← Back
One family attached or semi-detached
23 SIMMONS LOOP
STATEN ISLAND · BIN 5104656
💬 Discuss this project
1989Year Built
3Stories
A5Building Class
R3-2Zoning
1,240 sfGross Floor Area
1Units
One family attached or semi-detached · 1,792 sf lot · 0.69 FAR built · Flood zone X
Locations of Work
No floor-level scope or drawing coverage on file for this building.
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
MOMENTUM SOLAR208/25/2025
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
MXV SIA LLC9281208/25/2025
Building Lifecycle
All (14)Filed (2)Permit Issued (1)Signed Off (1)Special Inspection (10)
10/31/2025
Signed off — Alteration
Installation of solar panels; Rooftop, Railed, Grid tied, 14 Panels, 5.74 kW
S01163629-I1
08/26/2025
Special inspection requirement — Air barrier - visual inspection
Mina Makar
08/26/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
Mina Makar
08/26/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Mina Makar
08/26/2025
Special inspection requirement — Energy Code Compliance Inspections
Mina Makar
08/26/2025
Special inspection requirement — Final
Mina Makar
08/25/2025
Filed — Alteration
Installation of solar panels; Rooftop, Railed, Grid tied, 14 Panels, 5.74 kW
S01163629-P1
08/25/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Mina Makar
08/25/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
Mina Makar
08/25/2025
Special inspection requirement — Energy Code Compliance Inspections
Mina Makar
08/25/2025
Special inspection requirement — Final
Mina Makar
08/25/2025
Special inspection requirement — Air barrier - visual inspection
Mina Makar
01/09/2025
Permit issued — Solar
S01163629-I1-SL
01/07/2025
Filed — Alteration
Installation of solar panels; Rooftop, Railed, Grid tied, 14 Panels, 5.74 kW
S01163629-I1
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offMOMENTUM SOLAR01/09/2025
1 project · most recent 01/07/2025
FiledStatusContractorScope
01/07/2025CompleteISLAND ELECTRIC CORP—
▾Special Inspection Requirements (DOB NOW) — 10
DateRequirementInspectorRole
08/26/2025Air barrier - visual inspectionMina Makarenergy_progress
08/26/2025Structural Stability – Alterations of existing buildingsMina Makarspecial
08/26/2025Fire-Resistant Penetrations and JointsMina Makarspecial
08/26/2025Energy Code Compliance InspectionsMina Makarprogress
08/26/2025FinalMina Makarprogress
08/25/2025Fire-Resistant Penetrations and JointsMina Makarspecial
08/25/2025Structural Stability – Alterations of existing buildingsMina Makarspecial
08/25/2025Energy Code Compliance InspectionsMina Makarprogress
08/25/2025FinalMina Makarprogress
08/25/2025Air barrier - visual inspectionMina Makarenergy_progress
▾Documents — 11 on file (BIS + DOB NOW)
▸Plans & Drawings2
▸DOB NOWPlans/Sketch2
08/18/2026S01163629-P1Request digital key ↗
08/18/2026S01163629-I1Request digital key ↗
▸Seals & Professional Certifications8
▸DOB NOWProgress Inspector Seal & Signature4
08/24/2026S01163629-P1Open ↗
08/24/2026S01163629-P1Open ↗
08/22/2026S01163629-I1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature2
08/18/2026S01163629-P1Open ↗
08/18/2026S01163629-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature2
08/24/2026S01163629-P1Open ↗
08/22/2026S01163629-I1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/13/2026S01163629-I1Open ↗