| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 12/27/2021 | $1.2M | — | Private party → EASTCHESTER PROPERTY HOLDINGS LLC | $220/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| DDG ARCHITECTURE, P.C. | 1 | 06/12/2025 |
| GERALD CALIENDO ARCHITECTS | 6 | 04/07/2025 |
| SIDERIS KEFALAS ENGINEERS PC | 1 | 11/07/2022 |
| Representative | Filings | Most Recent |
|---|---|---|
| GERALD J CALIENDO ARCHITECT P C | 12 | 03/21/2026 |
| D+DG ARCHITECTURE | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| DASR CORP | General Contractor | 5 | 07/08/2026 |
| AMC PLBG, HTG & CLNG, INC | Plumbing | 4 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| HRF SERVICES CORP | 5616 | 7 | 04/07/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Permit Issued | DASR CORP | 12/06/2024 |
| DOB NOW | General Construction | Permit Issued | DASR CORP | 08/02/2023 |
| DOB NOW | Plumbing | Signed-off | AMC PLBG, HTG & CLNG, INC | 12/02/2022 |
| DOB NOW | General Construction | Signed-off | DASR CORP | 08/03/2022 |
| BIS | — | ISSUED | HIGH POINT ENGINEERING | 06/04/2015 |
| BIS | OT | ISSUED | CAPITAL 2 CONSTRUCTION & | 04/01/2015 |
| BIS | — | ISSUED | HIGH POINT ENGINEERING | 12/17/2014 |
| BIS | SP | ISSUED | TTM GROUP CORP | 12/02/2010 |
| BIS | PL | ISSUED | TT MECHANICAL CORP | 12/02/2010 |
| BIS | SP | ISSUED | R.V.S. PLBG & HTG INC | 02/10/2009 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 06/12/2025 | — | — | Others | Other Greenheck ×1 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/29/2022 | Permit Issued | KWONG MING ELECTRIC INC | — |
| Date | Type | Result | Report |
|---|---|---|---|
| 09/15/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 05/16/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 09/18/2024 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 04/25/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 09/21/2023 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 09/19/2023 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 09/19/2023 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 08/11/2023 | Fail-Final CND-Occupancy Inspection | Fail | View ↗ |
| 12/09/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 06/08/2025 | Insulation placement and R values | — | energy_progress |
| 06/08/2025 | Interior lighting power | — | energy_progress |
| 06/08/2025 | Lighting controls | — | energy_progress |
| 06/08/2025 | Fire-Resistant Penetrations and Joints | — | special |
| 06/05/2025 | Final | — | progress |
| 06/05/2025 | Mechanical Systems | — | special |
| 04/07/2025 | Lighting controls | FAHAD FATEH | energy_progress |
| 04/07/2025 | Permanent certificate | FAHAD FATEH | energy_progress |
| 04/07/2025 | HVAC-R and service water heating system controls | FAHAD FATEH | energy_progress |
| 04/07/2025 | Electrical motors and elevators | FAHAD FATEH | energy_progress |
| 04/07/2025 | Fire-Resistant Penetrations and Joints | FAHAD FATEH | special |
| 04/07/2025 | HVAC-R and service water heating equipment | FAHAD FATEH | energy_progress |
| 04/07/2025 | Energy Code Compliance Inspections | FAHAD FATEH | progress |
| 04/07/2025 | Maintenance information | FAHAD FATEH | energy_progress |
| 04/07/2025 | HVAC-R and service water piping design and insulation | FAHAD FATEH | energy_progress |
| 04/07/2025 | Interior lighting power | FAHAD FATEH | energy_progress |
| 04/07/2025 | Exterior lighting power | FAHAD FATEH | energy_progress |
| 10/02/2023 | Structural Stability – Alterations of existing buildings | FAHAD FATEH | special |
| 10/02/2023 | Energy Code Compliance Inspections | FAHAD FATEH | progress |
| 10/02/2023 | Interior lighting power | FAHAD FATEH | energy_progress |
| 10/02/2023 | Lighting controls | FAHAD FATEH | energy_progress |
| 10/02/2023 | Fire-Resistant Penetrations and Joints | FAHAD FATEH | special |
| 09/28/2023 | Structural Stability – Alterations of existing buildings | FAHAD FATEH | special |
| 09/28/2023 | Fire-Resistant Penetrations and Joints | FAHAD FATEH | special |
| 09/28/2023 | Energy Code Compliance Inspections | FAHAD FATEH | progress |