← Back
BuildNYC
Police Department
235 EAST 20TH STREET
MANHATTAN · Gramercy · BIN 1019613
💬 Discuss this project
1964Year Built
9Stories
Y2Building Class
R8BZoning
313,625 sfGross Floor Area
1Units
LL97 Covered13 Active Violations 2 unresolved · 11 paperwork only 2 likely answered 4 old, status unconfirmed ▸FISP: No Report Filed
Police Department · Owner of record: NYC Police Department · 42,412 sf lot · 7.39 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbingEquipmentLandscapeGeneral
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Permit Issued — active, not yet Signed-off
Floor 4New York Police Department1 filing · 8 docs
Floor 3New York Police Department1 filing · 8 docs
Floor 2Nypdjec Cadet Assessment Center, New York Police Department10p · 16 filings · 14 docs
Floor 1Nypdjec Cadet Assessment Center, New York Police DepartmentUnder Construction5p · 4 filings · 16 docs
Sub-BasementNypdjec Cadet Assessment Center1 filing · 3 docs
Site & exterior2p · 1 filing · 4 docs
Filed — no permit issuedSidewalk shed installation5p · 1 filing · 3 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
NYC Department of Design and Construction1803/21/2026
New York Police Department703/22/2026
NYPD703/22/2026
NYC Department of Housing Preservation and Development203/21/2026
City203/21/2026
DGS203/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
Mje Professional Services305/09/2025
Steven Reinert Architect707/03/2024
Associates111/04/2022
Rocco Defranco Architect709/13/2022
The Liro Group203/25/2021
Liro Architects + Planners103/05/2021
Green Design210/27/2020
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
Liro Architects + Planner303/21/2026
Atlantic Building Supply203/21/2026
YBL NY203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
LB and J ConstructionScaffold1608/21/2026
Hard Rock ConstructionScaffold1207/08/2026
R & L SystemsElectrical203/21/2026
Bulls Eye ContractorScaffold207/08/2026
N.Y.C. Police DepartmentElectrical203/21/2026
P & M Elect'l ContractingElectrical103/22/2026
Threetech ElectricElectrical103/21/2026
Inner City Electrical ContractorsElectrical103/21/2026
New Amsterdam ResElectrical103/21/2026
Approved Electric Cont'gElectrical103/22/2026
Building Lifecycle
All (146)Filed (23)Permit Issued (20)Facade (FISP) (9)Violation (60)Objection (24)Special Inspection (10)
08/20/2026
Permit issued — Sidewalk Shed
M01026693-I1-SH
08/20/2026
Permit issued — Sidewalk Shed
M01025315-I1-SH
05/29/2026
Permit issued — Sidewalk Shed
M01025315-I1-SH
05/28/2026
Permit issued — Sidewalk Shed
M01026693-I1-SH
03/23/2026
Violation issued (ECB, open)
Elevators
03/13/2026
Permit issued — Sidewalk Shed
M01025315-I1-SH
03/13/2026
Permit issued — Sidewalk Shed
M01026693-I1-SH
05/09/2025
Filed — Alteration
M01025315-P1
05/01/2025
Permit issued — Sidewalk Shed
M01026693-I1-SH
05/01/2025
Permit issued — Sidewalk Shed
M01025315-I1-SH
04/29/2025
Permit issued — Sidewalk Shed
M01025315-I1-SH
04/29/2025
Permit issued — Sidewalk Shed
M01026693-I1-SH
02/13/2025
Permit issued — Sidewalk Shed
M01025315-I1-SH
02/13/2025
Permit issued — Sidewalk Shed
M01026693-I1-SH
07/03/2024
Filed — No Work
M01075395-I1
05/29/2024
Violation issued (ECB, open)
Elevators
04/02/2024
Filed — Alteration
PROPOSED INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS. LIVE LOAD 300 LBS PER SQUARE FEET. SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY, OR EGRESS UNDER THIS APPLICATION.
M01026693-I1
04/02/2024
Filed — Alteration
M01025315-I1
04/02/2024
Permit issued — Sidewalk Shed
M01025315-I1-SH
04/02/2024
Permit issued — Sidewalk Shed
M01026693-I1-SH
03/18/2024
Filed — No Work
M01018197-I1
02/22/2024
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
12/05/2023
Filed — No Work
M00966816-I1
10/11/2023
Permit issued — Sidewalk Shed
M00309667-I1-SH
09/22/2023
Objection raised — Structural
09/22/2023
Objection resolved — Addressed
09/22/2023
Objection raised — Structural
09/22/2023
Objection resolved — Addressed
09/21/2023
Filed — No Work
M00936419-I1
06/15/2023
Filed — No Work
M00886471-I1
03/21/2023
Filed — No Work
M00845299-I1
12/07/2022
Filed — No Work
M08049733-I1
11/04/2022
Filed — Alteration
M00790122-I1
10/27/2022
Violation issued (ECB, closed)
Construction
10/27/2022
Violation issued (ECB, closed)
Construction
10/11/2022
Permit issued — Sidewalk Shed
M00309667-I1-SH
09/13/2022
Filed — No Work
M08000382-I1
06/15/2022
Filed — No Work
M00757231-I1
06/15/2022
Objection raised — Other
06/15/2022
Objection resolved — Addressed
03/21/2022
Filed — No Work
M00701014-I1
12/14/2021
Objection raised — Admin
12/14/2021
Objection resolved — Addressed
12/13/2021
Filed — No Work
M00646834-I1
11/23/2021
Filed — No Work
M00636536-I1
11/22/2021
Objection resolved — Addressed
11/19/2021
Objection raised — Other
11/18/2021
Filed — No Work
M00632883-I1
11/10/2021
Objection raised — Fire_Protection
11/10/2021
Objection resolved — Addressed
11/10/2021
Objection raised — Admin
11/10/2021
Objection resolved — Addressed
11/10/2021
Objection raised — Other
11/10/2021
Objection resolved — Addressed
11/10/2021
Objection raised — Scope
11/10/2021
Objection resolved — Addressed
11/10/2021
Objection raised — Structural
11/10/2021
Objection resolved — Addressed
11/10/2021
Objection raised — Structural
11/10/2021
Objection resolved — Addressed
Latest 60 of 146 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSidewalk ShedPermit IssuedLB and J Construction08/20/2026
DOB NOWSidewalk ShedPermit IssuedLB and J Construction08/20/2026
DOB NOWSidewalk ShedPermit IssuedLB and J Construction05/29/2026
DOB NOWSidewalk ShedPermit IssuedLB and J Construction05/28/2026
DOB NOWSidewalk ShedPermit IssuedLB and J Construction03/13/2026
DOB NOWSidewalk ShedPermit IssuedLB and J Construction03/13/2026
DOB NOWSidewalk ShedPermit IssuedLB and J Construction05/01/2025
DOB NOWSidewalk ShedPermit IssuedLB and J Construction05/01/2025
DOB NOWSidewalk ShedPermit IssuedBulls Eye Contractor04/29/2025
DOB NOWSidewalk ShedPermit IssuedBulls Eye Contractor04/29/2025
DOB NOWSidewalk ShedPermit IssuedLB and J Construction02/13/2025
DOB NOWSidewalk ShedPermit IssuedLB and J Construction02/13/2025
DOB NOWSidewalk ShedPermit IssuedLB and J Construction04/02/2024
DOB NOWSidewalk ShedPermit IssuedLB and J Construction04/02/2024
DOB NOWSidewalk ShedPermit IssuedHard Rock Construction10/11/2023
DOB NOWSidewalk ShedPermit IssuedHard Rock Construction10/11/2022
DOB NOWSidewalk ShedPermit IssuedHard Rock Construction10/12/2021
DOB NOWSidewalk ShedPermit IssuedHard Rock Construction05/06/2021
DOB NOWSidewalk ShedPermit IssuedHard Rock Construction10/13/2020
DOB NOWSidewalk ShedPermit IssuedHard Rock Construction03/09/2020
BISOTISSUEDZHL Group03/23/2021
BISOTISSUEDZHL Group01/14/2021
BISOTISSUEDZHL Group03/30/2020
BISOTISSUEDZHL Group11/13/2019
BISEQISSUEDYork Scaffold Equipment08/14/2017
BISOTISSUEDZHL Group07/21/2017
BISEQISSUEDJ & G GNRL Contracting10/28/2016
BISEQISSUEDYork Scaffold Equipment08/23/2016
BISOTISSUEDZHL Group03/17/2016
BISEQISSUEDYork Scaffold Equipment09/09/2015
BISOTISSUEDLefkas Contracting06/08/2005
BISOTISSUEDLefkas Contracting05/27/2005
BISEQISSUEDColgate Scaffolding & Equipment03/22/2005
BISSPISSUEDArrow Plumbing & Heating11/04/2004
BISEQISSUEDColgate Scaffolding & Equipment09/30/2004
BISPLISSUEDDynamic Contracting05/11/2004
BISOTISSUEDDynamic Contracting05/11/2004
BISMHISSUEDDynamic Contracting05/11/2004
BISPLISSUEDRocon03/18/2004
BISMHISSUEDS A HVAC06/13/2003
+ 13 more permits on file
1 project · most recent 03/25/2021
Others
FiledStatusContractorScope
03/25/2021——Others
1 project · most recent 03/25/2021
Water/Sanitary
FiledStatusContractorScope
03/25/2021——Water/Sanitary
7 projects · most recent 06/09/2025
General Wiring Lighting
FiledStatusContractorScope
06/09/2025Permit IssuedThreetech ElectricLighting
04/02/2024Permit IssuedRichard Neu—
04/02/2024Permit IssuedRichard Neu—
07/25/2023CompleteRobert Chimenti3 meters, 1 new_meters
09/17/2021Permit IssuedP & M Elect'l ContractingGeneral Wiring
08/26/2021CompleteApproved Electric Cont'gGeneral Wiring
02/28/2020Permit IssuedRichard Neu—
2 projects · most recent 04/02/2024
Sidewalk Shed
FiledStatusContractorScope
04/02/2024Permit IssuedLB and J ConstructionSidewalk Shed
10/27/2020——Sidewalk Shed
▾Special Inspection Requirements (DOB NOW) — 10
DateRequirementInspectorRole
03/05/2021Mechanical Systems—special
03/05/2021Final—progress
01/18/2021Fire-Resistance Rated Construction—progress
01/18/2021Energy Code Compliance Inspections—progress
01/18/2021Air barrier - visual inspection—energy_progress
01/18/2021Lighting controls—energy_progress
01/18/2021Air barrier — testing —energy_progress
01/18/2021Interior lighting power—energy_progress
01/18/2021Fire-Resistant Penetrations and Joints—special
01/15/2021Final—progress
▾Tenants in the building
TenantSpaceFloorsRenovation projects
Nypdjec Cadet Assessment CenterGovernment / CivicSub-basement, Floors 1, 2
Project M00790122 Alteration · Approved · 11/04/2022
New York Police DepartmentGovernment / CivicFloors 1–4
Project M00455363 Alteration · Approved · 03/05/2021
Names are taken automatically from the text of each project’s filed documents (title blocks and cover sheets) and screened to exclude owners, landlords and designers. They may be incomplete or wrong; check the filing.
▾Documents — 165 on file (BIS + DOB NOW)
▸Plans & Drawings23
▸DOB NOWPlans/Sketch - Temporary Place of Assembly14
09/03/2026M00636536-I1Request digital key ↗
09/02/2026M00701014-I1Request digital key ↗
09/01/2026M08000382-I1Request digital key ↗
Showing 3 of 14 on file for this type
▸DOB NOWPlans/Sketch6
09/04/2026M00455363-S2Request digital key ↗
09/01/2026M00790122-I1Request digital key ↗
08/27/2026M01026693-I1Request digital key ↗
Showing 3 of 6 on file for this type
▸DOB NOWPlans/Sketch - Sidewalk Shed2
09/05/2026M00309667-I1Request digital key ↗
09/04/2026M00420179-I1Request digital key ↗
▸DOB NOWPlans/Sketch - General Construction1
09/04/2026M00455363-I1Request digital key ↗
▸Applications & Permits25
▸BISWORK PERMIT APPLICATION12
03/24/2021121283805Open ↗
03/19/2021121283805Open ↗
01/15/2021121283805Open ↗
Showing 3 of 12 on file for this type
▸BISPLAN / WORK APPROVAL APPLICATION11
02/19/2020121283805Open ↗
02/14/2020121283805Open ↗
02/13/2020121283805Open ↗
Showing 3 of 11 on file for this type
▸BISPLAN - WORK & PERMITS - SUPPPORTING DOCUMENTATION2
09/02/2025120036424Open ↗
09/02/2025120036415Open ↗
▸Seals & Professional Certifications39
▸DOB NOWDPL-1: Design Professional Seal & Signature23
09/05/2026M00309667-I1Open ↗
09/04/2026M00420179-I1Open ↗
09/04/2026M00455363-I1Open ↗
Showing 3 of 23 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION9
02/19/2020121283805Open ↗
02/14/2020121283805Open ↗
09/24/2019121283805Open ↗
Showing 3 of 9 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT3
09/24/2019121283805Open ↗
10/20/2016140564949Open ↗
09/16/2015122481518Open ↗
▸BISPROFESSIONAL CERTIFIED CHECKLIST2
09/24/2019121283805Open ↗
09/16/2015122481518Open ↗
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION1
10/20/2016140564949Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
10/20/2016140564949Open ↗
▸Trade Schedules & Equipment2
▸BISFA - FDNY APPROVAL : FD-FAA2
02/14/2013120036424Open ↗
02/14/2013120036415Open ↗
▸Safety & Tenant Protection1
▸BISTENANT PROTECTION PLAN AND NOTES1
10/20/2016140564949Open ↗
▸Environmental & Asbestos8
▸BISASBESTOS INSPECTION REPORT4
05/14/2009120036424Open ↗
05/14/2009120036424Open ↗
05/13/2009120036415Open ↗
Showing 3 of 4 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)2
10/20/2016140564949Open ↗
01/28/2016122659532Open ↗
▸BISDEP ASBESTOS PROJECT COMPLETION FORM1
09/24/2019121283805Open ↗
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
09/01/2026M00790122-I1Open ↗
▸Energy Compliance5
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS3
02/19/2020121283805Open ↗
09/24/2019121283805Open ↗
01/28/2016122659532Open ↗
▸BISAS-BUILT ENERGY ANALYSIS (EN2)1
12/03/2024121283805Open ↗
▸BISAS-BUILT ENERGY ANALYSIS1
06/04/2019122659532Open ↗
▸Inspections & Test Reports1
▸BISTECHNICAL REPORT: RESPONSIBILITY1
10/20/2016140564949Open ↗
▸Approvals, Objections & Sign-offs35
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter23
09/05/2026M00309667-I1Open ↗
09/04/2026M00420179-I1Open ↗
09/04/2026M00455363-I1Open ↗
Showing 3 of 23 on file for this type
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST4
09/02/2025120036424Open ↗
09/02/2025120036415Open ↗
06/04/2019122659532Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWDesign Commission Sign Off City Owned (Exterior Work)4
09/04/2026M00420179-I1Open ↗
09/04/2026M00455363-I1Open ↗
08/15/2026M00455363-S1Open ↗
Showing 3 of 4 on file for this type
▸BISADMINISTRATIVE OBJECTIONS2
05/14/2009120036424Open ↗
05/13/2009120036415Open ↗
▸BISLETTERS - SUPPORTING DOCUMENTATION1
06/04/2019122659532Open ↗
▸DOB NOWDesign Commission Approval City Owned (Exterior Work)1
08/13/2026M00309667-I1Open ↗
▸Cost, Insurance & Ownership8
▸BISCOST AFFIDAVIT5
09/24/2019121283805Open ↗
06/04/2019122659532Open ↗
01/28/2016122659532Open ↗
Showing 3 of 5 on file for this type
▸BISCOST AFFIDAVIT (FINAL): PW32
09/02/2025120036424Open ↗
09/02/2025120036415Open ↗
▸BISCIVIL PENALTY AFFADAVIT/REQUEST1
10/28/2016140564949Open ↗
▸Filing & Intake Forms14
▸BISBOROUGH INTAKE FORM8
03/24/2021121283805Open ↗
03/19/2021121283805Open ↗
01/15/2021121283805Open ↗
Showing 3 of 8 on file for this type
▸BISEFILING COVER SHEET3
09/24/2019121283805Open ↗
01/28/2016122659532Open ↗
09/16/2015122481518Open ↗
▸BISADDITIONAL INFORMATION2
02/19/2020121283805Open ↗
10/03/2019121283805Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET1
10/20/2016140564949Open ↗
▸Other Documents4
▸BISSupporting Document: Fee Deferment1
01/28/2016122659532Open ↗
▸BISSupporting Document: Fee Exempt1
09/17/2015122481518Open ↗
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION1
09/20/2019121283805Open ↗
▸BISFEE EXEMPTION DOCUMENTATION1
10/20/2016140564949Open ↗