Three families · Owner of record: 2322 Holland Ave · 5,000 sf lot · 0.64 FAR built · Flood zone X
Locations of Work
Civil
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Floor 4New Twenty-eight Family Residence1 filing · 19 docs
Floor 3New Twenty-eight Family Residence1 filing · 19 docs
Floor 2
Floor 1
CellarNew Twenty-eight Family Residence1 filing · 19 docs
Filed — no permit issued1 filing · 3 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
New Line Builders410/13/2026
2322 Holland Ave103/22/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
06/24/2026$1.3M—2322 HOLLAND AVE LLC → STELUM REALTY LLC$406/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
Plus355 Integrated Solutions308/14/2026
Fred Geremia, Architects & Planners108/13/2026
Building Lifecycle
09/16/2026
Objection raised — Other
09/16/2026
Objection raised — Energy
09/16/2026
Objection raised — Scope
09/03/2026
Objection raised — Admin
09/03/2026
Objection raised — Structural
54 history events on file for this building. Sign in free to see the full history. Sign in · Create account
Nothing on file for this building.
1 project · most recent 08/14/2026
FiledStatusContractorScope
08/14/2026———
▾Special Inspection Requirements (DOB NOW) — 29
DateRequirementInspectorRole
08/14/2026Excavations - Sheeting, Shoring, and Bracing—special
08/14/2026Subsurface Investigations (Borings/Test Pits)—special
08/14/2026Subgrade Inspections—special
08/14/2026Structural Stability – Alterations of existing buildings—special
08/14/2026Footing and Foundation—progress
08/14/2026Subsurface Investigations (Borings/Test Pits)—special
08/14/2026Subgrade Inspections—special
08/14/2026Concrete - Cast-In-Place—special
08/14/2026Concrete - Cast-In-Place—special
08/13/2026Footing and Foundation—progress
08/13/2026Final—progress
08/13/2026Final—progress
08/07/2026Fenestration and door U-factor and product ratings—energy_progress
08/07/2026Air barrier - visual inspection—energy_progress
08/07/2026Fire-Resistant Penetrations and Joints—special
08/07/2026Maintenance information—energy_progress
08/07/2026Electrical motors and elevators—energy_progress
08/07/2026Protection of exposed foundation insulation—energy_progress
08/07/2026Energy Code Compliance Inspections—progress
08/07/2026Fire-Resistance Rated Construction—progress
08/07/2026Fenestration areas—energy_progress
08/07/2026Insulation placement and R values—energy_progress
08/07/2026Exterior lighting power—energy_progress
08/07/2026Lighting controls—energy_progress
08/07/2026Air barrier — testing —energy_progress