← Back
One story - permanent living quarter
232-07 129 AVENUE
QUEENS · BIN 4276992
💬 Discuss this project
1950Year Built
1Stories
A2Building Class
R2AZoning
1,159 sfGross Floor Area
1Units
One story - permanent living quarter · 3,895 sf lot · 0.3 FAR built · Flood zone X
Locations of Work
Other
Roof1p · 1 filing · 13 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
GREEN RIVER ENVIRONMENTAL ENGINEERI212/09/2025
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
NYSS LLCGeneral Contractor303/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
GREEN RIVER ENVIRONMENTAL7841212/09/2025
Building Lifecycle
All (12)Filed (2)Permit Issued (1)Signed Off (1)Special Inspection (8)
12/15/2025
Signed off — Alteration
Q01047459-I1
12/11/2025
Special inspection requirement — Air barrier - visual inspection
ROBERT MASONE
12/11/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
ROBERT MASONE
12/11/2025
Special inspection requirement — Energy Code Compliance Inspections
ROBERT MASONE
12/11/2025
Special inspection requirement — Final
ROBERT MASONE
12/09/2025
Filed — Alteration
Q01047459-P1
04/08/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
ROBERT MASONE
04/08/2025
Special inspection requirement — Energy Code Compliance Inspections
ROBERT MASONE
04/08/2025
Special inspection requirement — Final
ROBERT MASONE
04/08/2025
Special inspection requirement — Air barrier - visual inspection
ROBERT MASONE
05/17/2024
Permit issued — Solar
Q01047459-I1-SL
05/15/2024
Filed — Alteration
Q01047459-I1
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offNYSS LLC05/17/2024
1 project · most recent 05/06/2024
FiledStatusContractorScope
05/06/2024CompleteNY SOLAR ELECTRICAL LLC—
▾Special Inspection Requirements (DOB NOW) — 8
DateRequirementInspectorRole
12/11/2025Air barrier - visual inspectionROBERT MASONEenergy_progress
12/11/2025Fire-Resistant Penetrations and JointsROBERT MASONEspecial
12/11/2025Energy Code Compliance InspectionsROBERT MASONEprogress
12/11/2025FinalROBERT MASONEprogress
04/08/2025Fire-Resistant Penetrations and JointsROBERT MASONEspecial
04/08/2025Energy Code Compliance InspectionsROBERT MASONEprogress
04/08/2025FinalROBERT MASONEprogress
04/08/2025Air barrier - visual inspectionROBERT MASONEenergy_progress
▾Documents — 13 on file (BIS + DOB NOW)
▸Plans & Drawings2
▸DOB NOWPlans/Sketch2
08/22/2026Q01047459-P1Request digital key ↗
08/22/2026Q01047459-I1Request digital key ↗
▸Seals & Professional Certifications8
▸DOB NOWProgress Inspector Seal & Signature4
09/01/2026Q01047459-P1Open ↗
09/01/2026Q01047459-P1Open ↗
08/28/2026Q01047459-I1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature2
08/22/2026Q01047459-P1Open ↗
08/22/2026Q01047459-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature2
09/01/2026Q01047459-P1Open ↗
08/28/2026Q01047459-I1Open ↗
▸Environmental & Asbestos2
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
08/22/2026Q01047459-P1Open ↗
08/22/2026Q01047459-I1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/13/2026Q01047459-I1Open ↗