| Owner | Filings | Most Recent |
|---|---|---|
| Chelsea 7 JV | 126 | 03/21/2026 |
| Kano Rei | 22 | 07/08/2026 |
| Karmelena Company | 11 | 03/22/2026 |
| JTL Associates | 2 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| Leon Skvirsky PE | 1 | 08/12/2026 |
| Billah Engineering | 1 | 05/16/2023 |
| Prospect Associates | 1 | 12/13/2022 |
| Mottola Rini Engineers | 6 | 01/11/2022 |
| Concord Associates | 7 | 12/09/2020 |
| Representative | Filings | Most Recent |
|---|---|---|
| K & M Associates | 7 | 03/21/2026 |
| BMB Building Consulting | 2 | 03/21/2026 |
| Insha Building Consultants | 2 | 03/21/2026 |
| Y A Consulting Expediting | 12 | 03/21/2026 |
| KM Associates of New York | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| Pro N.Y. Solutions | General Contractor | 3 | 03/21/2026 |
| Katan P & H | Plumbing | 2 | 07/08/2026 |
| KCC D+B | General Contractor | 2 | 07/08/2026 |
| Paul Signs | Sign hanger | 1 | 08/16/2026 |
| Red Hook Sign and Electric | Sign hanger | 1 | 07/08/2026 |
| Unitech Design | Sign hanger | 1 | 07/08/2026 |
| A + Sprinkler | Fire Protection | 1 | 07/08/2026 |
| Orbit Sprinkler | Fire Protection | 1 | 07/08/2026 |
| M.R. Electrical Service | Electrical | 1 | 03/22/2026 |
| R & S Plumbing & Heating | Plumbing | 1 | 07/08/2026 |
| Omd Electrical | Electrical | 1 | 03/21/2026 |
| WCK Electric | Electrical | 1 | 03/22/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| Buildtech Engineering | 6369 | 1 | 05/16/2023 |
| Mottola Rini Engineers, P | 3251 | 4 | 01/11/2022 |
| Crosscheck Inspection Services | 544 | 3 | 10/07/2020 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Sign | Permit Issued | Paul Signs | 08/14/2026 |
| DOB NOW | General Construction | Signed-off | Pro N.Y. Solutions | 07/03/2023 |
| DOB NOW | Sign | Signed-off | Unitech Design | 12/30/2022 |
| DOB NOW | Mechanical Systems | Signed-off | KCC D+B | 04/29/2022 |
| DOB NOW | Sprinklers | Signed-off | Orbit Sprinkler | 03/15/2022 |
| DOB NOW | Mechanical Systems | Signed-off | KCC D+B | 01/25/2022 |
| DOB NOW | Plumbing | Signed-off | R & S Plumbing & Heating | 01/25/2022 |
| DOB NOW | Plumbing | Permit Issued | Katan P & H | 02/16/2021 |
| DOB NOW | Sprinklers | Signed-off | A + Sprinkler | 11/05/2020 |
| DOB NOW | Sign | Permit Issued | Red Hook Sign and Electric | 10/21/2020 |
| DOB NOW | Plumbing | Permit Issued | Katan P & H | 12/30/2019 |
| BIS | — | ISSUED | Rock of NYC Construction | 01/09/2026 |
| BIS | — | ISSUED | Rock of NYC Construction | 12/15/2025 |
| BIS | — | ISSUED | Rock of NYC Construction | 08/07/2025 |
| BIS | — | ISSUED | 5 Borough Renovations | 07/29/2024 |
| BIS | — | ISSUED | 5 Borough Renovations | 07/25/2023 |
| BIS | — | ISSUED | 5 Borough Renovations | 03/21/2023 |
| BIS | OT | ISSUED | KCC D+B | 04/28/2022 |
| BIS | OT | ISSUED | KCC D+B | 02/25/2022 |
| BIS | OT | ISSUED | Khatib Construction | 09/24/2020 |
| BIS | FS | ISSUED | Jack Piccini | 04/18/2019 |
| BIS | MH | ISSUED | Foremost Contracting & BU | 04/12/2019 |
| BIS | OT | ISSUED | Foremost Contracting & BU | 10/19/2018 |
| BIS | — | ISSUED | Foremost Contracting & BU | 10/12/2018 |
| BIS | OT | ISSUED | Foremost Contracting & BU | 09/11/2018 |
| BIS | PL | ISSUED | Reliable Plumbing & Heating | 08/22/2018 |
| BIS | EQ | ISSUED | Skyline Scaffolding Group | 05/25/2018 |
| BIS | FS | ISSUED | Champion Combustion | 05/17/2018 |
| BIS | OT | ISSUED | Foremost Contracting & BU | 04/12/2018 |
| BIS | OT | ISSUED | Foremost Contracting & BU | 04/12/2018 |
| BIS | MH | ISSUED | Foremost Contracting & BU | 04/12/2018 |
| BIS | MH | ISSUED | Foremost Contracting & BU | 04/03/2018 |
| BIS | MH | ISSUED | Foremost Contracting & BU | 03/16/2018 |
| BIS | SD | ISSUED | Allstate Sprinkler | 02/28/2018 |
| BIS | EQ | ISSUED | Foremost Contracting & BU | 02/26/2018 |
| BIS | SP | ISSUED | Allstate Sprinkler | 02/07/2018 |
| BIS | BL | ISSUED | Reliable Plumbing & Heating | 12/22/2017 |
| BIS | — | ISSUED | Foremost Contracting & BU | 12/08/2017 |
| BIS | EQ | ISSUED | Rockledge Scaffold | 11/14/2017 |
| BIS | EQ | ISSUED | Rockledge Scaffold | 10/30/2017 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/07/2020 | — | — | Air Conditioning Systems |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/12/2019 | — | — | 53 heads |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/09/2020 | Permit Issued | Katan P & H | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/14/2026 | Permit Issued | Limitless Electric Resources | — |
| 12/21/2023 | Permit Issued | Omd Electrical | 1 meters, 1 new_meters |
| 01/03/2023 | Complete | Atmos Electric Svce | — |
| 01/18/2022 | Complete | Solas Electrical Contracting | General Wiring |
| 05/14/2021 | Complete | WCK Electric | General Wiring |
| 12/23/2019 | Complete | Spectrum Electric | General Wiring |
| 08/12/2019 | Complete | M.R. Electrical Service | — |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/20/2026 | Final | LEON SKVIRSKY | progress |
| 05/16/2023 | Tenant Protection Plan Compliance | Luis Pichardo | special |
| 05/12/2023 | Final | RONALD VILLANO | progress |
| 01/12/2022 | HVAC and service water heating system controls | Anthony Rini, III | energy_progress |
| 01/12/2022 | Mechanical Systems | Anthony Rini, III | special |
| 01/12/2022 | Final | Anthony Rini, III | progress |
| 01/12/2022 | HVAC and service water heating equipment | Anthony Rini, III | energy_progress |
| 01/12/2022 | Maintenance information | Anthony Rini, III | energy_progress |
| 01/12/2022 | HVAC insulation and sealing | Anthony Rini, III | energy_progress |
| 01/11/2022 | Sprinkler Systems | Anthony Rini, III | special |
| 01/11/2022 | Fire-Resistant Penetrations and Joints | Anthony Rini, III | special |
| 01/11/2022 | Fire-Resistant Penetrations and Joints | Anthony Rini, III | special |
| 01/03/2022 | HVAC and service water heating system controls | — | energy_progress |
| 01/03/2022 | HVAC and service water heating equipment | — | energy_progress |
| 01/03/2022 | HVAC insulation and sealing | — | energy_progress |
| 01/03/2022 | Mechanical Systems | — | special |
| 01/03/2022 | Maintenance information | — | energy_progress |
| 01/03/2022 | Fire-Resistant Penetrations and Joints | — | special |
| 01/03/2022 | Final | — | progress |
| 10/02/2020 | HVAC and service water heating system controls | EUGENE BIFULCO | energy_progress |
| 10/02/2020 | Mechanical Systems | EUGENE BIFULCO | special |
| 10/02/2020 | Energy Code Compliance Inspections | EUGENE BIFULCO | progress |
| 10/02/2020 | Final | EUGENE BIFULCO | progress |
| 10/02/2020 | HVAC insulation and sealing | EUGENE BIFULCO | energy_progress |
| 10/02/2020 | Electrical motors | EUGENE BIFULCO | energy_progress |
| Tenant | Space | Floors | Renovation projects |
|---|---|---|---|
| Operation Falafel | Restaurant / Food Service | Cellar, Floors 1, 2, Roof | Project M00874071 Project M00331467 Project M00231562 Project M00231522 Project M00248234 |