| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/17/2024 | Complete | RELIABLE ELEC'L CONTR'S | General Wiring |
| 03/02/2023 | Complete | ELPO ELECTRICAL CONTG INC | — |
| Owner | Filings | Most Recent |
|---|---|---|
| PHOENIX SUTTON STR INC | 23 | 03/22/2026 |
| LAA GROUP LLC | 1 | 03/22/2026 |
| 235 WEST 11 ST LLC | 1 | 03/22/2026 |
| 235 WEST 11TH STREET | 12 | 03/21/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 12/03/2025 | $19.2M | — | T 235 W 11TH ST LLC → UNDICESIMA LLC | $3,402/sf building |
| 07/22/2019 | $7.3M | — | — → — | $1,290/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| RODNEY D. GIBBLE CONSULTING ENGINEE | 4 | 12/18/2024 |
| LEVIN ENGINEERING PLLC | 6 | 07/08/2024 |
| ENTHINK ENGINEERS LLC | 7 | 06/08/2023 |
| KIT MIDDLETON ARCHITECT P.C. | 1 | 03/23/2022 |
| Representative | Filings | Most Recent |
|---|---|---|
| KIT MIDDLETON ARCHITECT P C | 14 | 03/21/2026 |
| LEVIN ENGINEERING PLLC | 4 | 03/21/2026 |
| STARLITE PLUMBING HEATING | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| PHOENIX SUTTON STR INC | General Contractor | 8 | 03/21/2026 |
| B.O.S.S. ASSOCIATES, INC | General Contractor | 7 | 07/08/2026 |
| M&D FIRE SPRINKLER INC | Fire Protection | 2 | 07/08/2026 |
| RITE WAY HEATING CORP | Plumbing | 2 | 07/08/2026 |
| RELIABLE ELEC'L CONTR'S | Electrical | 1 | 03/22/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| CENTURY TESTING & CONSULT | 4081 | 14 | 12/18/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | LS PLUMBING CORP | 05/14/2024 |
| DOB NOW | Sprinklers | Signed-off | M&D FIRE SPRINKLER INC | 05/10/2024 |
| DOB NOW | Sidewalk Shed | Signed-off | PHOENIX SUTTON STR INC | 03/08/2024 |
| DOB NOW | Mechanical Systems | Signed-off | B.O.S.S. ASSOCIATES, INC | 08/14/2023 |
| DOB NOW | Supported Scaffold | Signed-off | PHOENIX SUTTON STR INC | 06/23/2023 |
| DOB NOW | Sprinklers | Signed-off | M&D FIRE SPRINKLER INC | 05/22/2023 |
| DOB NOW | Sprinklers | Signed-off | LS PLUMBING CORP | 05/22/2023 |
| DOB NOW | Structural | Permit Issued | B.O.S.S. ASSOCIATES, INC | 05/02/2023 |
| DOB NOW | Construction Fence | Signed-off | B.O.S.S. ASSOCIATES, INC | 04/18/2023 |
| DOB NOW | Sidewalk Shed | Signed-off | PHOENIX SUTTON STR INC | 03/08/2023 |
| DOB NOW | Supported Scaffold | Signed-off | PHOENIX SUTTON STR INC | 06/27/2022 |
| DOB NOW | Structural | Permit Issued | B.O.S.S. ASSOCIATES, INC | 04/06/2022 |
| DOB NOW | Construction Fence | Signed-off | B.O.S.S. ASSOCIATES, INC | 03/25/2022 |
| BIS | — | ISSUED | B.O.S.S. ASSOCIATES, INC | 03/20/2024 |
| BIS | — | ISSUED | B.O.S.S. ASSOCIATES, INC | 02/14/2024 |
| BIS | — | ISSUED | B.O.S.S. ASSOCIATES, INC | 02/16/2023 |
| BIS | — | ISSUED | B.O.S.S. ASSOCIATES, INC | 03/15/2022 |
| Date | Type | Result | Report |
|---|---|---|---|
| 06/28/2024 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 06/26/2024 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 12/14/2023 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 07/20/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 07/14/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 12/04/2024 | Concrete - Cast-In-Place | ALDO BRAVO | special |
| 12/04/2024 | Final | FRANZ SEBORGA | progress |
| 12/04/2024 | Structural Steel - Welding | ALDO BRAVO | special |
| 12/04/2024 | Structural Steel - High Strength Bolting | ALDO BRAVO | special |
| 12/04/2024 | Structural Steel - Details | ALDO BRAVO | special |
| 12/04/2024 | Structural Stability – Alterations of existing buildings | ALDO BRAVO | special |
| 12/04/2024 | Structural Cold-Formed Steel | ALDO BRAVO | special |
| 12/04/2024 | Masonry | ALDO BRAVO | special |
| 07/08/2024 | Sprinkler Systems | ALDO BRAVO | special |
| 07/08/2024 | Fire-Resistant Penetrations and Joints | ALDO BRAVO | special |
| 07/08/2024 | Post-installed Anchors | ALDO BRAVO | special |
| 07/03/2024 | Sprinkler Systems | ALDO BRAVO | special |
| 07/03/2024 | Fire-Resistant Penetrations and Joints | ALDO BRAVO | special |
| 07/03/2024 | Post-installed Anchors | ALDO BRAVO | special |
| 03/11/2024 | Heating Systems | ALDO BRAVO | special |
| 03/11/2024 | Final | ALDO BRAVO | progress |
| 03/11/2024 | Post-installed Anchors | ALDO BRAVO | special |
| 03/11/2024 | Mechanical Systems | ALDO BRAVO | special |
| 03/08/2024 | Heating Systems | ALDO BRAVO | special |
| 03/08/2024 | Final | ALDO BRAVO | progress |
| 03/08/2024 | Post-installed Anchors | ALDO BRAVO | special |
| 03/08/2024 | Mechanical Systems | ALDO BRAVO | special |
| 02/26/2024 | Sprinkler Systems | ALDO BRAVO | special |
| 02/26/2024 | Fire-Resistant Penetrations and Joints | ALDO BRAVO | special |
| 02/26/2024 | Post-installed Anchors | ALDO BRAVO | special |