| Owner | Filings | Most Recent |
|---|---|---|
| PROLOGIS | 55 | 07/08/2026 |
| GA INDUSTRIES | 3 | 03/22/2026 |
| AMB FUND III NEW YOR | 1 | 03/22/2026 |
| AMB PROPERTY L P | 3 | 03/22/2026 |
| ONE MEADOWLANDS PLAZA SUITE 100 | 2 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| TECTONIC ENGINEERING | 3 | 06/24/2026 |
| VALENTINO POMPEO ARCHITECT, P.C. | 6 | 09/24/2024 |
| HC ARCHITECT, PC | 2 | 01/10/2024 |
| JLS DESIGNS | 1 | 12/05/2023 |
| SPARC FIRE PROTECTION ENGINEERING | 1 | 11/04/2022 |
| CAESAR BUSTAMANTE, AIA | 3 | 10/27/2022 |
| F.P.VILLANO CONSULTING ENGINEER LLC | 2 | 11/19/2020 |
| Representative | Filings | Most Recent |
|---|---|---|
| JP EXPEDITE | 4 | 03/21/2026 |
| RIZZO GROUP | 3 | 03/21/2026 |
| LOUIS STRIAR | 4 | 03/21/2026 |
| CAESAR BUSTAMANTE, AIA | 3 | 03/21/2026 |
| INTEGRATED C O MILROSE CONSULTANTS | 3 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| TRANE U.S. INC | General Contractor | 7 | 07/08/2026 |
| GA INDUSTRIES INC | General Contractor | 5 | 07/08/2026 |
| J.V.S. SPRINT ENTERPRISES | General Contractor | 5 | 07/08/2026 |
| SIGNS CAD | Scaffold | 4 | 07/08/2026 |
| FIVE BOROUGH NYC | Plumbing | 2 | 03/22/2026 |
| P & D MECHANICAL CORP | Fire Protection | 1 | 07/08/2026 |
| FIVE BOROUGH NYC LLC | Fire Protection | 1 | 07/08/2026 |
| ECNY ELEC'L CONTR'S, INC | Electrical | 1 | 03/22/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| TECTONIC ENGINEERING CONS | 106 | 6 | 06/24/2026 |
| O'ROURKE ENGINEERING, LLC | 5873 | 2 | 09/24/2024 |
| VALENTINO POMPEO ARCHITEC | 1013 | 2 | 09/24/2024 |
| MILROSE CONSULTANTS LLC | 2003 | 3 | 10/27/2022 |
| C.M. TESTING LABORATORY, | 1352 | 1 | 08/18/2021 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Permit Issued | GA INDUSTRIES INC | 11/13/2024 |
| DOB NOW | Sprinklers | Signed-off | FIVE BOROUGH NYC LLC | 02/29/2024 |
| DOB NOW | Mechanical Systems | Signed-off | J.V.S. SPRINT ENTERPRISES | 02/12/2024 |
| DOB NOW | Sign | Signed-off | SIGNS CAD CORP | 01/11/2024 |
| DOB NOW | Sign | Signed-off | SIGNS CAD CORP | 01/11/2024 |
| DOB NOW | Construction Fence | Permit Issued | GA INDUSTRIES INC | 12/21/2023 |
| DOB NOW | General Construction | Permit Issued | GA INDUSTRIES INC | 12/05/2023 |
| DOB NOW | Mechanical Systems | Signed-off | TRANE U.S. INC | 05/04/2023 |
| DOB NOW | Mechanical Systems | Signed-off | TRANE U.S. INC | 03/20/2023 |
| DOB NOW | Mechanical Systems | Signed-off | TRANE U.S. INC | 10/31/2022 |
| DOB NOW | General Construction | Signed-off | J.V.S. SPRINT ENTERPRISES | 12/02/2021 |
| DOB NOW | Sprinklers | Permit Issued | P & D MECHANICAL CORP | 11/17/2021 |
| DOB NOW | General Construction | Signed-off | J.V.S. SPRINT ENTERPRISES | 07/23/2021 |
| DOB NOW | Mechanical Systems | Signed-off | TRANE U.S. INC | 07/12/2021 |
| DOB NOW | Sign | Signed-off | SIGNS CAD CORP | 12/17/2020 |
| DOB NOW | Sign | Signed-off | SIGNS CAD CORP | 12/11/2020 |
| BIS | OT | ISSUED | ECNY ELECTRICAL CONTRACT* | 10/21/2020 |
| BIS | OT | ISSUED | J.V.S. SPRINT ENTERPRISES | 06/01/2017 |
| BIS | PL | ISSUED | VARSITY PLBG AND HTG INC | 06/01/2017 |
| BIS | SP | ISSUED | ACCURATE MECHANICAL INC | 02/08/2017 |
| BIS | MH | ISSUED | J.V.S. SPRINT ENTERPRISES | 01/20/2017 |
| BIS | OT | ISSUED | J.V.S. SPRINT ENTERPRISES | 01/20/2017 |
| BIS | — | ISSUED | MAUCERI SIGN CO., INC | 04/22/2015 |
| BIS | SP | ISSUED | PAT SEMENTA P&H CO INC | 10/15/2014 |
| BIS | — | ISSUED | MAUCERI SIGN CO., INC | 06/11/2014 |
| BIS | MH | ISSUED | J.V.S. SPRINT ENTERPRISES | 04/30/2014 |
| BIS | — | ISSUED | SIGNSTAR NYC | 07/17/2013 |
| BIS | OT | ISSUED | SIGN STAR NYC | 07/17/2013 |
| BIS | — | ISSUED | SIGNSTAR NYC | 07/17/2013 |
| BIS | OT | ISSUED | SIGN STAR NYC | 07/15/2013 |
| BIS | OT | ISSUED | IDEAL CONSTRUCTION | 05/24/2005 |
| BIS | OT | ISSUED | VRH CONSTRUCTION CORP | 12/15/2004 |
| BIS | PL | ISSUED | PACE PLG CORP | 03/12/2003 |
| BIS | SP | ISSUED | SIRINA FIRE PROTECTIONC O | 03/06/2003 |
| BIS | MH | ISSUED | VRH CONSTRUCTION CORP | 02/27/2003 |
| BIS | — | ISSUED | GOING SIGN & SVCNG CO,INC | 02/06/2003 |
| BIS | OT | ISSUED | VRH CONSTRUCTION CORP | 02/06/2003 |
| BIS | SP | ISSUED | SIRINA FIRE PROTECTION CORP | 01/22/2003 |
| BIS | SP | ISSUED | SIRINA FIRE PROTECTION CORP | 01/22/2003 |
| BIS | PL | ISSUED | PACE PLUMBING CORP | 01/09/2003 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 09/24/2024 | Signed-off | J.V.S. SPRINT ENTERPRISES | Heating and Air Conditioning Systems | Heat / Cool Carrier CARRIER 38MPRB 90,000 BTU · Heat Pump Outdoor ×2 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/24/2024 | Signed-off | FIVE BOROUGH NYC LLC | Sprinkler System |
| 08/18/2021 | Permit Issued | CMP PIPING INC | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/18/2023 | Complete | ANCO ELECTL CONTCTNG INC | General Wiring |
| 05/06/2022 | Cancelled | HUNTER ELECTRIC, INC. | General Wiring |
| 01/20/2021 | Cancelled | L.E.B. ELECTRIC LTD | General Wiring |
| 09/23/2020 | Complete | ECNY ELEC'L CONTR'S, INC | 1 meters, 1 new_meters |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/24/2026 | Permit Issued | GA INDUSTRIES INC | Steel, Concrete |
| 09/08/2023 | Permit Issued | GA INDUSTRIES INC | Concrete |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/05/2023 | Permit Issued | GA INDUSTRIES INC | Fence |
| Date | Type | Result | Report |
|---|---|---|---|
| 03/03/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 03/03/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 11/15/2024 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 03/01/2024 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 01/10/2024 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 04/12/2023 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 04/12/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 04/12/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 09/27/2024 | Final | VALENTINO POMPEO | progress |
| 09/27/2024 | Fire-Resistant Penetrations and Joints | VALENTINO POMPEO | special |
| 09/27/2024 | Mechanical Systems | VALENTINO POMPEO | special |
| 09/26/2024 | Sprinkler Systems | BRIAN O'ROURKE | special |
| 09/19/2024 | Sprinkler Systems | BRIAN O'ROURKE | special |
| 09/19/2024 | Mechanical Systems | VALENTINO POMPEO | special |
| 09/19/2024 | Final | VALENTINO POMPEO | progress |
| 09/19/2024 | Fire-Resistant Penetrations and Joints | VALENTINO POMPEO | special |
| 10/13/2023 | Final | Hackjong Choi | progress |
| 09/01/2023 | Post-installed Anchors | GEORGE GHEBRYAL | special |
| 09/01/2023 | Concrete - Cast-In-Place | GEORGE GHEBRYAL | special |
| 08/22/2023 | Final | GEORGE GHEBRYAL | progress |
| 10/05/2022 | HVAC-R and service water heating equipment | CAESAR BUSTAMANTE | energy_progress |
| 10/05/2022 | Maintenance information | CAESAR BUSTAMANTE | energy_progress |
| 10/05/2022 | HVAC-R and service water heating system controls | CAESAR BUSTAMANTE | energy_progress |
| 10/05/2022 | HVAC-R and service water piping design and insulation | CAESAR BUSTAMANTE | energy_progress |
| 09/26/2022 | Final | CAESAR BUSTAMANTE | progress |
| 09/26/2022 | Mechanical Systems | CAESAR BUSTAMANTE | special |
| 10/14/2021 | HVAC-R and service water heating equipment | CAESAR BUSTAMANTE | energy_progress |
| 10/14/2021 | Maintenance information | CAESAR BUSTAMANTE | energy_progress |
| 10/14/2021 | HVAC-R and service water heating system controls | CAESAR BUSTAMANTE | energy_progress |
| 10/14/2021 | Energy Code Compliance Inspections | CAESAR BUSTAMANTE | progress |
| 10/14/2021 | Final | CAESAR BUSTAMANTE | progress |
| 10/14/2021 | Mechanical Systems | CAESAR BUSTAMANTE | special |
| 10/14/2021 | HVAC-R and service water piping design and insulation | CAESAR BUSTAMANTE | energy_progress |
| Tenant | Space | Floors | Renovation projects |
|---|---|---|---|
| Nippon Express | Office | Floors 1–5 | Project Q00395868 |