← Back
Miscellaneous warehouse
JFK Log Center A
230-19 ROCKAWAY BOULEVARD · BIN 4575277
💬 Discuss this project
2002Year Built
1Stories
E9Building Class
M1-1Zoning
97,721 sfGross Floor Area
1Units
LL97 Covered0 Open ViolationsFDNY Report ↗
Miscellaneous warehouse · Owner of record: AMB FUND III NEW YOR · 225,753 sf lot · 0.43 FAR built · Flood zone X500
Locations of Work
ArchitectureElectricalMechanicalFire ProtectionGeneral
Roof3p · 2 filings · 20 docs
Floor 116p · 1 filing · 17 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
PROLOGIS5507/08/2026
GA INDUSTRIES303/22/2026
AMB FUND III NEW YOR103/22/2026
AMB PROPERTY L P303/22/2026
ONE MEADOWLANDS PLAZA SUITE 100203/21/2026
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
JP EXPEDITE403/21/2026
RIZZO GROUP303/21/2026
LOUIS STRIAR403/21/2026
CAESAR BUSTAMANTE, AIA303/21/2026
INTEGRATED C O MILROSE CONSULTANTS303/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
TRANE U.S. INCGeneral Contractor707/08/2026
GA INDUSTRIES INCGeneral Contractor507/08/2026
J.V.S. SPRINT ENTERPRISESGeneral Contractor507/08/2026
SIGNS CADScaffold407/08/2026
FIVE BOROUGH NYCPlumbing203/22/2026
P & D MECHANICAL CORPFire Protection107/08/2026
FIVE BOROUGH NYC LLCFire Protection107/08/2026
ECNY ELEC'L CONTR'S, INCElectrical103/22/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
TECTONIC ENGINEERING CONS106606/24/2026
O'ROURKE ENGINEERING, LLC5873209/24/2024
VALENTINO POMPEO ARCHITEC1013209/24/2024
MILROSE CONSULTANTS LLC2003310/27/2022
C.M. TESTING LABORATORY,1352108/18/2021
Building Lifecycle
All (137)Filed (18)Permit Issued (16)Signed Off (8)Violation (26)Inspection (8)Objection (34)Special Inspection (27)
08/20/2026
Objection resolved — Resolved
07/31/2026
Objection raised — Scope
06/24/2026
Filed — Alteration
General construction and structural modifications to outside space as per plans filed herewith. No change in use, egress, or occupancy.
Q00793534-P1
10/01/2025
Violation issued (FDNY_ORDER, closed)
07/23/2025
Violation issued (FDNY_ORDER, closed)
06/27/2025
Signed off — Alteration
REPLACE NON-ILLUMINATED ACCESSORY BUSINESS CABINET WALL SIGN-B, REMOVE A PREVIOUS SIGN #Q00395868-I1, 42 S.F., NON-FLASHING, NON-ADVERTISING SIGN, NO CHANGE IN USE, EGRESS, OR OCCUPANCY
Q00947976-I1
06/27/2025
Signed off — Alteration
REPLACE NON-ILLUMINATED ACCESSORY BUSINESS CABINET WALL SIGN-B, REMOVE A PREVIOUS SIGN #Q00395868-I1, 42 S.F., NON-FLASHING, NON-ADVERTISING SIGN, NO CHANGE IN USE, EGRESS, OR OCCUPANCY
Q00947976-S1
03/03/2025
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
03/03/2025
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
11/24/2024
Signed off — Alteration
PROPOSED ALTERATION OF EXISTING SPRINKLER SYSTEM, PROPOSED SPRINKLER HEADS PER PLANS. NO CHANGE OF USE, EGRESS OR OCCUPANCY.
Q00966694-I1
11/24/2024
Signed off — Alteration
Q00552258-I1
11/15/2024
Inspection — Pass-Final General Construction Non-Directive 14
Pass
View inspection ↗
11/13/2024
Permit issued — General Construction
Q00793534-I1-GC-CX
09/27/2024
Special inspection requirement — Final
VALENTINO POMPEO
09/27/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
VALENTINO POMPEO
09/27/2024
Special inspection requirement — Mechanical Systems
VALENTINO POMPEO
09/26/2024
Special inspection requirement — Sprinkler Systems
BRIAN O'ROURKE
09/24/2024
Filed — Alteration
PROPOSED ALTERATION OF EXISTING SPRINKLER SYSTEM, PROPOSED SPRINKLER HEADS PER PLANS. NO CHANGE OF USE, EGRESS OR OCCUPANCY.
Q00966694-P2
09/24/2024
Filed — Alteration
PROPOSED ALTERATION OF EXISTING SPRINKLER SYSTEM, PROPOSED SPRINKLER HEADS PER PLANS. NO CHANGE OF USE, EGRESS OR OCCUPANCY.
Q00966694-P1
09/19/2024
Special inspection requirement — Sprinkler Systems
BRIAN O'ROURKE
09/19/2024
Special inspection requirement — Mechanical Systems
VALENTINO POMPEO
09/19/2024
Special inspection requirement — Final
VALENTINO POMPEO
09/19/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
VALENTINO POMPEO
03/01/2024
Inspection — Fail-Final PL - Up to 3 Requested Floors
Fail
View inspection ↗
02/29/2024
Permit issued — Sprinklers
Q00966694-S1-EW-SP
02/12/2024
Permit issued — Mechanical Systems
Q00966694-I1-GC-CX
01/24/2024
Objection raised — Other
01/24/2024
Objection resolved — Addressed
01/23/2024
Objection raised — Other
01/23/2024
Objection resolved — Addressed
01/15/2024
Filed — Alteration
PROPOSED ALTERATION OF EXISTING SPRINKLER SYSTEM, PROPOSED SPRINKLER HEADS PER PLANS. NO CHANGE OF USE, EGRESS OR OCCUPANCY.
Q00966694-S1
01/15/2024
Objection resolved — Addressed
01/15/2024
Objection resolved — Addressed
01/11/2024
Permit issued — Sign
Q00947976-S1-SG
01/11/2024
Permit issued — Sign
Q00947976-I1-SG
01/10/2024
Filed — Alteration
REPLACE NON-ILLUMINATED ACCESSORY BUSINESS CABINET WALL SIGN-B, REMOVE A PREVIOUS SIGN #Q00395868-I1, 42 S.F., NON-FLASHING, NON-ADVERTISING SIGN, NO CHANGE IN USE, EGRESS, OR OCCUPANCY
Q00947976-I1
01/10/2024
Filed — Alteration
REPLACE NON-ILLUMINATED ACCESSORY BUSINESS CABINET WALL SIGN-B, REMOVE A PREVIOUS SIGN #Q00395868-I1, 42 S.F., NON-FLASHING, NON-ADVERTISING SIGN, NO CHANGE IN USE, EGRESS, OR OCCUPANCY
Q00947976-S1
01/10/2024
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
01/10/2024
Objection raised — Fire_Protection
01/10/2024
Objection raised — Other
12/21/2023
Filed — Alteration
PROPOSED ALTERATION OF EXISTING SPRINKLER SYSTEM, PROPOSED SPRINKLER HEADS PER PLANS. NO CHANGE OF USE, EGRESS OR OCCUPANCY.
Q00966694-I1
12/21/2023
Permit issued — Construction Fence
Q00970636-I1-FN
12/14/2023
Objection resolved — Addressed
12/14/2023
Objection resolved — Addressed
12/12/2023
Objection raised — Structural
12/07/2023
Objection raised — Other
12/05/2023
Filed — Alteration
installation of temp construction fence
Q00970636-I1
12/05/2023
Permit issued — General Construction
Q00923217-I1-GC
10/13/2023
Special inspection requirement — Final
Hackjong Choi
10/05/2023
Objection resolved — Addressed
09/25/2023
Objection resolved — Addressed
09/25/2023
Objection resolved — Addressed
09/25/2023
Objection resolved — Addressed
09/20/2023
Objection raised — Scope
09/20/2023
Objection raised — Other
09/20/2023
Objection resolved — Addressed
09/18/2023
Objection raised — Admin
09/18/2023
Objection raised — Admin
09/18/2023
Objection raised — Other
09/08/2023
Filed — Alteration
General construction and structural modifications to outside space as per plans filed herewith. No change in use, egress, or occupancy.
Q00923217-I1
Latest 60 of 137 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionPermit IssuedGA INDUSTRIES INC11/13/2024
DOB NOWSprinklersSigned-offFIVE BOROUGH NYC LLC02/29/2024
DOB NOWMechanical SystemsSigned-offJ.V.S. SPRINT ENTERPRISES02/12/2024
DOB NOWSignSigned-offSIGNS CAD CORP01/11/2024
DOB NOWSignSigned-offSIGNS CAD CORP01/11/2024
DOB NOWConstruction FencePermit IssuedGA INDUSTRIES INC12/21/2023
DOB NOWGeneral ConstructionPermit IssuedGA INDUSTRIES INC12/05/2023
DOB NOWMechanical SystemsSigned-offTRANE U.S. INC05/04/2023
DOB NOWMechanical SystemsSigned-offTRANE U.S. INC03/20/2023
DOB NOWMechanical SystemsSigned-offTRANE U.S. INC10/31/2022
DOB NOWGeneral ConstructionSigned-offJ.V.S. SPRINT ENTERPRISES12/02/2021
DOB NOWSprinklersPermit IssuedP & D MECHANICAL CORP11/17/2021
DOB NOWGeneral ConstructionSigned-offJ.V.S. SPRINT ENTERPRISES07/23/2021
DOB NOWMechanical SystemsSigned-offTRANE U.S. INC07/12/2021
DOB NOWSignSigned-offSIGNS CAD CORP12/17/2020
DOB NOWSignSigned-offSIGNS CAD CORP12/11/2020
BISOTISSUEDECNY ELECTRICAL CONTRACT*10/21/2020
BISOTISSUEDJ.V.S. SPRINT ENTERPRISES06/01/2017
BISPLISSUEDVARSITY PLBG AND HTG INC06/01/2017
BISSPISSUEDACCURATE MECHANICAL INC02/08/2017
BISMHISSUEDJ.V.S. SPRINT ENTERPRISES01/20/2017
BISOTISSUEDJ.V.S. SPRINT ENTERPRISES01/20/2017
BIS—ISSUEDMAUCERI SIGN CO., INC04/22/2015
BISSPISSUEDPAT SEMENTA P&H CO INC10/15/2014
BIS—ISSUEDMAUCERI SIGN CO., INC06/11/2014
BISMHISSUEDJ.V.S. SPRINT ENTERPRISES04/30/2014
BIS—ISSUEDSIGNSTAR NYC07/17/2013
BISOTISSUEDSIGN STAR NYC07/17/2013
BIS—ISSUEDSIGNSTAR NYC07/17/2013
BISOTISSUEDSIGN STAR NYC07/15/2013
BISOTISSUEDIDEAL CONSTRUCTION05/24/2005
BISOTISSUEDVRH CONSTRUCTION CORP12/15/2004
BISPLISSUEDPACE PLG CORP03/12/2003
BISSPISSUEDSIRINA FIRE PROTECTIONC O03/06/2003
BISMHISSUEDVRH CONSTRUCTION CORP02/27/2003
BIS—ISSUEDGOING SIGN & SVCNG CO,INC02/06/2003
BISOTISSUEDVRH CONSTRUCTION CORP02/06/2003
BISSPISSUEDSIRINA FIRE PROTECTION CORP01/22/2003
BISSPISSUEDSIRINA FIRE PROTECTION CORP01/22/2003
BISPLISSUEDPACE PLUMBING CORP01/09/2003
+ 12 more permits on file
1 project · most recent 09/24/2024
Heating and Air Conditioning Systems
FiledStatusContractorScopeMake / Model / Capacity
09/24/2024Signed-offJ.V.S. SPRINT ENTERPRISESHeating and Air Conditioning Systems
Heat / Cool
Carrier CARRIER 38MPRB 90,000 BTU · Heat Pump Outdoor ×2
2 projects · most recent 09/24/2024
Sprinkler System
FiledStatusContractorScope
09/24/2024Signed-offFIVE BOROUGH NYC LLCSprinkler System
08/18/2021Permit IssuedCMP PIPING INC—
4 projects · most recent 12/18/2023
General Wiring
FiledStatusContractorScope
12/18/2023CompleteANCO ELECTL CONTCTNG INCGeneral Wiring
05/06/2022CancelledHUNTER ELECTRIC, INC.General Wiring
01/20/2021CancelledL.E.B. ELECTRIC LTDGeneral Wiring
09/23/2020CompleteECNY ELEC'L CONTR'S, INC1 meters, 1 new_meters
2 projects · most recent 06/24/2026
Concrete Steel
FiledStatusContractorScope
06/24/2026Permit IssuedGA INDUSTRIES INCSteel, Concrete
09/08/2023Permit IssuedGA INDUSTRIES INCConcrete
1 project · most recent 12/05/2023
Fence
FiledStatusContractorScope
12/05/2023Permit IssuedGA INDUSTRIES INCFence
▾Field Inspections (DOB CAP) — 8
DateTypeResultReport
03/03/2025Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
03/03/2025Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
11/15/2024Pass-Final General Construction Non-Directive 14PassView ↗
03/01/2024Fail-Final PL - Up to 3 Requested FloorsFailView ↗
01/10/2024Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
04/12/2023Certified Gas-Gas-Piping-RoughingCertifiedView ↗
04/12/2023Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
04/12/2023Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 27
DateRequirementInspectorRole
09/27/2024FinalVALENTINO POMPEOprogress
09/27/2024Fire-Resistant Penetrations and JointsVALENTINO POMPEOspecial
09/27/2024Mechanical SystemsVALENTINO POMPEOspecial
09/26/2024Sprinkler SystemsBRIAN O'ROURKEspecial
09/19/2024Sprinkler SystemsBRIAN O'ROURKEspecial
09/19/2024Mechanical SystemsVALENTINO POMPEOspecial
09/19/2024FinalVALENTINO POMPEOprogress
09/19/2024Fire-Resistant Penetrations and JointsVALENTINO POMPEOspecial
10/13/2023FinalHackjong Choiprogress
09/01/2023Post-installed AnchorsGEORGE GHEBRYALspecial
09/01/2023Concrete - Cast-In-PlaceGEORGE GHEBRYALspecial
08/22/2023FinalGEORGE GHEBRYALprogress
10/05/2022HVAC-R and service water heating equipmentCAESAR BUSTAMANTEenergy_progress
10/05/2022Maintenance informationCAESAR BUSTAMANTEenergy_progress
10/05/2022HVAC-R and service water heating system controlsCAESAR BUSTAMANTEenergy_progress
10/05/2022HVAC-R and service water piping design and insulationCAESAR BUSTAMANTEenergy_progress
09/26/2022FinalCAESAR BUSTAMANTEprogress
09/26/2022Mechanical SystemsCAESAR BUSTAMANTEspecial
10/14/2021HVAC-R and service water heating equipmentCAESAR BUSTAMANTEenergy_progress
10/14/2021Maintenance informationCAESAR BUSTAMANTEenergy_progress
10/14/2021HVAC-R and service water heating system controlsCAESAR BUSTAMANTEenergy_progress
10/14/2021Energy Code Compliance InspectionsCAESAR BUSTAMANTEprogress
10/14/2021FinalCAESAR BUSTAMANTEprogress
10/14/2021Mechanical SystemsCAESAR BUSTAMANTEspecial
10/14/2021HVAC-R and service water piping design and insulationCAESAR BUSTAMANTEenergy_progress
Latest 25 of 27.
▾Tenants in the building
TenantSpaceFloorsRenovation projects
Nippon ExpressOfficeFloors 1–5
Project Q00395868 Alteration · LOC Issued · 11/19/2020
Read from each project’s drawing title blocks and cover sheets and checked twice; a name appears only when it is the occupant, never the owner, landlord or designer.
▾Documents — 302 on file (BIS + DOB NOW)
▸Plans & Drawings18
▸DOB NOWPlans/Sketch16
08/27/2026Q00552258-I1Request digital key ↗
08/27/2026Q00566387-I1Request digital key ↗
08/27/2026Q00542855-I1Request digital key ↗
Showing 3 of 16 on file for this type
▸DOB NOWPlans/Sketch - Sign2
08/27/2026Q00395864-I1Request digital key ↗
08/27/2026Q00395868-I1Request digital key ↗
▸Applications & Permits39
▸BISPLAN / WORK APPROVAL APPLICATION24
08/24/2021440604712Open ↗
07/09/2020440604712Open ↗
06/06/2017421337770Open ↗
Showing 3 of 24 on file for this type
▸BISWORK PERMIT APPLICATION15
10/22/2020440604712Open ↗
06/07/2017421337770Open ↗
06/06/2017421337770Open ↗
Showing 3 of 15 on file for this type
▸Zoning, Tax Lot & Property Records1
▸BISFLOOD ZONE DESIGN CERTIFICATION1
07/09/2020440604712Open ↗
▸Seals & Professional Certifications102
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION39
11/23/2018420996051Open ↗
01/22/2018421337770Open ↗
06/14/2017421421704Open ↗
Showing 3 of 39 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature18
08/27/2026Q00395864-I1Open ↗
08/27/2026Q00395868-I1Open ↗
08/27/2026Q00552258-I1Open ↗
Showing 3 of 18 on file for this type
▸DOB NOWProgress Inspector Seal & Signature14
09/01/2026Q00923217-I1Open ↗
09/01/2026Q00947976-S1Open ↗
09/01/2026Q00966694-P2Open ↗
Showing 3 of 14 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST9
06/15/2017421421704Open ↗
06/06/2017421337770Open ↗
04/29/2015421153030Open ↗
Showing 3 of 9 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature9
09/17/2026Q00966694-P1Open ↗
09/01/2026Q00923217-I1Open ↗
09/01/2026Q00966694-P2Open ↗
Showing 3 of 9 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT7
06/06/2017421337770Open ↗
01/17/2017421421704Open ↗
01/17/2017421421704Open ↗
Showing 3 of 7 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISProfessional and Owner Certification (POC3)1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISAPPLICANT OWNER SIGNATURE1
07/09/2020440604712Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
07/09/2020440604712Open ↗
▸Trade Schedules & Equipment15
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE5
06/06/2017421337770Open ↗
01/17/2017421421704Open ↗
05/30/2014420976359Open ↗
Showing 3 of 5 on file for this type
▸BISEQUIPMENT USE PERMITS4
06/08/2015420976340Open ↗
06/08/2015420976340Open ↗
06/08/2015420976340Open ↗
Showing 3 of 4 on file for this type
▸BISSELF-CERT PLUMBING NOTICE2
03/21/2015420976359Open ↗
02/05/2015420976359Open ↗
▸BISFA - FDNY APPROVAL : FD-FAA1
02/04/2020420983644Open ↗
▸BISSIGN HANGER CERTIFICATE1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISEQUIPMENT USE APPLICATION/PERMIT1
06/08/2015420976340Open ↗
▸BISSPRINKLER INSP REPORT : FP-851
02/05/2015420976359Open ↗
▸Environmental & Asbestos13
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER8
05/21/2014420983644Open ↗
05/15/2014420976340Open ↗
03/05/2014420937954Open ↗
Showing 3 of 8 on file for this type
▸DOB NOWDEP ACP-5: Asbestos Assessment Report3
08/27/2026Q00542855-I1Open ↗
08/13/2026Q08009883-I1Open ↗
08/13/2026Q00542855-P1Open ↗
▸BISASBESTOS: CERTIFICATION (DEP ACP5)1
06/06/2017421337770Open ↗
▸BISASBESTOS-EXEMPTION (ASB4)1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Energy Compliance26
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS13
01/22/2018421337770Open ↗
06/06/2017421337770Open ↗
01/17/2017421421704Open ↗
Showing 3 of 13 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS5
01/21/2022440604712Open ↗
01/22/2018421337770Open ↗
03/19/2015420976340Open ↗
Showing 3 of 5 on file for this type
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY2
01/21/2022440604712Open ↗
07/09/2020440604712Open ↗
▸BISTR8: Energy Code Progress Inspections2
05/15/2014420953908Open ↗
Showing 1 of 2 on file for this type
▸BISPTA4: SOLAR TAX ABATEMENT APPLICATION (PRELIMINARY)1
07/09/2020440604712Open ↗
▸BISPTA4: SOLAR TAX ABATEMENT APPLICATION (FINAL)1
01/24/2022440604712Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS1
07/09/2020440604712Open ↗
▸DOB NOWEN2: As Built Energy Analysis.1
08/13/2026Q00542855-I1Open ↗
▸Inspections & Test Reports5
▸BISTECHNICAL REPORT: RESPONSIBILITY2
01/21/2022440604712Open ↗
07/09/2020440604712Open ↗
▸DOB NOWSOIL REPORT2
08/15/2026Q00793534-P1Open ↗
08/13/2026Q00793534-I1Open ↗
▸DOB NOWTR4 Test Report and Plot Diagram1
08/13/2026Q00793534-I1Open ↗
▸Approvals, Objections & Sign-offs25
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST10
01/25/2022440604712Open ↗
11/23/2018420996051Open ↗
04/03/2018421337770Open ↗
Showing 3 of 10 on file for this type
▸BISADMINISTRATIVE OBJECTIONS9
04/29/2015421153030Open ↗
06/24/2014420996051Open ↗
05/30/2014420976359Open ↗
Showing 3 of 9 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION4
09/01/2020440604712Open ↗
01/24/2018421337770Open ↗
10/28/2014420976359Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWOTCR Conditional Acceptance Letter2
08/15/2026Q00793534-P1Open ↗
08/13/2026Q00793534-I1Open ↗
▸Cost, Insurance & Ownership30
▸BISCOST AFFIDAVIT29
07/09/2020440604712Open ↗
11/23/2018420996051Open ↗
01/22/2018421337770Open ↗
Showing 3 of 29 on file for this type
▸BISCOST AFFIDAVIT (FINAL): PW31
01/21/2022440604712Open ↗
▸Filing & Intake Forms26
▸BISEFILING COVER SHEET19
06/06/2017421337770Open ↗
01/17/2017421421704Open ↗
01/17/2017421421704Open ↗
Showing 3 of 19 on file for this type
▸BISADDITIONAL INFORMATION6
10/06/2021440604712Open ↗
09/10/2021440604712Open ↗
09/01/2020440604712Open ↗
Showing 3 of 6 on file for this type
▸BISEFILING JOB APPLICATION COVER SHEET1
07/09/2020440604712Open ↗
▸Other Documents2
▸BISSUBSTANTIAL IMPROVEMENT CALCULATIONS1
07/09/2020440604712Open ↗
▸BISTax Abatement Miscellaneous1
01/24/2022440604712Open ↗