| Owner | Filings | Most Recent |
|---|---|---|
| OWNER OF 2323 VALENTINE A | 1 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 10/30/2025 | $3.6M | — | — → — | — not available |
| Firm | Filings | Most Recent |
|---|---|---|
| HAZI ENGINEERING | 4 | 06/10/2026 |
| NODE ARCHITECTURE,ENGINEERING, CONS | 7 | 05/27/2026 |
| GREENLITE CONSULTING CORP | 2 | 05/12/2026 |
| Representative | Filings | Most Recent |
|---|---|---|
| NODE ARCHITECTURE,ENGINEERING,CON | 4 | 03/21/2026 |
| NODE ENGINEERING CONSULTING | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| HENNAN GROUP INC | General Contractor | 1 | 04/09/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Construction Fence | Permit Issued | HENNAN GROUP | 12/04/2025 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/10/2026 | — | — | Heating and Air Conditioning Systems |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/10/2026 | — | — | Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/18/2018 | Permit Issued | V. VASS ELECTRIC CORP | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/10/2026 | — | — | Concrete |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/01/2025 | Permit Issued | HENNAN GROUP INC | Fence |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/27/2026 | Construction Operations Influencing Adjacent Structures | — | special |
| 07/27/2026 | Subsurface Conditions – Fill Placement & In-Place Density | — | special |
| 07/27/2026 | Excavations - Sheeting, Shoring, and Bracing | — | special |
| 07/27/2026 | Subgrade Inspections | — | special |
| 06/11/2026 | Combustible Exterior Wall Coverings | — | special |
| 06/11/2026 | Fire-Resistant Penetrations and Joints | — | special |
| 06/11/2026 | Fire-Resistance Rated Construction | — | progress |
| 06/11/2026 | Energy Code Compliance Inspections | — | progress |
| 06/11/2026 | Air barrier — testing | — | energy_progress |
| 06/11/2026 | Maintenance information | — | energy_progress |
| 06/11/2026 | Air barrier continuity plan testing | — | energy_progress |
| 06/11/2026 | Protection of exposed foundation insulation | — | energy_progress |
| 06/11/2026 | Fenestration and door U-factor and product ratings | — | energy_progress |
| 06/11/2026 | Metering | — | energy_progress |
| 06/11/2026 | Exterior lighting power | — | energy_progress |
| 06/11/2026 | Fenestration areas | — | energy_progress |
| 06/11/2026 | Interior lighting power | — | energy_progress |
| 06/11/2026 | Electrical motors and elevators | — | energy_progress |
| 06/11/2026 | Lighting in dwelling units | — | energy_progress |
| 06/11/2026 | Lighting controls | — | energy_progress |
| 06/11/2026 | Air barrier - visual inspection | — | energy_progress |
| 06/11/2026 | Fenestration air leakage | — | energy_progress |
| 06/11/2026 | Insulation placement and R values | — | energy_progress |
| 05/22/2026 | Fire-Resistant Penetrations and Joints | — | special |
| 05/22/2026 | Fire-Resistant Penetrations and Joints | — | special |