| Owner | Filings | Most Recent |
|---|---|---|
| COPPERMINE CONSTRUCTION | 2 | 08/29/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 01/18/2022 | $3.7M | — | — → — | $979/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| GRAND MILLENNIUM CONSULTING ENGINEE | 2 | 09/11/2026 |
| SHAHRISH SHUVO ENGINEERING P.C. | 1 | 04/24/2026 |
| WW ENGINEERING PLLC | 2 | 03/26/2026 |
| WORKSHOP DESIGN+ARCHITECTURE,PLLC | 1 | 03/26/2026 |
| QUAMAR ZAMAN | 2 | 07/17/2024 |
| ELIZABETH PARKS ARCHITECT | 2 | 07/15/2024 |
| CHANDA ENGINEERING CONSULTANT PC | 2 | 07/12/2024 |
| Representative | Filings | Most Recent |
|---|---|---|
| DOMINION EXPEDITING | 6 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| LEGACY BUILDERS/DEVELOPERS CORP | General Contractor | 8 | 03/21/2026 |
| COPPERMINE CONSTRUCTION * | General Contractor | 3 | 07/08/2026 |
| DEMAR MECHANICAL INC | Plumbing | 1 | 07/08/2026 |
| GAROFALO PLMBNG & HTG LTD | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| GRAND MILLENNIUM CONSULTI | 469 | 2 | 09/11/2026 |
| WW ENGINEERING PLLC | 7502 | 1 | 03/26/2026 |
| ESNYC CONSULTING INC | 4099 | 4 | 07/15/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Structural | Permit Issued | COPPERMINE CONSTRUCTION * | 06/16/2026 |
| DOB NOW | General Construction | Permit Issued | COPPERMINE CONSTRUCTION * | 06/02/2026 |
| DOB NOW | Construction Fence | Permit Issued | COPPERMINE CONSTRUCTION * | 04/24/2026 |
| DOB NOW | Plumbing | Signed-off | GAROFALO PLMBNG & HTG LTD | 02/28/2025 |
| DOB NOW | General Construction | Signed-off | LEGACY BUILDERS/DEVELOPER | 10/30/2023 |
| DOB NOW | Mechanical Systems | Signed-off | LEGACY BUILDERS/DEVELOPER | 10/30/2023 |
| DOB NOW | Plumbing | Signed-off | DEMAR MECHANICAL INC | 05/02/2023 |
| DOB NOW | Mechanical Systems | Signed-off | LEGACY BUILDERS/DEVELOPER | 03/15/2023 |
| DOB NOW | General Construction | Signed-off | LEGACY BUILDERS/DEVELOPER | 02/17/2023 |
| BIS | OT | ISSUED | DINEEN CONSTRUCTION CORP. | 12/11/1995 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 09/11/2026 | Permit Issued | COPPERMINE CONSTRUCTION * | Air Conditioning Systems | Cooling Mitsubishi Electric PEFY-L12NMAU-A 12,000 BTU · Vrf Indoor ×5 MXZ-SM48NLHZ 48,000 BTU · Condensing Unit ×2 PEFY-L15NMAU-A 15,000 BTU · Vrf Indoor ×2 PMFY-M12NCMU-A 12,000 BTU · Vrf Indoor ×1 PUZ-AK30NLHZ 30,000 BTU · Condensing Unit ×1 PVA-AA30NL 30,000 BTU · Fan Coil Indoor ×1 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/11/2026 | — | — | Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/26/2026 | Permit Issued | KEPLER ELECTRICAL CONT | General Wiring |
| 03/15/2023 | Permit Issued | FIU CORP DBA FIU ELECTRIC | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/11/2026 | Permit Issued | COPPERMINE CONSTRUCTION * | Wood |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/24/2026 | Permit Issued | COPPERMINE CONSTRUCTION * | Fence |
| Date | Type | Result | Report |
|---|---|---|---|
| 03/19/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 03/10/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 03/07/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 03/07/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 12/08/2023 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 09/10/2026 | Concrete - Cast-In-Place | Edwin Cheuk | special |
| 09/10/2026 | Masonry | Edwin Cheuk | special |
| 09/10/2026 | Post-installed Anchors | Edwin Cheuk | special |
| 09/10/2026 | Structural Steel - High Strength Bolting | Edwin Cheuk | special |
| 09/10/2026 | Structural Steel - Welding | Edwin Cheuk | special |
| 09/10/2026 | Subgrade Inspections | Edwin Cheuk | special |
| 09/10/2026 | Structural Stability – Alterations of existing buildings | Edwin Cheuk | special |
| 09/10/2026 | Final | Edwin Cheuk | progress |
| 09/10/2026 | Structural Wood Frame | Edwin Cheuk | progress |
| 03/24/2026 | Final | Wing Wong | progress |
| 03/24/2026 | Fire-Resistance Rated Construction | Wing Wong | progress |
| 03/24/2026 | Fire-Resistant Penetrations and Joints | Wing Wong | special |
| 03/23/2026 | Structural Wood Frame | Edwin Cheuk | progress |
| 03/23/2026 | Structural Stability – Alterations of existing buildings | Edwin Cheuk | special |
| 03/20/2026 | Final | Edwin Cheuk | progress |
| 07/05/2024 | Fire-Resistant Penetrations and Joints | sajjad javaid | special |
| 07/05/2024 | Fire-Resistance Rated Construction | sajjad javaid | progress |
| 07/05/2024 | Structural Wood Frame | sajjad javaid | progress |
| 07/05/2024 | Structural Steel - High Strength Bolting | sajjad javaid | special |
| 07/05/2024 | Structural Steel - Details | sajjad javaid | special |
| 07/05/2024 | Structural Stability – Alterations of existing buildings | sajjad javaid | special |
| 07/05/2024 | Masonry | sajjad javaid | special |
| 07/05/2024 | Final | sajjad javaid | progress |
| 07/05/2024 | Structural Cold-Formed Steel | sajjad javaid | special |
| 04/22/2024 | Mechanical Systems | sajjad javaid | special |