← Back
Office with commercial, 7-19 stories
232 MADISON AVENUE
MANHATTAN · BIN 1017194
💬 Discuss this project
1925Year Built
16Stories
O6Building Class
C5-2Zoning
115,945 sfGross Floor Area
39Units
LL97 Covered1 Open Violation ▸FISP: SAFE
Office with commercial, 7-19 stories · Owner of record: DASHAL MADISON LLC · 7,735 sf lot · 14.99 FAR built · Flood zone X
Locations of Work
No floor-level scope or drawing coverage on file for this building.
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
ROCK GROUP NY303/22/2026
SATO CONSTRUCTION203/22/2026
DARSHAL MADISON LLC103/22/2026
OWNER OF 232 MADISON A303/22/2026
THE OWNER OF103/22/2026
DIME COMMUNITY BANK103/22/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
ENTHINK ENGINEERS LLC202/23/2022
GREEN DESIGN109/04/2020
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
PHOENIX SUTTON STR INCGeneral Contractor907/08/2026
JEROME KRITZElectrical303/21/2026
HEMANCHAL DEONARINEElectrical203/21/2026
CABARCAS II, FERNANDOElectrical103/21/2026
MCKOSKY, KEVINElectrical103/21/2026
SRM ELECTRICAL SVC INCElectrical103/22/2026
COASTAL ELEC CONSTRUCTIONElectrical103/21/2026
Building Lifecycle
All (84)Filed (3)Permit Issued (5)Signed Off (2)Facade (FISP) (12)Violation (60)Special Inspection (2)
06/22/2022
Cycle 9 facade report submitted
06/21/2022
Cycle 9 facade report signed — SAFE
05/20/2022
Signed off — Alteration
INSTALLATION OF TEMPORARY HEAVY DUTY SIDEWALK SHED AND PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE.LIVE LOAD 300PSF.
M00672913-I1
05/03/2022
Cycle 9 facade inspection completed
02/24/2022
Special inspection requirement — Final
Sunil Saigal
02/23/2022
Filed — Alteration
INSTALLATION OF TEMPORARY HEAVY DUTY SIDEWALK SHED AND PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE.LIVE LOAD 300PSF.
M00672913-P1
02/02/2022
Filed — Alteration
INSTALLATION OF TEMPORARY HEAVY DUTY SIDEWALK SHED AND PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE.LIVE LOAD 300PSF.
M00672913-I1
02/02/2022
Permit issued — Sidewalk Shed
M00672913-I1-SH
02/02/2022
Permit issued — Supported Scaffold
M00672913-I1-SF
11/26/2021
Signed off — Alteration
INSTALLATION OF TEMPORARY HEAVY DUTY SIDEWALK SHED AND PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE.LIVE LOAD 300PSF.
M00394978-I1
09/16/2021
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
09/16/2021
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
09/16/2021
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
09/01/2021
Permit issued — Supported Scaffold
M00394978-I1-SH
11/18/2020
Violation issued (ECB, closed)
Construction
11/04/2020
Violation issued (ECB, closed)
Construction
09/04/2020
Filed — Alteration
INSTALLATION OF TEMPORARY HEAVY DUTY SIDEWALK SHED AND PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE.LIVE LOAD 300PSF.
M00394978-I1
09/04/2020
Permit issued — Sidewalk Shed
M00394978-I1-SH
09/04/2020
Permit issued — Sidewalk Shed
M00394978-I1-SF
09/04/2020
Special inspection requirement — Final
Sunil Saigal
03/28/2019
Violation issued (ECB, closed)
Construction
10/11/2018
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
10/11/2018
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
01/26/2018
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
08/22/2017
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
08/22/2017
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
08/22/2017
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
08/17/2017
Cycle 8 facade report submitted
08/07/2017
Cycle 8 facade report signed — SAFE
07/31/2017
Cycle 8 facade inspection completed
11/14/2016
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
06/01/2016
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
06/01/2016
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
06/01/2016
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
03/10/2016
Violation issued (ECB, closed)
Construction
01/05/2016
Violation issued (ECB, closed)
Construction
01/05/2016
Violation issued (ECB, closed)
Construction
08/21/2015
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
08/21/2015
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
08/21/2015
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
03/30/2015
Violation issued (ECB, closed)
Construction
03/30/2015
Violation issued (ECB, closed)
Construction
03/30/2015
Violation issued (ECB, closed)
Construction
03/30/2015
Violation issued (ECB, closed)
Unknown
05/30/2014
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
08/29/2012
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
08/29/2012
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
08/29/2012
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
08/29/2012
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
08/26/2012
Cycle 7 facade report signed — SWARMP
08/20/2012
Cycle 7 facade report submitted
07/26/2012
Cycle 7 facade inspection completed
07/07/2011
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
10/08/2010
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
07/06/2010
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
07/06/2010
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
07/06/2010
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
01/21/2009
Violation issued (ECB, closed)
Elevators
01/09/2009
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
01/09/2009
Violation issued (DOB, open)
VW-VIOLATION WORK WITHOUT PERMIT - ACTIVE
Latest 60 of 84 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSidewalk ShedSigned-offPHOENIX SUTTON STR INC02/02/2022
DOB NOWSupported ScaffoldSigned-offPHOENIX SUTTON STR INC02/02/2022
DOB NOWSupported ScaffoldSigned-offPHOENIX SUTTON STR INC09/01/2021
DOB NOWSidewalk ShedSigned-offPHOENIX SUTTON STR INC09/04/2020
DOB NOWSidewalk ShedSigned-offPHOENIX SUTTON STR INC09/04/2020
BISMHISSUEDT.S.M. MECHANICAL CORP07/18/2019
BISMHISSUEDT.S.M. MECHANICAL CORP05/02/2019
BISOTISSUEDDYNAIRE LLC10/10/2018
BISMHISSUEDT.S.M. MECHANICAL CORP10/25/2016
BISOTISSUEDSATO CONSTRUCTION CO.INC04/15/2016
BISMHISSUEDT.S.M. MECHANICAL CORP01/15/2016
BISOTISSUEDSATO CONSTRUCTION CO.INC01/06/2016
BISOTISSUEDSATO CONSTRUCTION CO.INC12/31/2015
BISEQISSUEDROCK GROUP NY CORP08/07/2015
BISEQISSUEDROCK GROUP NY CORP07/15/2015
BISOTISSUEDSATO CONSTRUCTION CO.INC01/12/2015
BISOTISSUEDSATO CONSTRUCTION CO.INC10/08/2014
BISEQISSUEDROCK GROUP NY CORP07/16/2014
BISOTISSUEDEAST COAST RESTORATION &06/14/2011
BISMHISSUEDAIRTRONICS AIR COND CORP01/03/2011
BISSPISSUEDBUCKMILLER AUTO.SPKLR.COR06/22/2010
BISSPISSUEDBUCKMILLER AUTO.SPKLR.COR06/17/2009
BISSPISSUEDBUCKMILLER AUTO.SPKLR.COR03/24/2008
BISPLISSUEDISIS PLUMBING INC12/18/2007
BISEQISSUEDBAY RESTORATION CORP10/22/2007
BISEQISSUEDEVEREST SCAFFOLDING INC01/22/2007
BISOTISSUEDBAY RESTORATION CORP10/17/2006
BISEQISSUEDEVEREST SCAFFOLDING INC05/10/2006
BISMHISSUEDAIRTRONICS AIR CONDIT04/25/2005
BISMHISSUEDAMEBOSINO CONSUL. CORP10/04/2004
BIS—ISSUEDGOING SIGN & SVCNG CO,INC10/09/2003
BIS—ISSUEDGOING SIGN & SVCNG CO,INC09/16/2003
BISOTISSUEDACCURATE CONSTRUCTION04/20/2001
BISPLISSUEDCAPE PLUMBING INC03/26/2001
BISMHISSUEDMNE CONSTRUCTION INC.03/09/2001
BISMHISSUEDBARR & BARR INC10/28/1998
BISMHISSUEDBARR & BARR INC10/15/1998
BISEQISSUEDNEW CENTURY CONSTRUCTION CORP08/04/1998
BISEQISSUEDNEW CENTURY CONSTRUCTION CORP04/24/1998
BISOTISSUEDMOREAIR MECHANICAL SERVIC09/10/1997
+ 4 more permits on file
4 projects · most recent 03/20/2026
General Wiring
FiledStatusContractorScope
03/20/2026CompleteSRM ELECTRICAL SVC INCGeneral Wiring
10/02/2025CompleteSRM ELECTRICAL SVC INC—
01/28/2022CompleteELPO ELECTRICAL CONTG INC—
08/28/2020CompleteELPO ELECTRICAL CONTG INC—
▾Special Inspection Requirements (DOB NOW) — 2
DateRequirementInspectorRole
02/24/2022FinalSunil Saigalprogress
09/04/2020FinalSunil Saigalprogress
▾Documents — 289 on file (BIS + DOB NOW)
▸Plans & Drawings4
▸DOB NOWPlans/Sketch2
09/02/2026M00672913-I1Request digital key ↗
09/02/2026M00672913-P1Request digital key ↗
▸DOB NOWPlans/Sketch - Supported Scaffold1
09/04/2026M00394978-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Sidewalk Shed1
09/04/2026M00394978-I1Request digital key ↗
▸Applications & Permits52
▸BISPLAN / WORK APPROVAL APPLICATION28
09/09/2019140858070Open ↗
09/05/2019140858070Open ↗
06/28/2019140858070Open ↗
Showing 3 of 28 on file for this type
▸BISWORK PERMIT APPLICATION24
06/28/2019140858070Open ↗
06/28/2019140858070Open ↗
05/02/2019140846084Open ↗
Showing 3 of 24 on file for this type
▸Seals & Professional Certifications66
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION26
09/11/2019140858070Open ↗
06/03/2019140846084Open ↗
06/03/2019140846084Open ↗
Showing 3 of 26 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST9
09/04/2019140858070Open ↗
09/03/2019140858070Open ↗
05/30/2019140846084Open ↗
Showing 3 of 9 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT8
06/28/2019140858070Open ↗
05/01/2019140846084Open ↗
10/03/2018140808437Open ↗
Showing 3 of 8 on file for this type
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION7
06/28/2019140858070Open ↗
05/01/2019140846084Open ↗
10/03/2018140808437Open ↗
Showing 3 of 7 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY6
06/28/2019140858070Open ↗
05/01/2019140846084Open ↗
10/03/2018140808437Open ↗
Showing 3 of 6 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature3
09/02/2026M00672913-I1Open ↗
09/02/2026M00672913-P1Open ↗
08/13/2026M00394978-I1Open ↗
▸BISPC FULL REPORT2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸DOB NOWProgress Inspector Seal & Signature2
08/26/2026M00672913-I1Open ↗
08/23/2026M00394978-I1Open ↗
▸Trade Schedules & Equipment42
▸BISEQUIPMENT USE PERMITS24
09/11/2019140858070Open ↗
09/11/2019140858070Open ↗
09/11/2019140858070Open ↗
Showing 3 of 24 on file for this type
▸BISEQUIPMENT USE APPLICATION/PERMIT12
09/11/2019140858070Open ↗
09/11/2019140858070Open ↗
09/11/2019140858070Open ↗
Showing 3 of 12 on file for this type
▸BISSELF-CERT PLUMBING NOTICE3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISSCHEDULE B - PLUMBING2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISSPRINKLER INSP REPORT : FP-851
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Safety & Tenant Protection1
▸BISSTREET TREE CHECKLIST1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Environmental & Asbestos12
▸BISASBESTOS: CERTIFICATION (DEP ACP5)7
06/28/2019140858070Open ↗
05/01/2019140846084Open ↗
10/03/2018140808437Open ↗
Showing 3 of 7 on file for this type
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'5
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 5 on file for this type
▸Energy Compliance26
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS8
09/11/2019140858070Open ↗
01/18/2019140808437Open ↗
07/18/2017121964213Open ↗
Showing 3 of 8 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS8
09/11/2019140858070Open ↗
06/03/2019140846084Open ↗
01/18/2019140808437Open ↗
Showing 3 of 8 on file for this type
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY5
06/28/2019140858070Open ↗
05/01/2019140846084Open ↗
10/03/2018140808437Open ↗
Showing 3 of 5 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS5
06/28/2019140858070Open ↗
05/01/2019140846084Open ↗
10/03/2018140808437Open ↗
Showing 3 of 5 on file for this type
▸Inspections & Test Reports9
▸BISTECHNICAL REPORT: RESPONSIBILITY9
06/28/2019140858070Open ↗
05/01/2019140846084Open ↗
10/03/2018140808437Open ↗
Showing 3 of 9 on file for this type
▸Approvals, Objections & Sign-offs25
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST12
09/11/2019140858070Open ↗
06/03/2019140846084Open ↗
01/18/2019140808437Open ↗
Showing 3 of 12 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION5
09/11/2019140858070Open ↗
06/03/2019140846084Open ↗
01/18/2019140808437Open ↗
Showing 3 of 5 on file for this type
▸BISADMINISTRATIVE OBJECTIONS4
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type
▸BISSUPERSEDING LETTER2
04/28/2016121964213Open ↗
07/23/2015122069475Open ↗
▸BISSHED LETTER1
07/23/2015122069475Open ↗
▸BISCONSTRUCTION CODE DETERMINATION1
05/09/2015121964213Open ↗
▸Cost, Insurance & Ownership26
▸BISCOST AFFIDAVIT26
09/11/2019140858070Open ↗
06/28/2019140858070Open ↗
06/03/2019140846084Open ↗
Showing 3 of 26 on file for this type
▸Filing & Intake Forms25
▸BISADDITIONAL INFORMATION9
10/25/2018140808437Open ↗
03/09/2016140445098Open ↗
03/09/2016140445098Open ↗
Showing 3 of 9 on file for this type
▸BISEFILING JOB APPLICATION COVER SHEET7
06/28/2019140858070Open ↗
05/01/2019140846084Open ↗
10/03/2018140808437Open ↗
Showing 3 of 7 on file for this type
▸BISBOROUGH INTAKE FORM5
09/11/2019140858070Open ↗
09/03/2019140858070Open ↗
06/03/2019140846084Open ↗
Showing 3 of 5 on file for this type
▸BISEFILING COVER SHEET4
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type
▸Other Documents1
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION1
09/11/2019140858070Open ↗