← Back
Two stories - detached, small or mid-size
226 EAST 236 STREET
BRONX · Wakefield-Woodlawn · BIN 2019085
💬 Discuss this project
1920Year Built
2.5Stories
A1Building Class
R4AZoning
2,910 sfGross Floor Area
1Units
Two stories - detached, small or mid-size · 2,500 sf lot · 1.16 FAR built · Flood zone X
Locations of Work
Electrical
Roof2p · 1 filing · 17 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
TRINITY SOLAR LLC209/05/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
ACA ASSOCIATES203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
REDLINE ELECTRIC INCElectrical103/22/2026
TRINITY SOLAR LLCGeneral Contractor107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
BITOPI CONSULTANTS LLC7036209/05/2025
Building Lifecycle
All (16)Filed (2)Permit Issued (1)Signed Off (1)Inspection (2)Special Inspection (10)
03/09/2026
Inspection — Pass-Final Curb Cut Non-Directive 14
Pass
View inspection ↗
10/14/2025
Signed off — Alteration
Installation of solar system on the roof as per plan. No change in use, egress or occupancy
X01163647-I1
09/05/2025
Filed — Alteration
Installation of solar system on the roof as per plan. No change in use, egress or occupancy
X01163647-P1
09/05/2025
Special inspection requirement — Air barrier - visual inspection
Ayracon Almaraz
09/05/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
KAMRUL AHSAN
09/05/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
KAMRUL AHSAN
09/05/2025
Special inspection requirement — Energy Code Compliance Inspections
Ayracon Almaraz
09/05/2025
Special inspection requirement — Final
Ayracon Almaraz
09/04/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
KAMRUL AHSAN
09/04/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
KAMRUL AHSAN
09/04/2025
Special inspection requirement — Energy Code Compliance Inspections
Ayracon Almaraz
09/04/2025
Special inspection requirement — Final
Ayracon Almaraz
09/04/2025
Special inspection requirement — Air barrier - visual inspection
Ayracon Almaraz
06/16/2025
Inspection — Fail-Final Curb Cut Non-Directive 14
Fail
View inspection ↗
01/16/2025
Permit issued — Solar
X01163647-I1-SL
01/09/2025
Filed — Alteration
Installation of solar system on the roof as per plan. No change in use, egress or occupancy
X01163647-I1
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offTRINITY SOLAR LLC01/16/2025
BISPLISSUEDJ&M PLUMBING OF WESTCHESTER11/20/2002
1 project · most recent 02/19/2025
FiledStatusContractorScope
02/19/2025CompleteREDLINE ELECTRIC INC—
▾Field Inspections (DOB CAP) — 2
DateTypeResultReport
03/09/2026Pass-Final Curb Cut Non-Directive 14PassView ↗
06/16/2025Fail-Final Curb Cut Non-Directive 14FailView ↗
▾Special Inspection Requirements (DOB NOW) — 10
DateRequirementInspectorRole
09/05/2025Air barrier - visual inspectionAyracon Almarazenergy_progress
09/05/2025Structural Stability – Alterations of existing buildingsKAMRUL AHSANspecial
09/05/2025Fire-Resistant Penetrations and JointsKAMRUL AHSANspecial
09/05/2025Energy Code Compliance InspectionsAyracon Almarazprogress
09/05/2025FinalAyracon Almarazprogress
09/04/2025Fire-Resistant Penetrations and JointsKAMRUL AHSANspecial
09/04/2025Structural Stability – Alterations of existing buildingsKAMRUL AHSANspecial
09/04/2025Energy Code Compliance InspectionsAyracon Almarazprogress
09/04/2025FinalAyracon Almarazprogress
09/04/2025Air barrier - visual inspectionAyracon Almarazenergy_progress
▾Documents — 17 on file (BIS + DOB NOW)
▸Plans & Drawings2
▸DOB NOWPlans/Sketch2
08/20/2026X01163647-I1Request digital key ↗
08/20/2026X01163647-P1Request digital key ↗
▸Seals & Professional Certifications12
▸DOB NOWProgress Inspector Seal & Signature6
09/02/2026X01163647-I1Open ↗
09/02/2026X01163647-I1Open ↗
09/02/2026X01163647-I1Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature4
09/02/2026X01163647-I1Open ↗
09/02/2026X01163647-I1Open ↗
09/02/2026X01163647-P1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature2
08/20/2026X01163647-I1Open ↗
08/13/2026X01163647-P1Open ↗
▸Environmental & Asbestos2
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
08/20/2026X01163647-I1Open ↗
08/13/2026X01163647-P1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/13/2026X01163647-I1Open ↗