← Back
One story - permanent living quarter
2316 EAST 64 STREET
BROOKLYN · Marine Park-Mill Basin-Bergen Beach · BIN 3243573
💬 Discuss this project
1950Year Built
1Stories
A2Building Class
R2Zoning
1,188 sfGross Floor Area
1Units
One story - permanent living quarter · 4,975 sf lot · 0.24 FAR built · Flood zone AE
Locations of Work
ArchitectureFire Protection
Roof1p · 1 filing · 6 docs
Floor 234p · 1 filing · 20 docs
Floor 133p · 1 filing · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
CITISCAPE CONSULTING LTD5107/08/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
07/15/2021$825K—— → —$694/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
CITISCAPE CONSULTING LTD1502/14/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
CITISCAPE CONSULTING LTD3003/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
MAZCO CONSTRUCTION CORPGeneral Contractor1407/08/2026
CITISCAPE DEVELOPMENT INCGeneral Contractor303/21/2026
CONTACT PLUS ELECL CORP 003500General Contractor203/22/2026
CONTACT PLUS ELEC'L CORPElectrical203/22/2026
EDGAR LEVENSTEINElectrical203/21/2026
CITISCAPE CONSULTING LTDGeneral Contractor103/22/2026
INNOVATION PLUMBING LLCPlumbing107/08/2026
PIPESTYLISTS, INCPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
CITISCAPE CONSULTING LTD7621002/14/2025
CONSULTING ENGINEER5093101/25/2022
Building Lifecycle
All (145)Filed (15)Permit Issued (9)Signed Off (4)Inspection (7)Objection (80)Special Inspection (30)
03/05/2025
Objection resolved — Addressed
03/05/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
Joe Lieberman
03/05/2025
Special inspection requirement — Fire-Resistance Rated Construction
Joe Lieberman
03/05/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Joe Lieberman
03/05/2025
Special inspection requirement — Energy Code Compliance Inspections
Joe Lieberman
03/05/2025
Special inspection requirement — Insulation placement and R values
Alix Michel
03/05/2025
Special inspection requirement — Fenestration and door U-factor and product ratings
Alix Michel
03/05/2025
Special inspection requirement — Interior lighting power
Alix Michel
03/05/2025
Special inspection requirement — Concrete - Cast-In-Place
Joe Lieberman
03/05/2025
Special inspection requirement — Fenestration air leakage
Alix Michel
03/05/2025
Special inspection requirement — Masonry
Joe Lieberman
03/05/2025
Special inspection requirement — Subgrade Inspections
Joe Lieberman
03/05/2025
Special inspection requirement — Fenestration areas
Alix Michel
03/05/2025
Special inspection requirement — Lowest Floor Elevation
Joe Lieberman
03/05/2025
Special inspection requirement — Metering
Alix Michel
02/19/2025
Objection raised — Scope
02/14/2025
Filed — ALT-CO - New Building with Existing Elements to Remain
FOUNDATION AND STRUCTURAL APPLICATION. THIS IS SUBSEQUENT FILING FOR GC-B00592885-I1
B00592885-P2
02/14/2025
Special inspection requirement — Insulation placement and R values
Alix Michel
02/14/2025
Special inspection requirement — Lowest Floor Elevation
Joe Lieberman
02/14/2025
Special inspection requirement — Fire-Resistance Rated Construction
Joe Lieberman
02/14/2025
Special inspection requirement — Subgrade Inspections
Joe Lieberman
02/14/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
Joe Lieberman
02/14/2025
Special inspection requirement — Masonry
Joe Lieberman
02/14/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Joe Lieberman
02/14/2025
Special inspection requirement — Concrete - Cast-In-Place
Joe Lieberman
02/14/2025
Special inspection requirement — Fenestration and door U-factor and product ratings
Alix Michel
02/14/2025
Special inspection requirement — Fenestration air leakage
Alix Michel
02/14/2025
Special inspection requirement — Interior lighting power
Alix Michel
02/14/2025
Special inspection requirement — Energy Code Compliance Inspections
Joe Lieberman
02/14/2025
Special inspection requirement — Metering
Alix Michel
02/14/2025
Special inspection requirement — Fenestration areas
Alix Michel
02/13/2025
Signed off — Alteration
APPLICATION FOR 10 LINEAR FEET CURB CUT TO BE LOCATED ALONG EAST 64th STREET. NO CHANGE IN EGRESS, USE, OCCUPANCY.
B00592991-I1
02/12/2025
Inspection — Pass-Final Curb Cut Non-Directive 14
Pass
View inspection ↗
02/06/2025
Permit issued — Curb Cut
B00592991-I1-CC
06/18/2024
Signed off — Alteration
PLUMBING APPLICATION IN CONJUNCTION WITH GC APPLICATION #B00592885-I1
B00592971-I1
05/15/2024
Signed off — ALT-CO - New Building with Existing Elements to Remain
FOUNDATION AND STRUCTURAL APPLICATION. THIS IS SUBSEQUENT FILING FOR GC-B00592885-I1
B00592885-S1
04/23/2024
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
03/06/2024
Signed off — Alteration
B00592990-I1
01/29/2024
Objection resolved — Addressed
01/29/2024
Special inspection requirement — HVAC-R and service water piping design and insulation
Alix Michel
01/29/2024
Special inspection requirement — Post-installed Anchors
Joe Lieberman
01/24/2024
Objection resolved — Addressed
01/24/2024
Objection resolved — Addressed
01/24/2024
Objection resolved — Addressed
01/23/2024
Objection raised — Structural
01/23/2024
Objection raised — Structural
01/23/2024
Objection raised — DPL-1
01/23/2024
Objection raised — Other
01/17/2024
Filed — Alteration
PLUMBING APPLICATION IN CONJUNCTION WITH GC APPLICATION #B00592885-I1
B00592971-P7
01/08/2024
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
12/29/2023
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
12/26/2023
Objection raised — Other
12/26/2023
Objection resolved — Addressed
12/21/2023
Filed — Alteration
PLUMBING APPLICATION IN CONJUNCTION WITH GC APPLICATION #B00592885-I1
B00592971-P6
12/12/2023
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
12/06/2023
Permit issued — Plumbing
B00592971-I1-PL
11/15/2023
Inspection — Fail-Final PL - Up to 3 Requested Floors
Fail
View inspection ↗
09/06/2023
Filed — Alteration
sprinkler application in conjunction with GC application # B00592885
B00592986-P1
08/21/2023
Objection resolved — Addressed
08/21/2023
Objection resolved — Addressed
Latest 60 of 145 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWCurb CutSigned-offCITISCAPE DEVELOPMENT INC02/06/2025
DOB NOWPlumbingSigned-offT & T PLUMBING INC12/06/2023
DOB NOWGeneral ConstructionPermit IssuedMAZCO CONSTRUCTION CORP01/25/2023
DOB NOWConstruction FenceSigned-offMAZCO CONSTRUCTION CORP01/24/2023
DOB NOWFoundationSigned-offMAZCO CONSTRUCTION CORP01/24/2023
DOB NOWPlumbingSigned-offINNOVATION PLUMBING LLC08/31/2022
DOB NOWGeneral ConstructionPermit IssuedMAZCO CONSTRUCTION CORP04/27/2022
DOB NOWStructuralSigned-offMAZCO CONSTRUCTION CORP04/27/2022
DOB NOWConstruction FenceSigned-offMAZCO CONSTRUCTION CORP03/17/2022
1 project · most recent 09/06/2023
FiledStatusContractorScope
09/06/2023——29 heads
2 projects · most recent 01/08/2024
General Wiring
FiledStatusContractorScope
01/08/2024CompleteCONTACT PLUS ELEC'L CORPGeneral Wiring
05/02/2022CompleteCONTACT PLUS ELEC'L CORP—
1 project · most recent 02/14/2025
Steel
FiledStatusContractorScope
02/14/2025Permit IssuedMAZCO CONSTRUCTION CORPSteel
▾Field Inspections (DOB CAP) — 7
DateTypeResultReport
02/12/2025Pass-Final Curb Cut Non-Directive 14PassView ↗
04/23/2024Pass-Final CND-Occupancy InspectionPassView ↗
01/08/2024Pass-Final CND-Occupancy InspectionPassView ↗
12/29/2023Pass-Final PL - Up to 3 Requested FloorsPassView ↗
12/12/2023Pass-Final PL - Up to 3 Requested FloorsPassView ↗
11/15/2023Fail-Final PL - Up to 3 Requested FloorsFailView ↗
02/28/2023Fail-Final CND-Occupancy InspectionFailView ↗
▾Special Inspection Requirements (DOB NOW) — 98
DateRequirementInspectorRole
03/05/2025Lowest Floor ElevationJoe Liebermanprogress
03/05/2025MeteringAlix Michelenergy_progress
03/05/2025Fenestration and door U-factor and product ratingsAlix Michelenergy_progress
03/05/2025Fenestration areasAlix Michelenergy_progress
03/05/2025Insulation placement and R valuesAlix Michelenergy_progress
03/05/2025Fenestration air leakageAlix Michelenergy_progress
03/05/2025Interior lighting powerAlix Michelenergy_progress
03/05/2025Fire-Resistance Rated ConstructionJoe Liebermanprogress
03/05/2025Energy Code Compliance InspectionsJoe Liebermanprogress
03/05/2025Concrete - Cast-In-PlaceJoe Liebermanspecial
03/05/2025Subgrade InspectionsJoe Liebermanspecial
03/05/2025Fire-Resistant Penetrations and JointsJoe Liebermanspecial
03/05/2025MasonryJoe Liebermanspecial
03/05/2025Structural Stability – Alterations of existing buildingsJoe Liebermanspecial
02/14/2025Fire-Resistance Rated ConstructionJoe Liebermanprogress
02/14/2025Insulation placement and R valuesAlix Michelenergy_progress
02/14/2025Fenestration areasAlix Michelenergy_progress
02/14/2025Interior lighting powerAlix Michelenergy_progress
02/14/2025MeteringAlix Michelenergy_progress
02/14/2025Fenestration air leakageAlix Michelenergy_progress
02/14/2025Fenestration and door U-factor and product ratingsAlix Michelenergy_progress
02/14/2025Concrete - Cast-In-PlaceJoe Liebermanspecial
02/14/2025Fire-Resistant Penetrations and JointsJoe Liebermanspecial
02/14/2025MasonryJoe Liebermanspecial
02/14/2025Structural Stability – Alterations of existing buildingsJoe Liebermanspecial
Latest 25 of 98.
▾Documents — 169 on file (BIS + DOB NOW)
▸Plans & Drawings15
▸DOB NOWPlans/Sketch15
08/31/2026B00592971-I1Request digital key ↗
08/31/2026B00592971-P5Request digital key ↗
08/31/2026B00592986-P1Request digital key ↗
Showing 3 of 15 on file for this type
▸Applications & Permits3
▸BISPLAN / WORK APPROVAL APPLICATION2
01/31/2022340834208Open ↗
01/27/2022340834208Open ↗
▸BISBPP-5 - Authorization to the Department of Transportation1
01/27/2022340834208Open ↗
▸Zoning, Tax Lot & Property Records7
▸DOB NOWZoning Exhibit form (1-5)3
08/13/2026B00592885-P2Open ↗
08/13/2026B00592885-P1Open ↗
08/13/2026B00592885-I1Open ↗
▸DOB NOWZD1: DOB Zoning Diagram3
08/13/2026B00592885-I1Open ↗
08/13/2026B00592885-P2Open ↗
08/13/2026B00592885-P1Open ↗
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/13/2026B00592885-I1Open ↗
▸Seals & Professional Certifications101
▸DOB NOWProgress Inspector Seal & Signature52
09/01/2026B00592971-P6Open ↗
09/01/2026B00592971-P6Open ↗
09/01/2026B00592971-P6Open ↗
Showing 3 of 52 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature33
09/01/2026B00592971-P6Open ↗
09/01/2026B00592971-P6Open ↗
09/01/2026B00592971-P7Open ↗
Showing 3 of 33 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature15
08/31/2026B00592971-P2Open ↗
08/31/2026B00592971-P6Open ↗
08/31/2026B00592971-I1Open ↗
Showing 3 of 15 on file for this type
▸BISAPPLICANT OWNER SIGNATURE1
01/27/2022340834208Open ↗
▸Trade Schedules & Equipment4
▸DOB NOWDEP: Sewer Certification (Sanitary/Storm)4
08/13/2026B00592885-P2Open ↗
08/13/2026B00592885-I1Open ↗
08/13/2026B00592885-S1Open ↗
Showing 3 of 4 on file for this type
▸Safety & Tenant Protection7
▸BISSTREET TREE CHECKLIST2
01/31/2022340834208Open ↗
01/31/2022340834208Open ↗
▸DOB NOWParks Department Acknowledgment Letter for Street Trees Plan2
08/13/2026B00592885-I1Open ↗
08/13/2026B00592885-S1Open ↗
▸BISBPP: STREET TREES SITE PLAN1
01/31/2022340834208Open ↗
▸DOB NOWStreet Tree Sign Off1
08/13/2026B00592885-I1Open ↗
▸DOB NOWStreet Trees Site Plan1
08/13/2026B00592885-I1Open ↗
▸Environmental & Asbestos12
▸DOB NOWDEP ACP-5: Asbestos Assessment Report12
08/31/2026B00592971-I1Open ↗
08/31/2026B00592971-P5Open ↗
08/31/2026B00592986-P1Open ↗
Showing 3 of 12 on file for this type
▸Energy Compliance2
▸DOB NOWEN2: As Built Energy Analysis.2
08/31/2026B00592971-I1Open ↗
08/13/2026B00592885-I1Open ↗
▸Inspections & Test Reports2
▸BISTECHNICAL REPORT: RESPONSIBILITY2
01/31/2022340834208Open ↗
01/27/2022340834208Open ↗
▸Filing & Intake Forms2
▸BISEFILING JOB APPLICATION COVER SHEET1
01/27/2022340834208Open ↗
▸BISBPP: CHECKLIST IN LIEU OF PLANS-ALT31
01/27/2022340834208Open ↗
▸Other Documents14
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone4
08/13/2026B00592885-P2Open ↗
08/13/2026B00592885-I1Open ↗
08/13/2026B00592885-P1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWProperty Ownership Certification3
08/31/2026B00592885-P1Open ↗
08/15/2026B00592885-I1Open ↗
08/14/2026B00592885-P2Open ↗
▸DOB NOWSite Survey: Initial3
08/13/2026B00592885-P2Open ↗
08/13/2026B00592885-P1Open ↗
08/13/2026B00592885-I1Open ↗
▸DOB NOWProject Specific General Liability (PGL1)2
08/13/2026B00592885-S1Open ↗
08/13/2026B00592885-I1Open ↗
▸BISBPP - SUPPORTING DOCUMENTATION1
01/27/2022340834208Open ↗
▸DOB NOWFinal Survey1
08/13/2026B00592885-I1Open ↗