| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 07/28/2026 | Permit Issued | CLEARCUT GROUP CORP | Heating and Air Conditioning Systems | Heat / Cool Ephoca APE 1 ON3H1 290 CFM · Ptac ×3 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/28/2026 | Permit Issued | JUST PLBG & HTG INC | Gas, Water/Sanitary |
| 04/12/2026 | Permit Issued | APOLLO PLBG & HTG INC | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/22/2026 | Complete | OSTRAVA ELECTRIC CORP | — |
| 08/25/2026 | Complete | FIRST STAR ELECTRIC INC | General Wiring |
| 08/24/2026 | Complete | BELMONT ELECTRICAL, INC | General Wiring |
| 05/13/2026 | Permit Issued | SUPREME ELECTRIC CORP | General Wiring |
| 05/04/2026 | Permit Issued | OSTRAVA ELECTRIC CORP | General Wiring |
| 05/04/2026 | Permit Issued | ARGON ELECTRICAL CORP | General Wiring |
| 04/14/2026 | Permit Issued | OSTRAVA ELECTRIC CORP | General Wiring |
| 03/03/2026 | Complete | OSTRAVA ELECTRIC CORP | General Wiring |
| 12/11/2025 | Complete | LB ELECTRIC CO.-NORTH LLC | General Wiring |
| 07/23/2025 | Complete | EMPIRE LIC ELECL CONTRS | — |
| 05/20/2025 | Complete | OSTRAVA ELECTRIC CORP | General Wiring |
| 04/17/2025 | Complete | OSTRAVA ELECTRIC CORP | — |
| 03/10/2025 | Complete | A.L. ELECTRICAL CORP. | General Wiring |
| 03/04/2025 | Complete | E & M ELECTRICAL NY CORP | General Wiring |
| 01/13/2025 | Complete | DANUBE ELECTRIC CO., INC. | General Wiring |
| Owner | Filings | Most Recent |
|---|---|---|
| 32 GRAMERCY PARK SO OWNERS | 123 | 03/22/2026 |
| 32 GRAMACY PK OWNER CORP | 2 | 03/22/2026 |
| W.P.G. RESIDENTIAL | 1 | 03/22/2026 |
| ANBY ASSOC | 1 | 03/22/2026 |
| CERTIFEID CONTRACTORS INC | 1 | 03/22/2026 |
| DECOBUILD | 2 | 03/22/2026 |
| LAMB GRAMERCY S CORP | 1 | 03/22/2026 |
| 32 GRAMERCY PARK SOUTH OWNERS | 26 | 03/21/2026 |
| COOPER SQUARE REALTY | 5 | 03/21/2026 |
| 61 WEST 62ND STREET | 2 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| DOWNTOWN ENGINEERS | 1 | 07/28/2026 |
| HOMAYOON SAGHAFI ARCHITECT | 2 | 04/22/2026 |
| ALEX ALAIMO AIA | 5 | 04/20/2026 |
| KIMBERLY PECK ARCHITECT | 7 | 11/24/2025 |
| RISE ARCHITECTURE | 1 | 03/19/2025 |
| RONALD D.VICTORIO R.A. | 2 | 05/30/2024 |
| ISADORA ACOSTA, LLC | 5 | 02/07/2024 |
| BATLIBOI STUDIO/ ARCHITECTURE, PLLC | 1 | 07/28/2023 |
| VAIL ASSOCIATES ARCHITECTS | 2 | 12/05/2022 |
| FRANK S CAMINITI, RA | 5 | 04/15/2022 |
| ASHRAF CORP | 4 | 04/06/2022 |
| AMR ENGINEERING CONSULTANT, P.C. | 3 | 03/29/2022 |
| CHARLES G. MICHEL ENGINEERING, PC. | 1 | 06/24/2021 |
| CSANAD BODNAR ARCHITECT | 2 | 06/23/2021 |
| HC ARCHITECT, PC | 1 | 06/29/2020 |
| RANDALL P. COLLINS ARCHITECT, PC | 1 | 06/10/2020 |
| EN-POWER GROUP | 2 | 11/08/2019 |
| PCS ENGINEERING | 1 | 07/15/2019 |
| Representative | Filings | Most Recent |
|---|---|---|
| DOMANI CONSULTING | 7 | 03/21/2026 |
| HAQUE ASSOCIATES | 6 | 03/21/2026 |
| ENIGMA EXPEDITING | 2 | 03/21/2026 |
| CLARKE CONSTRUCTION CONSULTANTS | 1 | 03/21/2026 |
| EAST COAST ENGINEERING P C | 6 | 03/21/2026 |
| J A EXPEDITING | 4 | 03/21/2026 |
| Rigid Structural Design, LLC | 4 | 03/21/2026 |
| CH CORNERSTONE DESIGN | 1 | 03/21/2026 |
| IOAD | 6 | 03/21/2026 |
| P WOLFE CONSULTANTS | 10 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| NEW AMSTERDAM RESTORATION | General Contractor | 17 | 07/08/2026 |
| NUZA HOME IMPROVEMENT COR | General Contractor | 15 | 07/08/2026 |
| APOLLO PLBG & HTG INC | Plumbing | 6 | 07/08/2026 |
| CONSTRUCTION GURU CORP | General Contractor | 3 | 03/21/2026 |
| PREMIER FLOW PLBG AND HTG | Plumbing | 2 | 07/08/2026 |
| JOE MIDDLETON | Electrical | 2 | 03/21/2026 |
| TRANSFORM ELECTL CONTRS I | Electrical | 2 | 03/22/2026 |
| TRIBORO ELEC'L CONTR'G CO | Electrical | 2 | 03/22/2026 |
| ARI GROUP, INC | General Contractor | 2 | 07/08/2026 |
| BR CONSTRUCTION & STONE I | General Contractor | 2 | 03/21/2026 |
| NEIL CABERA | Electrical | 1 | 03/21/2026 |
| RODRIGUEZ, ALEX | Electrical | 1 | 03/21/2026 |
| G.BASSOLINO PLUMBING LTD | Plumbing | 1 | 07/08/2026 |
| GREGG NY PLUMBING, INC | Plumbing | 1 | 07/08/2026 |
| WILLIE THROWER, JR. | Electrical | 1 | 03/21/2026 |
| YOUNG CHOE | Electrical | 1 | 03/21/2026 |
| AMSTERDAM RESTORATION LLC | General Contractor | 1 | 07/08/2026 |
| JUST PLBG & HTG INC | Plumbing | 1 | 07/08/2026 |
| ATRIUM INTERIORS INC | General Contractor | 1 | 07/08/2026 |
| ABE HIMELFARB | Electrical | 1 | 03/21/2026 |
| CLEARCUT GROUP CORP | General Contractor | 1 | 07/08/2026 |
| GJELOSH NICAJ | Electrical | 1 | 03/21/2026 |
| GROUP S LLC | General Contractor | 1 | 07/08/2026 |
| INTERIOR FINISHES INC | General Contractor | 1 | 07/08/2026 |
| J.A.J CONTRACTING CORP | General Contractor | 1 | 08/13/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| DOWNTOWN ENGINEERS | 9711 | 1 | 07/28/2026 |
| TSS ENGINEERS | 4492 | 3 | 04/07/2026 |
| KIMBERLY PECK ARCHITECT, | 6812 | 6 | 11/24/2025 |
| BIZ DESIGNS LLC | 6312 | 1 | 03/19/2025 |
| PROJECT TACTICAL SOLUTION | 5859 | 1 | 05/30/2024 |
| WAVIC ENGINEERING PLLC | 1733 | 3 | 02/07/2024 |
| BATLIBOI STUDIO / ARCHITE | 7658 | 1 | 07/28/2023 |
| CHARLES G MICHEL ENGINEER | 2871 | 1 | 06/24/2021 |
| CBA | 5091 | 2 | 06/23/2021 |
| GROUP-S LLC | 5216 | 1 | 10/31/2019 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Permit Issued | J.A.J CONTRACTING CORP | 08/12/2026 |
| DOB NOW | Plumbing | Permit Issued | CAPE PLUMBING INC | 06/29/2026 |
| DOB NOW | General Construction | Permit Issued | NUZA HOME IMPROVEMENT COR | 06/23/2026 |
| DOB NOW | General Construction | Permit Issued | NUZA HOME IMPROVEMENT COR | 06/23/2026 |
| DOB NOW | General Construction | Permit Issued | NUZA HOME IMPROVEMENT COR | 06/23/2026 |
| DOB NOW | Plumbing | Permit Issued | APOLLO PLBG & HTG INC | 05/11/2026 |
| DOB NOW | Plumbing | Permit Issued | JUST PLBG & HTG INC | 05/08/2026 |
| DOB NOW | General Construction | Permit Issued | CLEARCUT GROUP CORP | 05/06/2026 |
| DOB NOW | General Construction | Permit Issued | NUZA HOME IMPROVEMENT COR | 04/30/2026 |
| DOB NOW | Plumbing | Permit Issued | APOLLO PLBG & HTG INC | 04/24/2026 |
| DOB NOW | General Construction | Permit Issued | NUZA HOME IMPROVEMENT COR | 04/16/2026 |
| DOB NOW | General Construction | Permit Issued | NUZA HOME IMPROVEMENT COR | 04/07/2026 |
| DOB NOW | General Construction | Signed-off | NUZA HOME IMPROVEMENT COR | 08/15/2025 |
| DOB NOW | General Construction | Signed-off | NUZA HOME IMPROVEMENT COR | 06/24/2025 |
| DOB NOW | General Construction | Signed-off | CONSTRUCTION GURU CORP | 04/16/2025 |
| DOB NOW | General Construction | Signed-off | BR CONSTRUCTION & STONE I | 04/23/2024 |
| DOB NOW | General Construction | Signed-off | NUZA HOME IMPROVEMENT COR | 08/03/2023 |
| DOB NOW | Plumbing | Signed-off | APOLLO PLBG & HTG INC | 06/06/2023 |
| DOB NOW | Plumbing | Signed-off | GREGG NY PLUMBING, INC | 05/15/2023 |
| DOB NOW | General Construction | Signed-off | INTERIOR FINISHES INC | 05/05/2023 |
| DOB NOW | General Construction | Signed-off | NUZA HOME IMPROVEMENT COR | 05/01/2023 |
| DOB NOW | General Construction | Signed-off | NEW AMSTERDAM RESTORATION | 04/06/2023 |
| DOB NOW | Sidewalk Shed | Signed-off | NEW AMSTERDAM RESTORATION | 01/26/2023 |
| DOB NOW | Plumbing | Signed-off | SUPER PLUMBERS CORP | 01/20/2023 |
| DOB NOW | Plumbing | Signed-off | AMERICAN STANDARD P&H CORORP. | 06/23/2022 |
| DOB NOW | General Construction | Signed-off | NEW AMSTERDAM RESTORATION | 04/09/2022 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | NEW AMSTERDAM RESTORATION | 04/07/2022 |
| DOB NOW | General Construction | Signed-off | NEW AMSTERDAM RESTORATION | 03/31/2022 |
| DOB NOW | Plumbing | Signed-off | DEMAR MECHANICAL INC | 03/16/2022 |
| DOB NOW | General Construction | Signed-off | NUZA HOME IMPROVEMENT COR | 02/24/2022 |
| DOB NOW | Sidewalk Shed | Signed-off | NEW AMSTERDAM RESTORATION | 01/28/2022 |
| DOB NOW | Supported Scaffold | Signed-off | NEW AMSTERDAM RESTORATION | 01/27/2022 |
| DOB NOW | Plumbing | Signed-off | APOLLO PLBG & HTG INC | 01/19/2022 |
| DOB NOW | General Construction | Signed-off | ARI GROUP | 10/29/2021 |
| DOB NOW | Mechanical Systems | Signed-off | ARI GROUP | 10/28/2021 |
| DOB NOW | Plumbing | Signed-off | DEMAR PLUMBING CORP | 10/26/2021 |
| DOB NOW | Plumbing | Signed-off | GALICJA PLBG AND HTG.CORP | 05/27/2021 |
| DOB NOW | Plumbing | Signed-off | APOLLO PLBG & HTG INC | 05/14/2021 |
| DOB NOW | General Construction | Signed-off | ATRIUM INTERIORS | 05/03/2021 |
| DOB NOW | Plumbing | Signed-off | APOLLO PLBG & HTG INC | 04/22/2021 |
| Date | Type | Result | Report |
|---|---|---|---|
| 08/12/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 06/06/2024 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 06/05/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 01/22/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 01/18/2024 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 01/09/2024 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 12/15/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 06/16/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 06/13/2023 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 09/23/2022 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 09/21/2022 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 04/01/2022 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 03/22/2022 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 01/24/2022 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 12/02/2021 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 11/11/2021 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 06/23/2021 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/28/2026 | Tenant Protection Plan Compliance | Jeff Akerman | special |
| 07/28/2026 | Energy Code Compliance Inspections | Raimundo Ramos | progress |
| 07/21/2026 | HVAC-R and service water heating system controls | Raimundo Ramos | energy_progress |
| 07/21/2026 | HVAC-R and service water heating equipment | Raimundo Ramos | energy_progress |
| 07/21/2026 | Maintenance information | Raimundo Ramos | energy_progress |
| 07/21/2026 | HVAC-R and service water piping design and insulation | Raimundo Ramos | energy_progress |
| 07/21/2026 | Mechanical Systems | Raimundo Ramos | special |
| 07/21/2026 | Fire-Resistant Penetrations and Joints | Raimundo Ramos | special |
| 07/21/2026 | Final | Raimundo Ramos | progress |
| 05/07/2026 | Fire-Resistance Rated Construction | HOMAYOON SAGHAFI | progress |
| 05/07/2026 | Tenant Protection Plan Compliance | bassam (sam) rimawi | special |
| 05/07/2026 | Final | HOMAYOON SAGHAFI | progress |
| 05/07/2026 | Energy Code Compliance Inspections | HOMAYOON SAGHAFI | progress |
| 05/07/2026 | Lighting in dwelling units | HOMAYOON SAGHAFI | energy_progress |
| 02/13/2026 | Final | ALEX ALAIMO | progress |
| 02/13/2026 | Tenant Protection Plan Compliance | bassam (sam) rimawi | special |
| 01/27/2026 | Final | ALEX ALAIMO | progress |
| 03/17/2025 | Lighting in dwelling units | Jeff Akerman | energy_progress |
| 03/17/2025 | Fire-Resistant Penetrations and Joints | Jeff Akerman | special |
| 03/17/2025 | Tenant Protection Plan Compliance | Jeff Akerman | special |
| 03/17/2025 | Energy Code Compliance Inspections | Jeff Akerman | progress |
| 03/17/2025 | Insulation placement and R values | Jeff Akerman | energy_progress |
| 03/17/2025 | Fire-Resistance Rated Construction | Jeff Akerman | progress |
| 03/13/2025 | Final | Jeff Akerman | progress |
| 05/14/2024 | Tenant Protection Plan Compliance | Max Lee | special |