RoofUnder Construction10p · 2 filings · 12 docs
ArchitectureMechanical
Issued Permit Scope
General Construction · Mechanical Systems
Propose to remove interior non bearing partitions as per plans filed herewith. No change in use egress or occupancy is proposed under this application.
On file for this project
4 documents
Propose to install mechanical equipment as per plans filed herewith. No change in use egress or occupancy is proposed under this application.
On file for this project
8 documents
Floor 6Under Construction13p · 3 filings · 20 docs
ArchitectureFire ProtectionMechanical
Issued Permit Scope
General Construction · Mechanical Systems · Sprinklers
Propose to install plumbing and sprinkler system as per plans filed herewith. No change in use egress or occupancy is proposed under this application.
On file for this project
10 documents
Propose to remove interior non bearing partitions as per plans filed herewith. No change in use egress or occupancy is proposed under this application.
On file for this project
4 documents
Propose to install mechanical equipment as per plans filed herewith. No change in use egress or occupancy is proposed under this application.
On file for this project
8 documents
Floor 5Under Construction13p · 3 filings · 20 docs
ArchitectureFire ProtectionMechanical
Issued Permit Scope
General Construction · Mechanical Systems · Sprinklers
Propose to install plumbing and sprinkler system as per plans filed herewith. No change in use egress or occupancy is proposed under this application.
On file for this project
10 documents
Propose to remove interior non bearing partitions as per plans filed herewith. No change in use egress or occupancy is proposed under this application.
On file for this project
4 documents
Propose to install mechanical equipment as per plans filed herewith. No change in use egress or occupancy is proposed under this application.
On file for this project
8 documents
Floor 4Under Construction13p · 3 filings · 20 docs
ArchitectureFire ProtectionMechanical
Issued Permit Scope
General Construction · Mechanical Systems · Sprinklers
Propose to install plumbing and sprinkler system as per plans filed herewith. No change in use egress or occupancy is proposed under this application.
On file for this project
10 documents
Propose to remove interior non bearing partitions as per plans filed herewith. No change in use egress or occupancy is proposed under this application.
On file for this project
4 documents
Propose to install mechanical equipment as per plans filed herewith. No change in use egress or occupancy is proposed under this application.
On file for this project
8 documents
Floor 3Under Construction15p · 3 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Sprinklers
Propose to install plumbing and sprinkler system as per plans filed herewith. No change in use egress or occupancy is proposed under this application.
On file for this project
10 documents · 2 drawing sheets
Propose to remove interior non bearing partitions as per plans filed herewith. No change in use egress or occupancy is proposed under this application.
On file for this project
4 documents
Propose to install mechanical equipment as per plans filed herewith. No change in use egress or occupancy is proposed under this application.
On file for this project
8 documents
Floor 2Under Construction17p · 4 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Sprinklers · Structural
Propose to install plumbing and sprinkler system as per plans filed herewith. No change in use egress or occupancy is proposed under this application.
On file for this project
10 documents · 1 drawing sheet
Propose to remove interior non bearing partitions as per plans filed herewith. No change in use egress or occupancy is proposed under this application.
On file for this project
4 documents
Propose to install mechanical equipment as per plans filed herewith. No change in use egress or occupancy is proposed under this application.
On file for this project
8 documents
Latest 3 of 4 filings on this floor.
Floor 1Under Construction13p · 3 filings · 20 docs
ArchitectureFire ProtectionMechanical
Issued Permit Scope
General Construction · Mechanical Systems · Sprinklers
Propose to install plumbing and sprinkler system as per plans filed herewith. No change in use egress or occupancy is proposed under this application.
On file for this project
10 documents
Propose to remove interior non bearing partitions as per plans filed herewith. No change in use egress or occupancy is proposed under this application.
On file for this project
4 documents
Propose to install mechanical equipment as per plans filed herewith. No change in use egress or occupancy is proposed under this application.
On file for this project
8 documents
CellarUnder Construction14p · 3 filings · 20 docs
ArchitectureFire ProtectionMechanical
Issued Permit Scope
General Construction · Mechanical Systems · Sprinklers
Propose to install plumbing and sprinkler system as per plans filed herewith. No change in use egress or occupancy is proposed under this application.
On file for this project
10 documents · 1 drawing sheet
Propose to remove interior non bearing partitions as per plans filed herewith. No change in use egress or occupancy is proposed under this application.
On file for this project
4 documents
Propose to install mechanical equipment as per plans filed herewith. No change in use egress or occupancy is proposed under this application.
On file for this project
8 documents
Site & exterior4p · 1 filing · 3 docs
EquipmentGeneralMechanicalStructural
Issued Permit Scope
Sidewalk Shed
INSTALLATION OF TEMPORARY HEAVY DUTY SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY. SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF 2022 THE NYC BUILDING CODE. LIVE LOAD 300PSF.
On file for this project
3 documents · 4 drawing sheets