22/2013121538498Open ↗
11/08/2012121424048Open ↗
08/21/2012121346356Open ↗
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION2
11/20/2020140979733Open ↗
08/28/2019140865543Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY2
11/20/2020140979733Open ↗
08/28/2019140865543Open ↗
▸DOB NOWSpecial Inspector Seal & Signature2
08/28/2026M00429585-I1Open ↗
08/28/2026M00429585-P2Open ↗
▸Trade Schedules & Equipment18
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE6
08/22/2017123104880Open ↗
07/05/2017123296655Open ↗
09/29/2015121538498Open ↗
Showing 3 of 6 on file for this type
▸BISSELF-CERT PLUMBING NOTICE4
10/08/2015121538498Open ↗
05/12/2015121538498Open ↗
01/02/2014121424048Open ↗
Showing 3 of 4 on file for this type
▸BISSCHEDULE B - PLUMBING3
02/26/2013121538498Open ↗
02/22/2013121538498Open ↗
11/08/2012121424048Open ↗
▸BISFA - FDNY APPROVAL : FD-FAA2
10/20/2015121777960Open ↗
02/20/2014121538498Open ↗
▸BISBOILERS - SUPPORTING DOCUMENTATION1
01/06/2014121424048Open ↗
▸BISSCHEDULE C - HEATING & COMBUSTION EQUIPMENT1
11/08/2012121424048Open ↗
▸BISPLUMBING - SUPPORTING DOCUMENTATION1
01/22/2024140979733Open ↗
▸Safety & Tenant Protection9
▸DOB NOWTenant Protection Plan5
09/04/2026M00429585-P2Open ↗
09/04/2026M00429585-P1Open ↗
09/04/2026M00429585-I1Open ↗
Showing 3 of 5 on file for this type
▸BISTenant Protection Plan and Notes3
08/22/2017123104880Open ↗
07/05/2017123296655Open ↗
08/28/2019140865543Open ↗
▸BISTPP1: TENANT PROTECTION PLAN1
01/29/2021140979733Open ↗
▸Environmental & Asbestos14
▸BISASBESTOS: CERTIFICATION (DEP ACP5)5
11/20/2020140979733Open ↗
08/28/2019140865543Open ↗
08/22/2017123104880Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWDEP ACP-5: Asbestos Assessment Report5
09/05/2026M00260442-I1Open ↗
09/04/2026M00429585-P2Open ↗
09/04/2026M00429585-P1Open ↗
Showing 3 of 5 on file for this type
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER2
08/21/2012121346356Open ↗
05/24/2011120699477Open ↗
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'1
07/21/2008110201790Open ↗
▸BISACP5 ASBESTOS: CERTIFICATION (DEP ACP5)1
11/08/2012121424048Open ↗
▸Energy Compliance26
▸BISAS-BUILT ENERGY ANALYSIS8
08/28/2023140979733Open ↗
08/11/2023140979733Open ↗
06/28/2023140979733Open ↗
Showing 3 of 8 on file for this type
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS8
02/21/2020123296655Open ↗
02/21/2020123296655Open ↗
02/06/2020123296655Open ↗
Showing 3 of 8 on file for this type
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY2
01/29/2021140979733Open ↗
08/28/2019140865543Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS2
11/20/2020140979733Open ↗
08/28/2019140865543Open ↗
▸BISAS-BUILT ENERGY ANALYSIS (EN2)2
01/22/2024140979733Open ↗
07/30/2020140865543Open ↗
▸BISENERGY CODE COMPLIANCE INSPECTIONS1
07/30/2020140865543Open ↗
▸BISLIGHTING CONTROLS1
01/22/2024140979733Open ↗
▸BISTR8 INSPECTOR TO CONFIRM AS-BUILT VALUES1
06/28/2023140979733Open ↗
▸BISNYCECC ANALYSIS1
08/28/2019140865543Open ↗
▸Inspections & Test Reports13
▸BISTECHNICAL REPORT: RESPONSIBILITY9
06/28/2023140979733Open ↗
01/29/2021140979733Open ↗
01/29/2021140979733Open ↗
Showing 3 of 9 on file for this type
▸BISFIRE-RESISTANT PENETRATIONS AND JOINTS (FIRESTOP)3
01/22/2024140979733Open ↗
01/22/2024140979733Open ↗
07/30/2020140865543Open ↗
▸BISTECHNICAL REPORT: CONCRETE/TEST CYLINDER1
01/30/2019123296655Open ↗
▸Approvals, Objections & Sign-offs18
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST11
01/22/2024140979733Open ↗
07/30/2020140865543Open ↗
06/18/2020123296655Open ↗
Showing 3 of 11 on file for this type
▸BISADMINISTRATIVE OBJECTIONS4
02/22/2013121538498Open ↗
08/21/2012121346356Open ↗
05/24/2011120699477Open ↗
Showing 3 of 4 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION2
09/28/2015121538498Open ↗
04/25/2013121346356Open ↗
▸BISFINAL1
01/22/2024140979733Open ↗
▸Cost, Insurance & Ownership21
▸BISCOST AFFIDAVIT19
08/28/2023140979733Open ↗
08/11/2023140979733Open ↗
11/20/2020140979733Open ↗
Showing 3 of 19 on file for this type
▸BISCOST AFFIDAVIT (FINAL): PW32
01/22/2024140979733Open ↗
07/30/2020140865543Open ↗
▸Filing & Intake Forms19
▸BISEFILING COVER SHEET7
01/22/2018123190082Open ↗
08/22/2017123104880Open ↗
07/05/2017123296655Open ↗
Showing 3 of 7 on file for this type
▸BISBOROUGH INTAKE FORM7
02/21/2020123296655Open ↗
02/06/2020123296655Open ↗
03/13/2019123296655Open ↗
Showing 3 of 7 on file for this type
▸BISADDITIONAL INFORMATION3
01/27/2014121538498Open ↗
11/21/2013121424048Open ↗
09/17/2013121424048Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET2
11/20/2020140979733Open ↗
08/28/2019140865543Open ↗
▸Other Documents2
▸BISPRELIMINARY1
07/30/2020140865543Open ↗
▸DOB NOWDHCR Document1
09/04/2026M00429585-I1Open ↗