← Back
Elevator apt, semi-fireproof without stores
233 EAST 202 STREET
BRONX · BIN 2129785
💬 Discuss this project
2025Year Built
8Stories
D1Building Class
R8Zoning
30,469 sfGross Floor Area
44Units
Rent Stabilized3 Open Violations ▸
Elevator apt, semi-fireproof without stores · Owner of record: 233 EAST 202 LLC · 5,000 sf lot · 6.09 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbingFire Protection
Floor 514p · 1 filing · 20 docs
Floor 414p · 1 filing · 20 docs
Floor 316p · 1 filing · 20 docs
Floor 216p · 1 filing · 20 docs
Floor 116p · 1 filing · 20 docs
Cellar17p · 1 filing · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
2625 GRAND AVENUE2807/08/2026
233 EAST 202 LLC103/22/2026
NEW LINE CONSTRUCTION203/22/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
06/06/2023$2.4M—— → —— not available
▾Design Consultants (Architect / Engineer of Record)
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
NEW LINE CONSTRUCTION LLCGeneral Contractor907/08/2026
PRIME PIPING & HEATING INFire Protection107/08/2026
PRIME PIPING & HEATING INPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
REGIONAL TESTING CORP.394501/31/2025
KCE CONSULTING ENGINEERIN3712401/12/2025
AUTOMATED DESIGN CONSULTA895204/22/2024
Building Lifecycle
All (29)Filed (17)Signed Off (12)
05/14/2026
Signed off — New Building
Install sprinkler system in conjunction with NB. The system is hydraulically calculated.
X00930842-I1
07/08/2025
Signed off — Alteration
X00921535-I1
06/27/2025
Signed off — New Building
Install sprinkler system in conjunction with NB. The system is hydraulically calculated.
X00930842-S3
06/27/2025
Signed off — New Building
Install sprinkler system in conjunction with NB. The system is hydraulically calculated.
X00930842-S6
06/26/2025
Signed off — New Building
Install sprinkler system in conjunction with NB. The system is hydraulically calculated.
X00930842-S5
06/25/2025
Signed off — New Building
Install sprinkler system in conjunction with NB. The system is hydraulically calculated.
X00930842-S4
06/24/2025
Signed off — New Building
Install sprinkler system in conjunction with NB. The system is hydraulically calculated.
X00930842-S1
06/20/2025
Signed off — Alteration
X01113203-S1
06/20/2025
Signed off — Alteration
X01113203-I1
05/19/2025
Signed off — New Building
Install sprinkler system in conjunction with NB. The system is hydraulically calculated.
X00930842-S7
03/14/2025
Signed off — New Building
Install sprinkler system in conjunction with NB. The system is hydraulically calculated.
X00930842-S2
02/01/2025
Filed — New Building
Install sprinkler system in conjunction with NB. The system is hydraulically calculated.
X00930842-P5
01/31/2025
Filed — New Building
Install sprinkler system in conjunction with NB. The system is hydraulically calculated.
X00930842-P4
01/31/2025
Filed — New Building
Install sprinkler system in conjunction with NB. The system is hydraulically calculated.
X00930842-P3
01/12/2025
Filed — New Building
Install sprinkler system in conjunction with NB. The system is hydraulically calculated.
X00930842-P2
10/28/2024
Filed — New Building
Install sprinkler system in conjunction with NB. The system is hydraulically calculated.
X00930842-P1
09/18/2024
Filed — Alteration
X01113203-S1
09/18/2024
Filed — Alteration
X01113203-I1
07/26/2024
Filed — New Building
Install sprinkler system in conjunction with NB. The system is hydraulically calculated.
X00930842-S7
04/24/2024
Filed — New Building
Install sprinkler system in conjunction with NB. The system is hydraulically calculated.
X00930842-S3
04/22/2024
Filed — New Building
Install sprinkler system in conjunction with NB. The system is hydraulically calculated.
X00930842-S6
04/15/2024
Filed — New Building
Install sprinkler system in conjunction with NB. The system is hydraulically calculated.
X00930842-S5
04/15/2024
Filed — New Building
Install sprinkler system in conjunction with NB. The system is hydraulically calculated.
X00930842-S4
02/13/2024
Filed — New Building
Install sprinkler system in conjunction with NB. The system is hydraulically calculated.
X00930842-S1
02/13/2024
Filed — New Building
Install sprinkler system in conjunction with NB. The system is hydraulically calculated.
X00930842-S2
11/20/2023
Signed off — Full Demolition
Full demolition to a two story house
X00896051-I1
09/11/2023
Filed — New Building
Install sprinkler system in conjunction with NB. The system is hydraulically calculated.
X00930842-I1
08/21/2023
Filed — Alteration
X00921535-I1
07/19/2023
Filed — Full Demolition
Full demolition to a two story house
X00896051-I1
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWFoundationSigned-offNEW LINE CONSTRUCTION LLC05/13/2025
DOB NOWMechanical SystemsSigned-offNEW LINE CONSTRUCTION LLC04/07/2025
DOB NOWSprinklersSigned-offA M B MECHANICAL INC03/27/2025
DOB NOWGeneral ConstructionPermit IssuedNEW LINE CONSTRUCTION LLC11/01/2024
DOB NOWSupport of ExcavationSigned-offNEW LINE CONSTRUCTION LLC10/31/2024
DOB NOWStructuralSigned-offNEW LINE CONSTRUCTION LLC10/31/2024
DOB NOWStructuralSigned-offNEW LINE CONSTRUCTION LLC10/07/2024
DOB NOWGeneral ConstructionPermit IssuedNEW LINE CONSTRUCTION LLC10/04/2024
DOB NOWPlumbingSigned-offPRIME PIPING & HEATING IN09/27/2024
DOB NOWSidewalk ShedSigned-offCONSOLIDATED SCAFFOLDING09/18/2024
DOB NOWProtection and Mechanical MethodsSigned-offCONSOLIDATED SCAFFOLDING09/18/2024
DOB NOWConstruction FenceSigned-offPARAMOUNT HOME MNGMT INC09/06/2024
DOB NOWSupport of ExcavationSigned-offNEW LINE CONSTRUCTION LLC04/11/2024
DOB NOWFoundationSigned-offNEW LINE CONSTRUCTION LLC04/05/2024
DOB NOWFull DemolitionSigned-offFIRST WORLD DEVELOPMENT10/23/2023
DOB NOWConstruction FenceSigned-offPARAMOUNT HOME MNGMT INC09/06/2023
1 project · most recent 02/01/2025
Heating and Air Conditioning Systems Ventilation Systems
FiledStatusContractorScopeMake / Model / Capacity
02/01/2025Signed-offNEW LINE CONSTRUCTION LLCHeating and Air Conditioning Systems, Ventilation Systems
Heat / Cool
Amana PTH123G50AXXX 12,000 BTU · Ptac ×44
PTH073G35AXXX 7,600 BTU · Ptac ×31
Cadet CEC163TW 5,115 BTU · Electric Heater ×42
Friedrich PDH12K3SGR3 12,000 BTU · Heat Pump Outdoor ×44
PDH09K3SGR3 7,600 BTU · Heat Pump Outdoor ×31
Ventilation
Panasonic FV-0511VFL1 50 CFM · Exhaust Fan ×90
Broan 413001 150 CFM · Kitchen Exhaust ×88
Fantech REC10XL 680 CFM · Exhaust Fan ×12
REC8XL 320 CFM · Exhaust Fan ×4
1 project · most recent 02/01/2025
Storm Water/Sanitary
FiledStatusContractorScope
02/01/2025Signed-offA M B MECHANICAL INCStorm, Water/Sanitary
4 projects · most recent 06/16/2025
General Wiring
FiledStatusContractorScope
06/16/2025CompleteJAM ELECTRICAL CORP—
03/05/2025CompleteJ&H ELECTRICAL CONT INCGeneral Wiring
12/11/2024CompleteJ&H ELECTRICAL CONT INC—
09/19/2024CompleteSOLAS ELECTRICAL CORP—
1 project · most recent 02/01/2025
Steel Concrete Masonry
FiledStatusContractorScope
02/01/2025Signed-offNEW LINE CONSTRUCTION LLCSteel, Concrete, Masonry
▾Field Inspections (DOB CAP) — 11
DateTypeResultReport
08/06/2025Pass-Final CND-Occupancy InspectionPassView ↗
07/10/2025Pass-Final CND-Occupancy InspectionPassView ↗
06/20/2025Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
06/17/2025Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
02/26/2025Certified Storm Drainage-ST-Piping-RoughingCertifiedView ↗
10/07/2024Certified Storm Drainage-ST-Piping-UndergroundCertifiedView ↗
10/07/2024Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
09/18/2023Pass-Final CND-Occupancy InspectionPassView ↗
09/07/2023Fail-Final CND-Occupancy InspectionFailView ↗
08/25/2023Fail-Final CND-Occupancy InspectionFailView ↗
08/16/2023Fail-Final CND-Occupancy InspectionFailView ↗
▾Special Inspection Requirements (DOB NOW) — 57
DateRequirementInspectorRole
02/03/2025HVAC-R and service water heating system controlsGregory Mortmanenergy_progress
02/03/2025FinalGregory Mortmanprogress
02/03/2025Energy Code Compliance InspectionsGregory Mortmanprogress
02/03/2025HVAC-R and service water heating equipmentGregory Mortmanenergy_progress
02/03/2025HVAC-R and service water heating system controlsGregory Mortmanenergy_progress
02/03/2025HVAC-R and service water piping design and insulationGregory Mortmanenergy_progress
02/03/2025Maintenance informationGregory Mortmanenergy_progress
02/03/2025Shutoff dampersGregory Mortmanenergy_progress
02/03/2025HVAC-R and service water heating equipmentGregory Mortmanenergy_progress
02/03/2025HVAC-R and service water piping design and insulationGregory Mortmanenergy_progress
02/03/2025Maintenance informationGregory Mortmanenergy_progress
02/03/2025Ventilation and air distribution systemGregory Mortmanenergy_progress
02/03/2025Mechanical SystemsGregory Mortmanspecial
01/31/2025Ventilation and air distribution system—energy_progress
01/31/2025Mechanical SystemsPaul Raymondspecial
01/31/2025FinalPaul Raymondprogress
01/31/2025Maintenance information—energy_progress
01/31/2025HVAC-R and service water heating system controls—energy_progress
01/31/2025HVAC-R and service water piping design and insulation—energy_progress
01/31/2025HVAC-R and service water heating equipment—energy_progress
01/31/2025Shutoff dampers—energy_progress
01/31/2025Energy Code Compliance InspectionsGregory Mortmanprogress
01/31/2025Maintenance informationGregory Mortmanenergy_progress
01/31/2025HVAC-R and service water piping design and insulationGregory Mortmanenergy_progress
01/31/2025HVAC-R and service water heating system controlsGregory Mortmanenergy_progress
Latest 25 of 57.
▾Documents — 97 on file (BIS + DOB NOW)
▸Plans & Drawings17
▸DOB NOWPlans/Sketch17
08/22/2026X00896051-I1Request digital key ↗
08/22/2026X00921535-I1Request digital key ↗
08/21/2026X00930842-I1Request digital key ↗
Showing 3 of 17 on file for this type
▸Zoning, Tax Lot & Property Records5
▸DOB NOWZD1: DOB Zoning Diagram2
08/13/2026X00930842-P1Open ↗
08/13/2026X00930842-I1Open ↗
▸DOB NOWZoning Exhibit form (1-5)2
08/13/2026X00930842-I1Open ↗
08/13/2026X00930842-P1Open ↗
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/13/2026X00930842-I1Open ↗
▸Seals & Professional Certifications56
▸DOB NOWSpecial Inspector Seal & Signature27
08/28/2026X00930842-S7Open ↗
08/28/2026X00930842-S7Open ↗
08/28/2026X00930842-S7Open ↗
Showing 3 of 27 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature16
08/22/2026X00921535-I1Open ↗
08/21/2026X00930842-I1Open ↗
08/21/2026X00930842-P5Open ↗
Showing 3 of 16 on file for this type
▸DOB NOWProgress Inspector Seal & Signature13
08/28/2026X00930842-S7Open ↗
08/28/2026X00930842-S7Open ↗
08/28/2026X00930842-S5Open ↗
Showing 3 of 13 on file for this type
▸Trade Schedules & Equipment2
▸DOB NOWDEP: Sewer Certification (Sanitary/Storm)2
08/13/2026X00930842-I1Open ↗
08/13/2026X00930842-P1Open ↗
▸Safety & Tenant Protection5
▸DOB NOWStreet Tree Checklist2
08/13/2026X00930842-P1Open ↗
08/13/2026X00930842-I1Open ↗
▸DOB NOWStreet Tree Sign Off1
08/13/2026X00930842-I1Open ↗
▸DOB NOWStreet Trees Site Plan1
08/13/2026X00930842-I1Open ↗
▸DOB NOWParks Department Acknowledgment Letter for Street Trees Plan1
08/13/2026X00930842-I1Open ↗
▸Environmental & Asbestos1
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/22/2026X00896051-I1Open ↗
▸Energy Compliance2
▸DOB NOWPreliminary Commissioning Report Certification2
08/13/2026X00930842-S4Open ↗
08/13/2026X00930842-S5Open ↗
▸Other Documents9
▸DOB NOWProperty Ownership Certification3
08/22/2026X00896051-I1Open ↗
08/21/2026X00930842-I1Open ↗
08/21/2026X00930842-P1Open ↗
▸DOB NOWSite Survey: Initial2
08/13/2026X00930842-P1Open ↗
08/13/2026X00930842-I1Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone2
08/13/2026X00930842-I1Open ↗
08/13/2026X00930842-P1Open ↗
▸DOB NOWFinal Survey1
08/13/2026X00930842-I1Open ↗
▸DOB NOWAdjoining Owners Notification1
08/13/2026X00930842-S1Open ↗