| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 10/30/2020 | $950K | — | Private party → Private party | $679/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| GARFINKEL ARCHITECT, PLLC | 5 | 03/29/2022 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| G & T CONSULTANT CORP | General Contractor | 2 | 03/21/2026 |
| PIPESTYLISTS, INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| AZ PROFESSIONAL ENGINEERI | 766 | 3 | 03/29/2022 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | T & T PLUMBING INC | 07/09/2021 |
| DOB NOW | General Construction | Signed-off | G T CONSULTANT | 04/07/2021 |
| BIS | PL | ISSUED | STUART WACHTEL & SON INC | 11/04/2002 |
| BIS | OT | ISSUED | METRO CEMENT INC | 08/08/2002 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/27/2021 | Permit Issued | KINGS ELECTRIC CO., INC. | 1 meters, 1 new_meters |
| 04/14/2021 | Permit Issued | KINGS ELECTRIC CO., INC. | General Wiring |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 03/30/2022 | Fenestration areas | VIJAY KUMAR | energy_progress |
| 03/30/2022 | Insulation placement and R values | VIJAY KUMAR | energy_progress |
| 03/30/2022 | Fenestration and door U-factor and product ratings | VIJAY KUMAR | energy_progress |
| 03/30/2022 | Air barrier - visual inspection | VIJAY KUMAR | energy_progress |
| 03/30/2022 | Fenestration air leakage | VIJAY KUMAR | energy_progress |
| 03/30/2022 | Permanent certificate | VIJAY KUMAR | energy_progress |
| 03/30/2022 | HVAC-R and service water piping design and insulation | VIJAY KUMAR | energy_progress |
| 03/30/2022 | Interior lighting power | VIJAY KUMAR | energy_progress |
| 03/30/2022 | Energy Code Compliance Inspections | VIJAY KUMAR | progress |
| 03/30/2022 | Final | VIJAY KUMAR | progress |
| 03/30/2022 | Preliminary | VIJAY KUMAR | progress |
| 03/30/2022 | Fire-Resistance Rated Construction | VIJAY KUMAR | progress |
| 03/30/2022 | Exterior Insulation and Finish Systems (EIFS) | VIJAY KUMAR | special |
| 03/30/2022 | Structural Stability – Alterations of existing buildings | VIJAY KUMAR | special |
| 03/30/2022 | Fire-Resistant Penetrations and Joints | VIJAY KUMAR | special |
| 03/29/2022 | Insulation placement and R values | VIJAY KUMAR | energy_progress |
| 03/29/2022 | Fire-Resistant Penetrations and Joints | VIJAY KUMAR | special |
| 03/29/2022 | Structural Stability – Alterations of existing buildings | VIJAY KUMAR | special |
| 03/29/2022 | Energy Code Compliance Inspections | VIJAY KUMAR | progress |
| 03/29/2022 | Final | VIJAY KUMAR | progress |
| 03/29/2022 | Fire-Resistance Rated Construction | VIJAY KUMAR | progress |
| 03/29/2022 | Preliminary | VIJAY KUMAR | progress |
| 03/29/2022 | Interior lighting power | VIJAY KUMAR | energy_progress |
| 03/29/2022 | HVAC-R and service water piping design and insulation | VIJAY KUMAR | energy_progress |
| 03/29/2022 | Permanent certificate | VIJAY KUMAR | energy_progress |