← Back
STATEN ISLAND
23 VULCAN STREET
STATEN ISLAND · BIN 5176277
💬 Discuss this project
—Year Built
—Stories
—Building Class
—Zoning
—Gross Floor Area
—Units
Flood zone AE
Locations of Work
ArchitectureStructuralPlumbing
Floor 312p · 1 filing · 20 docs
Floor 213p · 1 filing · 20 docs
Floor 112p · 1 filing · 20 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
C&P DESIGN CONSULTANTS401/31/2025
STANLEY M. KREBUSHEVSKI, R.A.212/23/2024
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
STATCON DEVELOPMENT LLCGeneral Contractor1803/21/2026
FLOW-RIGHT PLBG & HTG CORPlumbing107/08/2026
QUALITY PLUMBING, INCPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
C&P DESIGN CONSULTANT8472501/31/2025
SRA PLANNING & EXPEDITING5677212/23/2024
Building Lifecycle
All (55)Filed (6)Permit Issued (8)Signed Off (3)Inspection (11)Objection (6)Special Inspection (21)
04/28/2025
Signed off — New Building
1) INSTALLATION OF GAS FURNACE WITH SPLIT SYSTEM DX COIL FOR HEATINGAND COOLING OF EACH RESIDENCE.2) INSTALLATION OF EXHAUST AND ERV SYSTEMS FOR VENTILATION OF EACHRESIDENCE.
S00915681-S2
04/28/2025
Signed off — New Building
1) INSTALLATION OF GAS FURNACE WITH SPLIT SYSTEM DX COIL FOR HEATINGAND COOLING OF EACH RESIDENCE.2) INSTALLATION OF EXHAUST AND ERV SYSTEMS FOR VENTILATION OF EACHRESIDENCE.
S00915681-S1
04/03/2025
Signed off — New Building
1) INSTALLATION OF GAS FURNACE WITH SPLIT SYSTEM DX COIL FOR HEATINGAND COOLING OF EACH RESIDENCE.2) INSTALLATION OF EXHAUST AND ERV SYSTEMS FOR VENTILATION OF EACHRESIDENCE.
S00915681-S3
03/18/2025
Inspection — Pass-Final Curb Cut Non-Directive 14
Pass
View inspection ↗
02/04/2025
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
02/04/2025
Special inspection requirement — Maintenance information
Stanislav Pilipenko
02/04/2025
Special inspection requirement — HVAC-R and service water heating equipment
Stanislav Pilipenko
02/04/2025
Special inspection requirement — Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation
Stanislav Pilipenko
02/04/2025
Special inspection requirement — Flood Zone Compliance (attach FEMA elevation/dry floodproofing certificate where applicable)
Stanislav Pilipenko
02/04/2025
Special inspection requirement — Energy Code Compliance Inspections
Stanislav Pilipenko
02/04/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
Stanislav Pilipenko
02/04/2025
Special inspection requirement — HVAC-R and service water heating system controls
Stanislav Pilipenko
02/04/2025
Special inspection requirement — Permanent certificate
Stanislav Pilipenko
01/31/2025
Filed — New Building
1) INSTALLATION OF GAS FURNACE WITH SPLIT SYSTEM DX COIL FOR HEATINGAND COOLING OF EACH RESIDENCE.2) INSTALLATION OF EXHAUST AND ERV SYSTEMS FOR VENTILATION OF EACHRESIDENCE.
S00915681-P2
01/27/2025
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
01/24/2025
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
01/16/2025
Permit issued — Mechanical Systems
S00915681-S2-MS
01/16/2025
Permit issued — Curb Cut
S00915681-S3-CC
12/31/2024
Filed — New Building
1) INSTALLATION OF GAS FURNACE WITH SPLIT SYSTEM DX COIL FOR HEATINGAND COOLING OF EACH RESIDENCE.2) INSTALLATION OF EXHAUST AND ERV SYSTEMS FOR VENTILATION OF EACHRESIDENCE.
S00915681-S3
12/30/2024
Objection resolved — Addressed
12/27/2024
Objection raised — Scope
12/23/2024
Filed — New Building
1) INSTALLATION OF GAS FURNACE WITH SPLIT SYSTEM DX COIL FOR HEATINGAND COOLING OF EACH RESIDENCE.2) INSTALLATION OF EXHAUST AND ERV SYSTEMS FOR VENTILATION OF EACHRESIDENCE.
S00915681-P1
08/14/2024
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
08/02/2024
Permit issued — Foundation
S00915681-I1-GC
07/17/2024
Inspection — Pass-Final PL - Underground
Pass
View inspection ↗
07/02/2024
Permit issued — Plumbing
S94311096-S1-PL
06/26/2024
Inspection — Certified Storm Drainage-ST-Fixtures-Finish
Certified
View inspection ↗
06/21/2024
Inspection — Certified Storm Drainage-ST-Piping-Underground
Certified
View inspection ↗
06/17/2024
Permit issued — Plumbing
S00915681-S1-PL
05/29/2024
Filed — New Building
1) INSTALLATION OF GAS FURNACE WITH SPLIT SYSTEM DX COIL FOR HEATINGAND COOLING OF EACH RESIDENCE.2) INSTALLATION OF EXHAUST AND ERV SYSTEMS FOR VENTILATION OF EACHRESIDENCE.
S00915681-S2
05/29/2024
Special inspection requirement — Permanent certificate
Stanislav Pilipenko
05/29/2024
Special inspection requirement — HVAC-R and service water piping design and insulation
Stanislav Pilipenko
05/29/2024
Special inspection requirement — HVAC-R and service water heating equipment
Stanislav Pilipenko
05/29/2024
Special inspection requirement — Ventilation and air distribution system
Stanislav Pilipenko
05/29/2024
Special inspection requirement — Chimneys and vents
Stanislav Pilipenko
05/29/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
Stanislav Pilipenko
05/29/2024
Special inspection requirement — Heating Systems
Stanislav Pilipenko
05/29/2024
Special inspection requirement — Energy Code Compliance Inspections
Stanislav Pilipenko
05/29/2024
Special inspection requirement — Maintenance information
Stanislav Pilipenko
05/29/2024
Special inspection requirement — Duct leakage testing, insulation and design
Stanislav Pilipenko
05/29/2024
Special inspection requirement — HVAC-R and service water heating system controls
Stanislav Pilipenko
05/27/2024
Filed — New Building
1) INSTALLATION OF GAS FURNACE WITH SPLIT SYSTEM DX COIL FOR HEATINGAND COOLING OF EACH RESIDENCE.2) INSTALLATION OF EXHAUST AND ERV SYSTEMS FOR VENTILATION OF EACHRESIDENCE.
S00915681-S1
05/25/2024
Special inspection requirement — Mechanical Systems
Stanislav Pilipenko
05/25/2024
Special inspection requirement — Final
Stanislav Pilipenko
04/02/2024
Permit issued — General Construction
S00915681-I1-FO
04/02/2024
Permit issued — General Construction
S00915681-I1-GC
03/27/2024
Permit issued — Structural
S00915681-I1-ST
12/07/2023
Objection resolved — Addressed
11/29/2023
Inspection — Fail-Final PL - Up to 3 Requested Floors
Fail
View inspection ↗
11/20/2023
Objection raised — Inspections
11/20/2023
Objection resolved — Addressed
11/20/2023
Objection raised — Scope
10/31/2023
Filed — New Building
1) INSTALLATION OF GAS FURNACE WITH SPLIT SYSTEM DX COIL FOR HEATINGAND COOLING OF EACH RESIDENCE.2) INSTALLATION OF EXHAUST AND ERV SYSTEMS FOR VENTILATION OF EACHRESIDENCE.
S00915681-I1
07/11/2023
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
07/11/2023
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWMechanical SystemsSigned-offSTATCON DEVELOPMENT LLC01/16/2025
DOB NOWCurb CutSigned-offSTATCON DEVELOPMENT LLC01/16/2025
DOB NOWFoundationPermit IssuedSTATCON DEVELOPMENT LLC08/02/2024
DOB NOWPlumbingSigned-offFLOW-RIGHT PLBG & HTG COR07/02/2024
DOB NOWPlumbingSigned-offQUALITY PLUMBING, INC06/17/2024
DOB NOWGeneral ConstructionSigned-offSTATCON DEVELOPMENT LLC04/02/2024
DOB NOWGeneral ConstructionPermit IssuedSTATCON DEVELOPMENT LLC04/02/2024
DOB NOWStructuralSigned-offSTATCON DEVELOPMENT LLC03/27/2024
1 project · most recent 01/31/2025
Air Conditioning Systems Heating Systems Ventilation Systems
FiledStatusContractorScopeMake / Model / Capacity
01/31/2025Signed-offSTATCON DEVELOPMENT LLCAir Conditioning Systems, Heating Systems, Ventilation Systems
Cooling
Comfortmaker CC: EAH1P42C - CU: R4A4S36AKAMAAAAC 35,000 BTU · Split System ×1
CC: EAH1P51C - CU: R4A4S60AKANAABAG 56,000 BTU · Split System ×1
Heating
Comfortmaker N80ESN0702116A 57,000 BTU · Furnace ×1
N80ESN1102120A2 76,000 BTU · Furnace ×1
Ventilation
Fantech FIT 70E 70 CFM · Erv ×1
HERO 150H-EC 170 CFM · Erv ×1
1 project · most recent 01/31/2025
Gas Storm Water/Sanitary
FiledStatusContractorScope
01/31/2025Signed-offQUALITY PLUMBING, INCGas, Storm, Water/Sanitary
1 project · most recent 09/04/2024
General Wiring
FiledStatusContractorScope
09/04/2024CompleteD AND H ELECTRICAL CONSTGeneral Wiring
1 project · most recent 01/31/2025
Wood
FiledStatusContractorScope
01/31/2025Signed-offSTATCON DEVELOPMENT LLCWood
▾Field Inspections (DOB CAP) — 11
DateTypeResultReport
03/18/2025Pass-Final Curb Cut Non-Directive 14PassView ↗
02/04/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
01/27/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
01/24/2025Pass-Final CND-Occupancy InspectionPassView ↗
08/14/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
07/17/2024Pass-Final PL - UndergroundPassView ↗
06/26/2024Certified Storm Drainage-ST-Fixtures-FinishCertifiedView ↗
06/21/2024Certified Storm Drainage-ST-Piping-UndergroundCertifiedView ↗
11/29/2023Fail-Final PL - Up to 3 Requested FloorsFailView ↗
07/11/2023Certified Gas-Gas-Piping-RoughingCertifiedView ↗
07/11/2023Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 21
DateRequirementInspectorRole
02/04/2025Maintenance informationStanislav Pilipenkoenergy_progress
02/04/2025HVAC-R and service water heating equipmentStanislav Pilipenkoenergy_progress
02/04/2025Private On-Site Storm Water Disposal Systems-, and Detention Facilities, InstallationStanislav Pilipenkospecial
02/04/2025Flood Zone Compliance (attach FEMA elevation/dry floodproofing certificate where applicable)Stanislav Pilipenkospecial
02/04/2025Energy Code Compliance InspectionsStanislav Pilipenkoprogress
02/04/2025HVAC-R and service water piping design and insulationStanislav Pilipenkoenergy_progress
02/04/2025HVAC-R and service water heating system controlsStanislav Pilipenkoenergy_progress
02/04/2025Permanent certificateStanislav Pilipenkoenergy_progress
05/29/2024Permanent certificateStanislav Pilipenkoenergy_progress
05/29/2024HVAC-R and service water piping design and insulationStanislav Pilipenkoenergy_progress
05/29/2024HVAC-R and service water heating equipmentStanislav Pilipenkoenergy_progress
05/29/2024Ventilation and air distribution systemStanislav Pilipenkoenergy_progress
05/29/2024Chimneys and ventsStanislav Pilipenkospecial
05/29/2024Fire-Resistant Penetrations and JointsStanislav Pilipenkospecial
05/29/2024Heating SystemsStanislav Pilipenkospecial
05/29/2024Energy Code Compliance InspectionsStanislav Pilipenkoprogress
05/29/2024Maintenance informationStanislav Pilipenkoenergy_progress
05/29/2024Duct leakage testing, insulation and designStanislav Pilipenkoenergy_progress
05/29/2024HVAC-R and service water heating system controlsStanislav Pilipenkoenergy_progress
05/25/2024Mechanical SystemsStanislav Pilipenkospecial
05/25/2024FinalStanislav Pilipenkoprogress
▾Documents — 54 on file (BIS + DOB NOW)
▸Plans & Drawings6
▸DOB NOWPlans/Sketch6
08/22/2026S00915681-S2Request digital key ↗
08/22/2026S00915681-S1Request digital key ↗
08/22/2026S00915681-I1Request digital key ↗
Showing 3 of 6 on file for this type
▸Applications & Permits2
▸BISBPP-5 - Authorization to the Department of Transportation1
11/09/2023540260563Open ↗
▸BISPLAN / WORK APPROVAL APPLICATION1
11/09/2023540260563Open ↗
▸Zoning, Tax Lot & Property Records6
▸DOB NOWZD1: DOB Zoning Diagram2
08/13/2026S00915681-P1Open ↗
08/13/2026S00915681-I1Open ↗
▸DOB NOWZoning Exhibit form (1-5)2
08/13/2026S00915681-P1Open ↗
08/13/2026S00915681-I1Open ↗
▸BISTAX LOT: TENTATIVE LOT NUMBER ISSUED1
11/24/2023540260563Open ↗
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/13/2026S00915681-I1Open ↗
▸Seals & Professional Certifications15
▸DOB NOWDPL-1: Design Professional Seal & Signature6
08/22/2026S00915681-I1Open ↗
08/22/2026S00915681-S2Open ↗
08/22/2026S00915681-S1Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWProgress Inspector Seal & Signature4
08/26/2026S00915681-S2Open ↗
08/26/2026S00915681-S2Open ↗
08/23/2026S00915681-S1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature3
08/26/2026S00915681-S2Open ↗
08/23/2026S00915681-S1Open ↗
08/23/2026S00915681-S1Open ↗
▸BISAPPLICANT OWNER SIGNATURE1
11/09/2023540260563Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
11/09/2023540260563Open ↗
▸Trade Schedules & Equipment2
▸DOB NOWDEP: Sewer Certification (Sanitary/Storm)2
08/13/2026S00915681-I1Open ↗
08/13/2026S00915681-P1Open ↗
▸Safety & Tenant Protection5
▸DOB NOWStreet Tree Checklist2
08/13/2026S00915681-I1Open ↗
08/13/2026S00915681-P1Open ↗
▸DOB NOWStreet Trees Site Plan1
08/13/2026S00915681-I1Open ↗
▸DOB NOWStreet Tree Sign Off1
08/13/2026S00915681-I1Open ↗
▸DOB NOWParks Department Acknowledgment Letter for Street Trees Plan1
08/13/2026S00915681-I1Open ↗
▸Inspections & Test Reports4
▸DOB NOWSOIL REPORT2
08/13/2026S00915681-I1Open ↗
08/13/2026S00915681-P1Open ↗
▸BISBPP-9 - Request for Builders Pavement Field Inspection1
11/09/2023540260563Open ↗
▸DOB NOWTR4 Test Report and Plot Diagram1
08/13/2026S00915681-I1Open ↗
▸Approvals, Objections & Sign-offs2
▸BISBPP-8 - Request Items for Builders Pavement Plan Signoff1
11/09/2023540260563Open ↗
▸BISNYS DEC FRESHWATER WETLANDS APPROVAL1
11/24/2023540260563Open ↗
▸Filing & Intake Forms1
▸BISEFILING JOB APPLICATION COVER SHEET1
11/09/2023540260563Open ↗
▸Other Documents11
▸DOB NOWSite Survey: Initial2
08/13/2026S00915681-I1Open ↗
08/13/2026S00915681-P1Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone2
08/13/2026S00915681-I1Open ↗
08/13/2026S00915681-P1Open ↗
▸DOB NOWProperty Ownership Certification2
08/22/2026S00915681-I1Open ↗
08/22/2026S00915681-P1Open ↗
▸BISBPP - DOT Builders Pavement Unit Waiver Request Form1
11/24/2023540260563Open ↗
▸BISNYS DEC FRESHWATER WETLANDS MAP1
11/24/2023540260563Open ↗
▸BISBPP - SUPPORTING DOCUMENTATION1
11/09/2023540260563Open ↗
▸DOB NOWFinal Survey1
08/13/2026S00915681-I1Open ↗
▸DOB NOWFEMA Elevation Certificate (086-0-33)/Flood Proofing Certificate (086-0-34)1
08/13/2026S00915681-I1Open ↗