| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 11/10/2025 | $1.7M | — | Private party → 2280 85TH STREET LLC | $483/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| FARHAD BASSIRI-TEHRANI | 6 | 04/24/2026 |
| Representative | Filings | Most Recent |
|---|---|---|
| ECDESIGN STUDIO | 6 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| KALE CONSTRUCTION INC | General Contractor | 1 | 07/08/2026 |
| CATMAN PLUMBING INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| BASSIRI | 8394 | 3 | 04/24/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Signed-off | KALE CONSTRUCTION INC | 12/05/2025 |
| DOB NOW | Plumbing | Signed-off | CATMAN PLUMBING INC | 12/04/2025 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/24/2026 | Signed-off | CATMAN PLUMBING INC | Gas, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/10/2026 | Complete | KJK ELECTRIC INC | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 06/16/2026 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 04/01/2026 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 03/13/2026 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 03/13/2026 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 03/10/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 03/09/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 02/19/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 01/21/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 04/27/2026 | Fire-Resistant Penetrations and Joints | FARHAD BASSIRI-TEHRANI | special |
| 04/27/2026 | Energy Code Compliance Inspections | FARHAD BASSIRI-TEHRANI | progress |
| 04/27/2026 | Fire-Resistance Rated Construction | FARHAD BASSIRI-TEHRANI | progress |
| 04/22/2026 | Fire-Resistance Rated Construction | FARHAD BASSIRI-TEHRANI | progress |
| 04/22/2026 | Fire-Resistant Penetrations and Joints | FARHAD BASSIRI-TEHRANI | special |
| 04/22/2026 | Energy Code Compliance Inspections | FARHAD BASSIRI-TEHRANI | progress |
| 03/02/2026 | Fire-Resistant Penetrations and Joints | FARHAD BASSIRI-TEHRANI | special |
| 03/02/2026 | Fire-Resistance Rated Construction | FARHAD BASSIRI-TEHRANI | progress |
| 03/02/2026 | Energy Code Compliance Inspections | FARHAD BASSIRI-TEHRANI | progress |