← Back
BuildNYC
Factory, light manufacturing
23 WYTHE AVENUE
BROOKLYN · Greenpoint · BIN 3337782
💬 Discuss this project
1918Year Built
2Stories
F5Building Class
M1-2Zoning
27,806 sfGross Floor Area
14Units
8 Active Violations 0 unresolved · 8 paperwork only ▸FDNY Report ↗
Factory, light manufacturing · Owner of record: 72 North 15th Street Owner · 27,806 sf lot · 1 FAR built · Flood zone X500
Locations of Work
ArchitectureStructuralMechanicalFire ProtectionEquipmentGeneral
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Permit Issued — active, not yet Signed-off
RoofUnder Construction3p · 2 filings · 20 docs
BulkheadUnder Construction2p · 1 filing · 17 docs
Floor 2Under Construction4p · 1 filing · 17 docs
Floor 1Under Construction46p · 2 filings · 20 docs
MezzanineUnder Construction4p · 2 filings · 20 docs
Site & exteriorInstallation of sidewalk shedUnder Construction4p · 1 filing · 2 docs
Filed — no permit issuedConstruction fence installation4p · 1 filing · 2 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
Palm Tree Consulting1410/16/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
Vasilios Artemiou PE310/15/2026
Structure 22 Engineering108/31/2026
Volume Space Consulting108/14/2026
Adroit Engineering309/30/2025
Nikolai Katz Architect306/05/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
Express Filing503/21/2026
Avalon Designs603/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Lightforce Electrical Contng IElectrical103/22/2026
Crowbar IndustriesGeneral Contractor108/21/2026
Ace Group NYScaffold108/16/2026
Innovative Construction NYCScaffold107/22/2026
Bruche Mechanical NYFire Protection108/14/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Adroit Engineering8885209/30/2025
Building Lifecycle
All (80)Filed (11)Permit Issued (4)Objection (35)Special Inspection (30)
10/15/2026
Filed — New Building
INSTALLATION OF A TEMPORARY WOODEN CONSTRUCTION FENCE
B01214039-S7
10/15/2026
Special inspection requirement — Post-installed Anchors
10/15/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
10/15/2026
Special inspection requirement — Standpipe Systems
10/15/2026
Special inspection requirement — Sprinkler Systems
10/14/2026
Filed — New Building
INSTALLATION OF A TEMPORARY WOODEN CONSTRUCTION FENCE
B01214039-S6
10/13/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
10/13/2026
Special inspection requirement — HVAC-R and service water heating equipment
10/13/2026
Special inspection requirement — Maintenance information
10/13/2026
Special inspection requirement — HVAC-R and service water heating system controls
10/13/2026
Special inspection requirement — Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation
10/13/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
10/05/2026
Filed — New Building
INSTALLATION OF A TEMPORARY WOODEN CONSTRUCTION FENCE
B01214039-S5
09/24/2026
Special inspection requirement — Mechanical Systems
09/24/2026
Special inspection requirement — Shutoff dampers
09/24/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
09/24/2026
Special inspection requirement — Post-installed Anchors
09/24/2026
Special inspection requirement — Final
09/24/2026
Special inspection requirement — Energy Code Compliance Inspections
09/24/2026
Special inspection requirement — HVAC-R and service water heating equipment
09/24/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
09/24/2026
Special inspection requirement — HVAC-R and service water heating system controls
09/24/2026
Special inspection requirement — Maintenance information
09/24/2026
Special inspection requirement — Duct leakage testing, insulation and design
09/14/2026
Objection resolved — Resolved
09/11/2026
Objection raised — Other
09/11/2026
Objection raised — Scope
08/31/2026
Filed — New Building
INSTALLATION OF A TEMPORARY WOODEN CONSTRUCTION FENCE
B01214039-S3
08/31/2026
Special inspection requirement — Structural Steel - Details
08/31/2026
Special inspection requirement — Structural Steel - High Strength Bolting
08/31/2026
Special inspection requirement — Concrete - Cast-In-Place
08/31/2026
Special inspection requirement — Final
08/31/2026
Special inspection requirement — Structural Cold-Formed Steel
08/31/2026
Special inspection requirement — Structural Steel - Welding
08/20/2026
Permit issued — Full Demolition
B01223023-I1-FD
08/14/2026
Filed — Alteration
INSTALLATION OF 300 PSF SIDEWALK SHED AS PER PLANS. ALL EQUIPMENT SHALL COMPLY WITH CHAPTER #33 OF THE 2022 CODE. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
B01445816-I1
08/14/2026
Permit issued — Sidewalk Shed
B01445816-I1-SH
08/13/2026
Permit issued — Sprinklers
B01223023-S1-EW-SP
07/21/2026
Permit issued — Construction Fence
B01214039-S1-FN
04/20/2026
Objection resolved — Resolved
04/20/2026
Objection resolved — Addressed
03/13/2026
Objection resolved — Addressed
01/05/2026
Objection resolved — Addressed
12/23/2025
Special inspection requirement — Protection of exposed foundation insulation
11/13/2025
Objection resolved — Addressed
11/13/2025
Objection resolved — Addressed
11/13/2025
Objection resolved — Addressed
10/22/2025
Special inspection requirement — Electric vehicle service equipment requirements
10/16/2025
Objection resolved — Addressed
09/30/2025
Filed — Alteration
installation of 8' construction fence.
B01249961-I1
09/30/2025
Filed — Full Demolition
Full demolition of Existing 2 story Building.
B01223023-S1
09/30/2025
Objection resolved — Addressed
09/30/2025
Objection resolved — Addressed
09/15/2025
Objection resolved — Addressed
08/28/2025
Objection resolved — Addressed
08/28/2025
Objection resolved — Addressed
08/28/2025
Objection resolved — Addressed
07/22/2025
Objection resolved — Resolved
07/01/2025
Special inspection requirement — Sprinkler Systems
DUY HOANG
06/20/2025
Objection raised — Scope
Latest 60 of 80 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWFull DemolitionPermit IssuedCrowbar Industries08/20/2026
DOB NOWSidewalk ShedPermit IssuedAce Group NY08/14/2026
DOB NOWSprinklersPermit IssuedBruche Mechanical NY08/13/2026
DOB NOWConstruction FencePermit IssuedInnovative Construction NYC07/21/2026
2 projects · most recent 10/15/2026
Sprinkler System
FiledStatusContractorScope
10/15/2026——Sprinkler System
09/30/2025Permit IssuedPlumbing P & H1 heads
2 projects · most recent 10/15/2026
Storm Water/Sanitary
FiledStatusContractorScope
10/15/2026——Storm, Water/Sanitary
09/30/2025———
2 projects · most recent 08/13/2026
General Wiring
FiledStatusContractorScope
08/13/2026Permit IssuedHigh Quality Electric of NYC—
12/14/2025Permit IssuedLightforce Electrical Contng IGeneral Wiring
1 project · most recent 10/15/2026
Steel
FiledStatusContractorScope
10/15/2026Permit IssuedInnovative Construction NYCSteel
3 projects · most recent 10/15/2026
Fence Sidewalk Shed
FiledStatusContractorScope
10/15/2026Permit IssuedInnovative Construction NYCFence
08/14/2026Permit IssuedAce Group NYSidewalk Shed
09/30/2025——Fence
▾Special Inspection Requirements (DOB NOW) — 47
DateRequirementInspectorRole
10/15/2026Post-installed Anchors—special
10/15/2026Fire-Resistant Penetrations and Joints—special
10/15/2026Standpipe Systems—special
10/15/2026Sprinkler Systems—special
10/13/2026HVAC-R and service water piping design and insulation—energy_progress
10/13/2026HVAC-R and service water heating equipment—energy_progress
10/13/2026Maintenance information—energy_progress
10/13/2026HVAC-R and service water heating system controls—energy_progress
10/13/2026Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation—special
10/13/2026Fire-Resistant Penetrations and Joints—special
09/24/2026Mechanical Systems—special
09/24/2026Shutoff dampers—energy_progress
09/24/2026Fire-Resistant Penetrations and Joints—special
09/24/2026Post-installed Anchors—special
09/24/2026Final—progress
09/24/2026Energy Code Compliance Inspections—progress
09/24/2026HVAC-R and service water heating equipment—energy_progress
09/24/2026HVAC-R and service water piping design and insulation—energy_progress
09/24/2026HVAC-R and service water heating system controls—energy_progress
09/24/2026Maintenance information—energy_progress
09/24/2026Duct leakage testing, insulation and design—energy_progress
08/31/2026Structural Steel - Details—special
08/31/2026Structural Steel - High Strength Bolting—special
08/31/2026Concrete - Cast-In-Place—special
08/31/2026Final—progress
Latest 25 of 47.
▾Documents — 47 on file (BIS + DOB NOW)
▸Plans & Drawings7
▸DOB NOWPlans/Sketch7
08/21/2026B01214039-S1Request digital key ↗
08/21/2026B01214039-I1Request digital key ↗
08/21/2026B01214039-S2Request digital key ↗
Showing 3 of 7 on file for this type
▸Applications & Permits3
▸BISPLAN / WORK APPROVAL APPLICATION2
06/25/2025340918680Open ↗
06/24/2025340918680Open ↗
▸BISBPP-5 - Authorization to the Department of Transportation1
06/24/2025340918680Open ↗
▸Zoning, Tax Lot & Property Records6
▸DOB NOWRestrictive Declaration/Easement 13
09/15/2026B01214039-S3Open ↗
08/21/2026B01214039-I1Open ↗
08/13/2026B01214039-S2Open ↗
▸DOB NOWZD1: DOB Zoning Diagram1
08/21/2026B01214039-I1Open ↗
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/21/2026B01214039-I1Open ↗
▸DOB NOWZoning Exhibit form (1-5)1
08/21/2026B01214039-I1Open ↗
▸Seals & Professional Certifications11
▸DOB NOWDPL-1: Design Professional Seal & Signature8
09/15/2026B01214039-S3Open ↗
08/21/2026B01214039-S1Open ↗
08/21/2026B01214039-I1Open ↗
Showing 3 of 8 on file for this type
▸BISAPPLICANT OWNER SIGNATURE1
06/24/2025340918680Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
06/24/2025340918680Open ↗
▸DOB NOWSpecial Inspector Seal & Signature1
08/22/2026B01223023-S1Open ↗
▸Trade Schedules & Equipment4
▸DOB NOWElectric Cut-Off1
08/20/2026B01223023-I1Open ↗
▸DOB NOWWater Cut-Off1
08/20/2026B01223023-I1Open ↗
▸DOB NOWGas Cut-Off1
08/20/2026B01223023-I1Open ↗
▸DOB NOWSewer Cut-Off1
08/20/2026B01223023-I1Open ↗
▸Safety & Tenant Protection3
▸BISBPP: STREET TREES SITE PLAN1
06/24/2025340918680Open ↗
▸BISSTREET TREE CHECKLIST1
06/24/2025340918680Open ↗
▸DOB NOWStreet Tree Checklist1
08/21/2026B01214039-I1Open ↗
▸Environmental & Asbestos3
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
08/20/2026B01223023-S1Open ↗
08/20/2026B01223023-I1Open ↗
▸DOB NOWRodent Control1
08/20/2026B01223023-I1Open ↗
▸Filing & Intake Forms2
▸BISEFILING JOB APPLICATION COVER SHEET1
06/24/2025340918680Open ↗
▸BISBPP: CHECKLIST IN LIEU OF PLANS-ALT31
06/24/2025340918680Open ↗
▸Other Documents8
▸DOB NOWProperty Ownership Certification2
08/21/2026B01214039-I1Open ↗
08/20/2026B01223023-I1Open ↗
▸BISBPP - SUPPORTING DOCUMENTATION1
06/24/2025340918680Open ↗
▸DOB NOWCommunity Board Notification1
08/20/2026B01223023-I1Open ↗
▸DOB NOWFull Demo: 10-Day Notice1
08/20/2026B01223023-I1Open ↗
▸DOB NOWStructure Photographs1
08/13/2026B01223023-I1Open ↗
▸DOB NOWSite Survey: Initial1
08/21/2026B01214039-I1Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone1
08/21/2026B01214039-I1Open ↗