1925Year Built
2Stories
C0Building Class
R3-1Zoning
2,160 sfGross Floor Area
3Units
1 Active Violation ▸FDNY Report ↗
Three families · 2,500 sf lot · 0.86 FAR built · Flood zone X500
Locations of Work
Electrical
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
RoofResidential solar electric generation array installation1 filing · 7 docs
Floor 11 filing · 3 docs
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
12/19/2023$815K—— → —$377/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
Safiya Consultants112/12/2024
Momentum Solar101/30/2024
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
MXV Sia9281101/30/2024
Building Lifecycle
All (15)Filed (2)Permit Issued (1)Signed Off (1)Violation (1)Objection (5)Special Inspection (5)
01/22/2025
Signed off — Alteration
Installation of solar panels; Rooftop, Railed, Grid tied, 14 Panels, 5.6 kW
Q00985030-I1
12/19/2024
Objection raised — Zoning
12/12/2024
Filed — Alteration
RESTORE EXTENDED PORTION OF CURB CUT TO ORIGINAL LEGAL CONDITION TO CURE ECB VIOLATION 35667947X.
Q01152654-I1
10/09/2024
Violation issued (ECB, open)
Construction
02/28/2024
Permit issued — Solar
Q00985030-I1-SL
02/16/2024
Objection resolved — Addressed
02/14/2024
Objection resolved — Addressed
02/06/2024
Objection raised — Other
02/06/2024
Objection raised — Other
01/30/2024
Filed — Alteration
Installation of solar panels; Rooftop, Railed, Grid tied, 14 Panels, 5.6 kW
Q00985030-I1
01/03/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
Mina Makar
01/03/2024
Special inspection requirement — Structural Stability – Alterations of existing buildings
Mina Makar
01/03/2024
Special inspection requirement — Energy Code Compliance Inspections
Mina Makar
01/03/2024
Special inspection requirement — Final
Mina Makar
01/03/2024
Special inspection requirement — Air barrier - visual inspection
Mina Makar
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offMomentum Solar02/28/2024
1 project · most recent 01/09/2024
FiledStatusContractorScope
01/09/2024CompleteIsland Electric—
▾Special Inspection Requirements (DOB NOW) — 5
DateRequirementInspectorRole
01/03/2024Fire-Resistant Penetrations and JointsMina Makarspecial
01/03/2024Structural Stability – Alterations of existing buildingsMina Makarspecial
01/03/2024Energy Code Compliance InspectionsMina Makarprogress
01/03/2024FinalMina Makarprogress
01/03/2024Air barrier - visual inspectionMina Makarenergy_progress
▾Documents — 9 on file (BIS + DOB NOW)
▸Plans & Drawings2
▸DOB NOWPlans/Sketch2
08/23/2026Q00985030-I1Request digital key ↗
08/21/2026Q01152654-I1Request digital key ↗
▸Seals & Professional Certifications5
▸DOB NOWDPL-1: Design Professional Seal & Signature2
08/21/2026Q01152654-I1Open ↗
08/13/2026Q00985030-I1Open ↗
▸DOB NOWProgress Inspector Seal & Signature2
08/31/2026Q00985030-I1Open ↗
08/31/2026Q00985030-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature1
08/31/2026Q00985030-I1Open ↗
▸Environmental & Asbestos1
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/13/2026Q00985030-I1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/13/2026Q00985030-I1Open ↗