← Back
Public elementary, junior or senior high
Queens United Middle School
229-02 137 AVENUE · BIN 4283015
💬 Discuss this project
1930Year Built
3Stories
W1Building Class
R2AZoning
79,200 sfGross Floor Area
0Units
LL97 Covered14 Open Violations 0 unresolved · 14 paperwork only ▸FDNY Report ↗
Public elementary, junior or senior high · Owner of record: NYC DEPARTMENT OF EDUCATION · 100,000 sf lot · 0.79 FAR built · Flood zone X
Locations of Work
ArchitectureMechanicalPlumbing
Permit Issued — active, not yet Signed-off
Floor 2Under Construction15p · 1 filing · 20 docs
Floor 11p · 1 filing · 9 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
NYC SCHOOL CONSTRUCTION AUTHORITY1507/08/2026
NYC DEPARTMENT OF EDUCATION103/22/2026
DEPARTMENT OF EDUCATION703/22/2026
DEPARTMENT OF BUILDINGS103/22/2026
DOE PS 156203/22/2026
DEPT OF EDUCATION P.S.156703/22/2026
DOE PS 156 040903/22/2026
DOE 040403/22/2026
DOE PS 156 TRANSPORTA040203/22/2026
DEPT. OF EDUCATION P.S.15303/22/2026
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
EME CONSULTING ENGINEERING GROUP103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
D. PAUL CONSTRUCTION INCGeneral Contractor607/08/2026
A&H EXPRESS PLBG&HTG CORPPlumbing207/04/2026
CEDOMIR MARAElectrical103/21/2026
GIOVANNI DITURIElectrical103/21/2026
LASER ELEC'L CONSTR'G INCElectrical103/22/2026
MNBC ELECTRICAL CORPElectrical103/22/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
JPC LOGISTICS DBA JPCL EN351201/06/2026
KS ENGINEERS, P.C.7715208/30/2023
Building Lifecycle
All (98)Filed (7)Permit Issued (6)Violation (60)Objection (8)Special Inspection (17)
03/24/2026
Permit issued — General Construction
Q00919714-S1-GC
03/23/2026
Violation issued (FDNY_ORDER, closed)
03/23/2026
Violation issued (FDNY_ORDER, closed)
03/23/2026
Violation issued (FDNY_ORDER, closed)
03/23/2026
Violation issued (FDNY_ORDER, closed)
02/24/2026
Permit issued — Plumbing
Q00919714-I1-PL
02/20/2026
Violation issued (FDNY_ORDER, closed)
02/12/2026
Violation issued (ECB, open)
Construction
02/12/2026
Violation issued (ECB, open)
Construction
02/12/2026
Violation issued (ECB, open)
Construction
02/12/2026
Violation issued (ECB, open)
Construction
02/12/2026
Violation issued (ECB, open)
Construction
01/29/2026
Objection raised — Scope
01/29/2026
Objection raised — Zoning
01/06/2026
Filed — Alteration
THE SCOPE OF WORK INCLUDES ALL LABOR, MATERIALS, AND EQUIPMENT NECESSARY TO COMPLETE INSTALLATION OF THE SUPPLEMENTAL COOLING SYSTEM IN THE KITCHEN AREA.
Q01296999-I1
01/05/2026
Special inspection requirement — Post-installed Anchors
Asma Hashmi
01/05/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Asma Hashmi
12/12/2025
Violation issued (FDNY_ORDER, closed)
12/12/2025
Violation issued (FDNY_ORDER, closed)
12/12/2025
Violation issued (FDNY_ORDER, closed)
12/04/2025
Violation issued (FDNY_ORDER, closed)
10/02/2025
Special inspection requirement — Final
Asma Hashmi
10/02/2025
Special inspection requirement — Mechanical Systems
Asma Hashmi
09/23/2025
Filed — Alteration
THE SCOPE OF WORK INCLUDES THE INSTALLATION OF A SUPPLEMENTAL SPLIT COOLING SYSTEM FOR THE AUDITORIUM.
Q01224053-I1
08/06/2025
Violation issued (FDNY_ORDER, closed)
08/06/2025
Violation issued (FDNY_ORDER, closed)
05/12/2025
Special inspection requirement — Mechanical Systems
Asma Hashmi
05/12/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Asma Hashmi
05/12/2025
Special inspection requirement — Post-installed Anchors
Asma Hashmi
05/12/2025
Special inspection requirement — Final
Asma Hashmi
04/28/2025
Violation issued (ECB, open)
Construction
04/28/2025
Violation issued (ECB, open)
Construction
04/28/2025
Violation issued (ECB, open)
Construction
04/08/2025
Permit issued — General Construction
Q00919714-S1-GC
02/13/2025
Violation issued (ECB, open)
Construction
01/28/2025
Permit issued — General Construction
Q00919714-S1-GC
01/23/2025
Permit issued — Plumbing
Q00919714-I1-PL
01/07/2025
Permit issued — General Construction
Q00919714-S1-GC
10/28/2024
Filed — Alteration
Q01129441-I1
10/18/2024
Special inspection requirement — Post-installed Anchors
10/18/2024
Special inspection requirement — Final
10/18/2024
Special inspection requirement — Mechanical Systems
10/18/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
09/13/2024
Objection raised — Other
09/13/2024
Objection resolved — Addressed
09/13/2024
Special inspection requirement — Fire-Resistance Rated Construction
Mohamed Shahid
09/13/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
Mohamed Shahid
09/12/2024
Filed — Alteration
RENOVATE CLASSROOM 224 TO COMPUTER LAB. MISC. RENOVATE DRINKING FOUNTAIN ALCOVE.
Q00919714-P1
09/12/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
09/12/2024
Special inspection requirement — Fire-Resistance Rated Construction
03/01/2024
Violation issued (ECB, closed)
Construction
03/01/2024
Violation issued (ECB, open)
Construction
03/01/2024
Violation issued (ECB, open)
Construction
03/01/2024
Violation issued (ECB, closed)
Construction
03/01/2024
Violation issued (ECB, closed)
Construction
03/01/2024
Violation issued (ECB, closed)
Construction
03/01/2024
Violation issued (ECB, closed)
Construction
01/03/2024
Violation issued (FDNY_NOV, closed)
11/02/2023
Violation issued (FDNY_NOV, closed)
10/23/2023
Objection resolved — Addressed
Latest 60 of 98 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionPermit IssuedD. PAUL CONSTRUCTION INC03/24/2026
DOB NOWPlumbingPermit IssuedA&H EXPRESS PLBG&HTG CORP02/24/2026
DOB NOWGeneral ConstructionPermit IssuedD. PAUL CONSTRUCTION INC04/08/2025
DOB NOWGeneral ConstructionPermit IssuedD. PAUL CONSTRUCTION INC01/28/2025
DOB NOWPlumbingPermit IssuedA&H EXPRESS PLBG&HTG CORP01/23/2025
DOB NOWGeneral ConstructionPermit IssuedD. PAUL CONSTRUCTION INC01/07/2025
BISOTISSUEDSAAD CONSTRUCTION CORP04/29/2025
BISOTISSUEDSAAD CONSTRUCTION CORP06/20/2023
BISOTISSUEDSAAD CONSTRUCTION CORP07/14/2022
BISEQISSUEDA.S.C CONTRACTING CORP06/25/2021
BISOTISSUEDA.S.C CONTRACTING CORP06/25/2021
BISOTISSUEDA.S.C CONTRACTING CORP06/25/2021
BISPLISSUEDMAR-SAL PLBG & HTG, INC04/23/2021
BISOTISSUEDA.S.C CONTRACTING CORP06/23/2020
BISEQISSUEDA.S.C CONTRACTING CORP06/22/2020
BISEQISSUEDA.S.C CONTRACTING CORP03/25/2019
BISOTISSUEDA.S.C CONTRACTING CORP03/25/2019
BISOTISSUEDA.S.C CONTRACTING CORP03/25/2019
BISPLISSUEDMAR-SAL PLBG & HTG, INC07/09/2018
BISOTISSUEDA.S.C CONTRACTING CORP02/06/2018
BISOTISSUEDA.S.C CONTRACTING CORP02/06/2018
BISEQISSUEDA.S.C CONTRACTING CORP02/06/2018
BISOTISSUEDA.S.C CONTRACTING CORP11/13/2017
BISOTISSUEDA.S.C CONTRACTING CORP11/08/2017
BISOTISSUEDA.S.C CONTRACTING CORP07/14/2017
BISOTISSUEDA.S.C CONTRACTING CORP07/14/2017
BISPLISSUEDMAR-SAL PLBG & HTG, INC07/05/2017
BISEQISSUEDA.S.C CONTRACTING CORP05/23/2017
BISMHISSUEDMIDTOWN HVAC ENTERPRISES06/25/2015
BISMHISSUEDMIDTOWN HVAC ENTERPRISES06/30/2014
BISOTISSUEDEMPIRE CONTROL ABATEMENT07/15/2013
BISOTISSUEDEMPIRE CONTROL ABATEMENT07/11/2013
BISMHISSUEDACS SYSTEM ASSOCIATES INC.06/05/2012
BISOTISSUEDABAX INC01/03/2012
BISOTISSUEDABAX INC01/03/2012
BISPLISSUEDEAGLE 1 MECHANICAL, INC11/25/2011
BISPLISSUEDEAGLE 1 MECHANICAL, INC10/26/2011
BISMHISSUEDACS SYSTEM ASSOCIATES INC.10/20/2011
BISOTISSUEDABAX INC10/11/2011
BISOTISSUEDABAX INC10/11/2011
+ 16 more permits on file
2 projects · most recent 01/06/2026
Air Conditioning Systems
FiledStatusContractorScopeMake / Model / Capacity
01/06/2026——Air Conditioning Systems
Cooling
Lg LG - ZRNU303SRAA 30,000 BTU · Vrf Indoor ×8
LG ZRUM060GSS0 60,000 BTU · Vrf Outdoor ×4
09/23/2025——Air Conditioning Systems
Cooling
Fujitsu ASUA36TLAV2 34,000 BTU · Fan Coil Indoor ×11
AOU120RLAVL 120,000 BTU · Condensing Unit ×2
AOU96RLAVL 96,000 BTU · Condensing Unit ×1
1 project · most recent 09/12/2024
Water/Sanitary
FiledStatusContractorScope
09/12/2024Permit IssuedA&H EXPRESS PLBG&HTG CORPWater/Sanitary
13 projects · most recent 01/29/2025
General Wiring
FiledStatusContractorScope
01/29/2025CancelledMNBC ELECTRICAL CORPGeneral Wiring
11/06/2024CompleteWILLDAN ELECTRICAL OF NYGeneral Wiring
09/11/2024Permit IssuedMNBC ELECTRICAL CORPGeneral Wiring
04/23/2024CompleteGEMINI ELECTRIC CO., INC.—
11/29/2023Permit IssuedGEMINI ELECTRIC CO., INC.General Wiring
11/02/2023CompleteGEMINI ELECTRIC CO., INC.—
07/25/2023CompleteWORD OF LIGHT ELECT LLCGeneral Wiring
08/16/2022CompleteABM ELECTRIC, INCGeneral Wiring
09/21/2020CompleteJAMES F. VOLPE ELEC'LGeneral Wiring
06/26/2020CompleteCHARAN ELEC'L ENTERP'S IN—
02/17/2020CompleteCHARAN ELEC'L ENTERP'S INGeneral Wiring
01/20/2020CompleteCHARAN ELEC'L ENTERP'S IN—
02/13/2019Permit IssuedLASER ELEC'L CONSTR'G INCGeneral Wiring
▾Special Inspection Requirements (DOB NOW) — 17
DateRequirementInspectorRole
01/05/2026Post-installed AnchorsAsma Hashmispecial
01/05/2026Fire-Resistant Penetrations and JointsAsma Hashmispecial
10/02/2025FinalAsma Hashmiprogress
10/02/2025Mechanical SystemsAsma Hashmispecial
05/12/2025Mechanical SystemsAsma Hashmispecial
05/12/2025Fire-Resistant Penetrations and JointsAsma Hashmispecial
05/12/2025Post-installed AnchorsAsma Hashmispecial
05/12/2025FinalAsma Hashmiprogress
10/18/2024Post-installed Anchors—special
10/18/2024Final—progress
10/18/2024Mechanical Systems—special
10/18/2024Fire-Resistant Penetrations and Joints—special
09/13/2024Fire-Resistance Rated ConstructionMohamed Shahidprogress
09/13/2024Fire-Resistant Penetrations and JointsMohamed Shahidspecial
09/12/2024Fire-Resistant Penetrations and Joints—special
09/12/2024Fire-Resistance Rated Construction—progress
08/15/2023Fire-Resistant Penetrations and JointsMohamed Shahidspecial
▾Documents — 45 on file (BIS + DOB NOW)
▸Plans & Drawings7
▸DOB NOWPlans/Sketch7
08/24/2026Q00914155-I1Request digital key ↗
08/24/2026Q00919714-I1Request digital key ↗
08/24/2026Q00919714-S1Request digital key ↗
Showing 3 of 7 on file for this type
▸Seals & Professional Certifications14
▸DOB NOWDPL-1: Design Professional Seal & Signature7
08/24/2026Q00914155-I1Open ↗
08/24/2026Q00919714-S1Open ↗
08/21/2026Q01129441-I1Open ↗
Showing 3 of 7 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature5
09/23/2026Q01224053-I1Open ↗
09/23/2026Q01224053-I1Open ↗
09/23/2026Q01224053-I1Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWProgress Inspector Seal & Signature2
09/23/2026Q01224053-I1Open ↗
08/23/2026Q00919714-S1Open ↗
▸Approvals, Objections & Sign-offs16
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter7
08/24/2026Q00919714-S1Open ↗
08/13/2026Q00914155-I1Open ↗
08/13/2026Q01129441-I1Open ↗
Showing 3 of 7 on file for this type
▸DOB NOWDesign Commission Approval City Owned (Exterior Work)7
08/24/2026Q00919714-S1Open ↗
08/13/2026Q00914155-I1Open ↗
08/13/2026Q01129441-I1Open ↗
Showing 3 of 7 on file for this type
▸DOB NOWDEP Variance (V5) letter2
08/13/2026Q00919714-S1Open ↗
08/13/2026Q00919714-I1Open ↗
▸Other Documents8
▸DOB NOWProof of Historic Building5
08/13/2026Q01224053-I1Open ↗
08/13/2026Q01296999-I1Open ↗
08/13/2026Q00919714-I1Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWNYCSCA - BCC Plan Examination Transmittal3
08/24/2026Q00919714-S1Open ↗
08/13/2026Q00919714-P1Open ↗
08/13/2026Q00919714-I1Open ↗