| Owner | Filings | Most Recent |
|---|---|---|
| 77 RIDGE DEVELOPMENT | 42 | 07/08/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 10/31/2025 | $2.6M | — | — → — | $941/sf building |
| 01/18/2022 | $1.7M | — | — → — | — not available |
| 01/05/2017 | $1.8M | — | Private party → Private party | — not available |
| Firm | Filings | Most Recent |
|---|---|---|
| ZPROEKT ARCHITECTURE | 15 | 12/23/2024 |
| FIRST HEC DESIGN INC. | 1 | 08/07/2020 |
| Representative | Filings | Most Recent |
|---|---|---|
| HM CONSULTING EXPEDITING | 18 | 03/21/2026 |
| D S CREATIVE INOVATIONS | 12 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| SAPOL CONSTRUCTION LLC | General Contractor | 12 | 07/08/2026 |
| GENESIS NYC CONSTRUCTION | General Contractor | 3 | 03/21/2026 |
| PFL MECHANICAL CORP | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| C&P DESIGN CONSULTANT | 8472 | 10 | 12/23/2024 |
| SRA PLANNING & EXPEDITING | 5677 | 3 | 07/17/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Curb Cut | Signed-off | LEON D. DEMATTEIS CONSTR | 06/27/2024 |
| DOB NOW | Plumbing | Signed-off | PFL MECHANICAL CORP | 09/20/2023 |
| DOB NOW | General Construction | Signed-off | LEON D. DEMATTEIS CONSTR | 07/19/2023 |
| DOB NOW | Mechanical Systems | Signed-off | LEON D. DEMATTEIS CONSTR | 07/13/2023 |
| DOB NOW | Construction Fence | Signed-off | LEON D. DEMATTEIS CONSTR | 07/12/2023 |
| DOB NOW | General Construction | Permit Issued | LEON D. DEMATTEIS CONSTR | 07/12/2023 |
| DOB NOW | Support of Excavation | Signed-off | LEON D. DEMATTEIS CONSTR | 06/15/2023 |
| DOB NOW | Construction Fence | Signed-off | LEON D. DEMATTEIS CONSTR | 03/17/2023 |
| DOB NOW | Construction Fence | Signed-off | LEON D. DEMATTEIS CONSTR | 03/25/2022 |
| DOB NOW | Construction Fence | Signed-off | GENESIS NYC CONSTRUCTION | 08/19/2020 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/23/2024 | Signed-off | PFL MECHANICAL CORP | Gas, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/11/2024 | Complete | SHELBY ELECTRICAL CORP | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 05/08/2026 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 10/07/2024 | Pass-Final Curb Cut Non-Directive 14 | Pass | View ↗ |
| 10/04/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 07/25/2024 | Fail-Final Curb Cut Non-Directive 14 | Fail | View ↗ |
| 06/13/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 01/23/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 10/11/2023 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 10/11/2023 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 10/11/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 10/11/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 12/30/2024 | Shutoff dampers | Stanislav Pilipenko | energy_progress |
| 12/30/2024 | Insulation placement and R values | Stanislav Pilipenko | energy_progress |
| 12/30/2024 | HVAC-R and service water heating equipment | Stanislav Pilipenko | energy_progress |
| 12/30/2024 | Protection of exposed foundation insulation | Stanislav Pilipenko | energy_progress |
| 12/30/2024 | Permanent certificate | Stanislav Pilipenko | energy_progress |
| 12/30/2024 | HVAC-R and service water piping design and insulation | Stanislav Pilipenko | energy_progress |
| 12/30/2024 | Exterior lighting power | Stanislav Pilipenko | energy_progress |
| 12/30/2024 | Fenestration and door U-factor and product ratings | Stanislav Pilipenko | energy_progress |
| 12/30/2024 | HVAC-R and service water heating system controls | Stanislav Pilipenko | energy_progress |
| 12/30/2024 | Electric vehicle service equipment requirements | Stanislav Pilipenko | energy_progress |
| 12/30/2024 | Fenestration air leakage | Stanislav Pilipenko | energy_progress |
| 12/30/2024 | Ventilation and air distribution system | Stanislav Pilipenko | energy_progress |
| 12/30/2024 | Maintenance information | Stanislav Pilipenko | energy_progress |
| 12/30/2024 | Air barrier — testing | Stanislav Pilipenko | energy_progress |
| 12/30/2024 | Fenestration areas | Stanislav Pilipenko | energy_progress |
| 12/30/2024 | Interior lighting power | Stanislav Pilipenko | energy_progress |
| 12/30/2024 | Air barrier - visual inspection | Stanislav Pilipenko | energy_progress |
| 12/30/2024 | Insulation placement and R values | Stanislav Pilipenko | energy_progress |
| 12/30/2024 | Air barrier - visual inspection | Stanislav Pilipenko | energy_progress |
| 12/30/2024 | Fenestration air leakage | Stanislav Pilipenko | energy_progress |
| 12/30/2024 | Exterior lighting power | Stanislav Pilipenko | energy_progress |
| 12/30/2024 | Shutoff dampers | Stanislav Pilipenko | energy_progress |
| 12/30/2024 | HVAC-R and service water heating system controls | Stanislav Pilipenko | energy_progress |
| 12/30/2024 | Fenestration areas | Stanislav Pilipenko | energy_progress |
| 12/30/2024 | HVAC-R and service water heating equipment | Stanislav Pilipenko | energy_progress |