1930Year Built
2Stories
B3Building Class
R4Zoning
1,472 sfGross Floor Area
2Units
0 Open ViolationsFDNY Report ↗
Two family converted from one family · 2,000 sf lot · 0.74 FAR built · Flood zone X500
Locations of Work
ArchitectureCivilGeneral
Roof5p · 1 filing · 5 docs
Floor 22p · 1 filing · 3 docs
Floor 1
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
ADB ASSOCIATES211/16/2022
STREET CONSULTING ENGINEERING, P. .207/02/2021
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
ZOBUILDEN403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
CEDARS CONSTRUCTION CORPGeneral Contractor107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
A&B WORLD CONSULTING, INC5704107/02/2021
Building Lifecycle
All (50)Filed (4)Permit Issued (1)Violation (1)Objection (36)Special Inspection (8)
12/02/2022
Objection raised — Structural
12/02/2022
Objection raised — Admin
12/02/2022
Objection raised — Structural
12/02/2022
Objection raised — Structural
12/02/2022
Objection raised — Mechanical
12/02/2022
Objection raised — Other
12/02/2022
Objection raised — Other
12/02/2022
Objection raised — Structural
12/02/2022
Objection raised — Structural
12/02/2022
Objection raised — Structural
12/02/2022
Objection raised — Structural
12/02/2022
Objection raised — Scope
12/02/2022
Objection raised — Zoning
12/02/2022
Objection raised — Zoning
12/02/2022
Objection raised — Fire_Protection
12/02/2022
Objection raised — Fire_Protection
12/02/2022
Objection raised — Fire_Protection
12/02/2022
Objection raised — Fire_Protection
12/02/2022
Objection raised — Structural
12/02/2022
Objection raised — Structural
12/02/2022
Objection raised — Structural
12/02/2022
Objection raised — Scope
12/02/2022
Objection raised — Inspections
12/02/2022
Objection raised — Inspections
12/02/2022
Objection raised — Inspections
12/02/2022
Objection raised — Other
12/02/2022
Objection raised — Admin
12/02/2022
Objection raised — Structural
11/16/2022
Filed — Alteration
EXISTING TWO SOTRY & CELLAR BUILDING: PROPOSED CELLAR THRU ATTIC EXTENSION. INTERIOR RENOVATION ON ALL FLOORS, AND NEW PLUMBING. NO CHANGE TO USE, OCCUPANCY, EGRESS.
B00760419-I1
08/29/2022
Permit issued — Construction Fence
B00792915-I1-FN
08/18/2022
Objection raised — Structural
08/18/2022
Objection resolved — Addressed
08/18/2022
Objection raised — Scope
08/18/2022
Objection resolved — Addressed
08/18/2022
Objection raised — Structural
08/18/2022
Objection resolved — Addressed
08/18/2022
Objection raised — Inspections
08/18/2022
Objection resolved — Addressed
08/17/2022
Filed — Alteration
ERECT TEMPORARY PLYWOOD FENCE ON THE PROPERTY LINE TO PROTECT PEDESTRIANS. REFER TO SEPARATED GC APPLICATION B00544843 AND PL B00548605
B00792915-I1
06/19/2022
Special inspection requirement — Fire-Resistant Penetrations and Joints
06/19/2022
Special inspection requirement — Structural Stability – Alterations of existing buildings
06/19/2022
Special inspection requirement — Energy Code Compliance Inspections
06/19/2022
Special inspection requirement — Fire-Resistance Rated Construction
06/19/2022
Special inspection requirement — Fenestration air leakage
06/19/2022
Special inspection requirement — Fenestration and door U-factor and product ratings
06/19/2022
Special inspection requirement — Fenestration areas
06/19/2022
Special inspection requirement — Interior lighting power
07/02/2021
Filed — Alteration
B00544843-I1
07/02/2021
Filed — Alteration
B00548605-I1
05/22/1997
Violation issued (ECB, closed)
Plumbing
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWConstruction FencePermit IssuedCEDARS CONSTRUCTION GROUP08/29/2022
BISOTISSUED1ST LIGHT ENERGY INC08/07/2017
1 project · most recent 08/17/2022
Fence
FiledStatusContractorScope
08/17/2022Permit IssuedCEDARS CONSTRUCTION CORPFence
▾Special Inspection Requirements (DOB NOW) — 8
DateRequirementInspectorRole
06/19/2022Fire-Resistant Penetrations and Joints—special
06/19/2022Structural Stability – Alterations of existing buildings—special
06/19/2022Energy Code Compliance Inspections—progress
06/19/2022Fire-Resistance Rated Construction—progress
06/19/2022Fenestration air leakage—energy_progress
06/19/2022Fenestration and door U-factor and product ratings—energy_progress
06/19/2022Fenestration areas—energy_progress
06/19/2022Interior lighting power—energy_progress
▾Documents — 32 on file (BIS + DOB NOW)
▸Plans & Drawings4
▸DOB NOWPlans/Sketch4
09/01/2026B00548605-I1Request digital key ↗
09/01/2026B00544843-I1Request digital key ↗
08/15/2026B00792915-I1Request digital key ↗
Showing 3 of 4 on file for this type
▸Applications & Permits2
▸BISPLAN / WORK APPROVAL APPLICATION1
07/28/2017340526808Open ↗
▸BISWORK PERMIT APPLICATION1
08/07/2017340526808Open ↗
▸Zoning, Tax Lot & Property Records1
▸DOB NOWZD1: DOB Zoning Diagram1
08/13/2026B00760419-I1Open ↗
▸Seals & Professional Certifications5
▸DOB NOWDPL-1: Design Professional Seal & Signature4
09/01/2026B00548605-I1Open ↗
09/01/2026B00544843-I1Open ↗
08/28/2026B00792915-I1Open ↗
Showing 3 of 4 on file for this type
▸BISAPPLICANT OWNER SIGNATURE1
07/28/2017340526808Open ↗
▸Safety & Tenant Protection1
▸BISTENANT PROTECTION PLAN AND NOTES1
07/28/2017340526808Open ↗
▸Environmental & Asbestos4
▸DOB NOWDEP ACP-5: Asbestos Assessment Report3
09/01/2026B00548605-I1Open ↗
09/01/2026B00544843-I1Open ↗
08/14/2026B00760419-I1Open ↗
▸BISASBESTOS: CERTIFICATION (DEP ACP5)1
07/28/2017340526808Open ↗
▸Energy Compliance5
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY2
02/18/2020340526808Open ↗
07/28/2017340526808Open ↗
▸BISAS-BUILT ENERGY ANALYSIS1
02/18/2020340526808Open ↗
▸BISSOLAR TAX ABATEMENT APPLICATION1
02/18/2020340526808Open ↗
▸BISPTA4: SOLAR TAX ABATEMENT APPLICATION (PRELIMINARY)1
07/28/2017340526808Open ↗
▸Inspections & Test Reports2
▸BISTECHNICAL REPORT: RESPONSIBILITY2
02/18/2020340526808Open ↗
07/28/2017340526808Open ↗
▸Approvals, Objections & Sign-offs3
▸BISUtility Company PV System Interconnection Acknowledgement Letter1
02/18/2020340526808Open ↗
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST1
02/18/2020340526808Open ↗
▸BISThird Party Electrical Signoff Compliance Report1
02/18/2020340526808Open ↗
▸Cost, Insurance & Ownership2
▸BISCOST AFFIDAVIT2
02/18/2020340526808Open ↗
07/28/2017340526808Open ↗
▸Filing & Intake Forms2
▸BISADDITIONAL INFORMATION1
08/04/2017340526808Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET1
07/28/2017340526808Open ↗
▸Other Documents1
▸DOB NOWSite Survey: Initial1