← Back
Five to six families
235A LEXINGTON AVENUE
BROOKLYN · Bedford-Stuyvesant (West) · BIN 3050389
💬 Discuss this project
1931Year Built
3Stories
C2Building Class
R6BZoning
2,750 sfGross Floor Area
6Units
Rent Stabilized26 Open Violations ▸FDNY Report ↗
Five to six families · Owner of record: LEXINGTON RESIDENTS LLC · 1,667 sf lot · 1.65 FAR built · Flood zone X
Locations of Work
ArchitectureMechanicalPlumbing
Roof5p · 2 filings · 17 docs
Floor 27p · 1 filing · 15 docs
Floor 17p · 1 filing · 15 docs
Cellar8p · 1 filing · 15 docs
Basement3p · 1 filing · 2 docs
Sub-Basement7p · 1 filing · 15 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
MJH CONSTRUCTION1304/09/2026
LEXINGTON RESIDENTS LLC303/22/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
07/29/2024$875K—Private party → LEXINGTON RESIDENTS LLC$318/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
DIEGO AGUILERA ARCHITECTS P.C.401/27/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
EXPRESS FILING INC803/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
MJH CONSTRUCTION CORPGeneral Contractor304/09/2026
NESS MECHANICAL P & H INCPlumbing106/28/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
HRF SERVICES CORP5616301/27/2025
Building Lifecycle
All (105)Filed (4)Permit Issued (3)Violation (42)Objection (32)Special Inspection (24)
03/19/2025
Permit issued — Mechanical Systems
B01149022-S2-MS
03/19/2025
Permit issued — Plumbing
B01149022-S1-PL
03/17/2025
Permit issued — General Construction
B01149022-I1-GC
02/05/2025
Objection resolved — Addressed
01/31/2025
Objection resolved — Addressed
01/31/2025
Objection resolved — Addressed
01/31/2025
Objection resolved — Addressed
01/31/2025
Objection resolved — Addressed
01/30/2025
Objection raised — Plumbing
01/30/2025
Objection raised — Fire_Protection
01/30/2025
Objection raised — Plumbing
01/30/2025
Objection raised — Scope
01/30/2025
Objection raised — Mechanical
01/27/2025
Filed — Alteration
MECHANICAL SPECIFICATIONS FILED IN CONJUNCTION WITH GC APPLICATION B01149022-I1
B01149022-S2
01/27/2025
Filed — Alteration
MECHANICAL SPECIFICATIONS FILED IN CONJUNCTION WITH GC APPLICATION B01149022-I1
B01149022-S1
01/24/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
FAHAD FATEH
01/24/2025
Special inspection requirement — Mechanical Systems
FAHAD FATEH
01/24/2025
Special inspection requirement — Energy Code Compliance Inspections
FAHAD FATEH
01/24/2025
Special inspection requirement — Final
FAHAD FATEH
01/24/2025
Special inspection requirement — Maintenance information
FAHAD FATEH
01/24/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
FAHAD FATEH
01/24/2025
Special inspection requirement — HVAC-R and service water heating system controls
FAHAD FATEH
01/24/2025
Special inspection requirement — HVAC-R and service water heating equipment
FAHAD FATEH
01/24/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
FAHAD FATEH
01/24/2025
Special inspection requirement — Energy Code Compliance Inspections
FAHAD FATEH
01/24/2025
Special inspection requirement — HVAC-R and service water heating system controls
FAHAD FATEH
01/24/2025
Special inspection requirement — Maintenance information
FAHAD FATEH
01/24/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
FAHAD FATEH
01/24/2025
Special inspection requirement — HVAC-R and service water heating equipment
FAHAD FATEH
01/14/2025
Objection resolved — Addressed
01/14/2025
Objection resolved — Addressed
01/14/2025
Objection resolved — Addressed
01/14/2025
Objection resolved — Addressed
01/14/2025
Objection resolved — Addressed
01/14/2025
Objection resolved — Addressed
01/14/2025
Objection resolved — Addressed
01/07/2025
Objection resolved — Addressed
01/07/2025
Objection resolved — Addressed
01/07/2025
Objection resolved — Addressed
01/02/2025
Objection raised — Structural
01/02/2025
Objection raised — Cost
01/02/2025
Objection raised — Mechanical
01/02/2025
Objection raised — Structural
01/02/2025
Objection raised — Structural
01/02/2025
Objection raised — Structural
01/02/2025
Objection raised — Structural
01/02/2025
Objection raised — Structural
01/02/2025
Objection raised — Structural
12/24/2024
Objection resolved — Addressed
12/09/2024
Objection raised — Scope
12/09/2024
Objection raised — Admin
12/05/2024
Filed — Alteration
MECHANICAL SPECIFICATIONS FILED IN CONJUNCTION WITH GC APPLICATION B01149022-I1
B01149022-I1
11/25/2024
Filed — Alteration
B01146534-I1
11/22/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
11/22/2024
Special inspection requirement — Structural Stability – Alterations of existing buildings
11/22/2024
Special inspection requirement — Energy Code Compliance Inspections
11/22/2024
Special inspection requirement — Fire-Resistance Rated Construction
11/22/2024
Special inspection requirement — Final
11/22/2024
Special inspection requirement — Exterior lighting power
11/22/2024
Special inspection requirement — Lighting controls
Latest 60 of 105 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWMechanical SystemsPermit IssuedMJH CONSTRUCTION CORP03/19/2025
DOB NOWPlumbingPermit IssuedNESS MECHANICAL P & H INC03/19/2025
DOB NOWGeneral ConstructionPermit IssuedMJH CONSTRUCTION CORP03/17/2025
1 project · most recent 01/27/2025
Heating and Air Conditioning Systems
FiledStatusContractorScopeMake / Model / Capacity
01/27/2025Permit IssuedMJH CONSTRUCTION CORPHeating and Air Conditioning Systems
Heat / Cool
Daikin RXS12LVJU 14,400 BTU · Heat Pump Outdoor ×4
1 project · most recent 01/27/2025
Storm Water/Sanitary
FiledStatusContractorScope
01/27/2025Permit IssuedQUALITY PIPING, INCStorm, Water/Sanitary
2 projects · most recent 03/12/2025
General Wiring
FiledStatusContractorScope
03/12/2025Permit IssuedS&R ELECTRICAL & MECHANICGeneral Wiring
10/02/2024Permit IssuedS&R ELECTRICAL & MECHANICGeneral Wiring
▾Special Inspection Requirements (DOB NOW) — 24
DateRequirementInspectorRole
01/24/2025Fire-Resistant Penetrations and JointsFAHAD FATEHspecial
01/24/2025Mechanical SystemsFAHAD FATEHspecial
01/24/2025Energy Code Compliance InspectionsFAHAD FATEHprogress
01/24/2025FinalFAHAD FATEHprogress
01/24/2025Maintenance informationFAHAD FATEHenergy_progress
01/24/2025HVAC-R and service water piping design and insulationFAHAD FATEHenergy_progress
01/24/2025HVAC-R and service water heating system controlsFAHAD FATEHenergy_progress
01/24/2025HVAC-R and service water heating equipmentFAHAD FATEHenergy_progress
01/24/2025Fire-Resistant Penetrations and JointsFAHAD FATEHspecial
01/24/2025Energy Code Compliance InspectionsFAHAD FATEHprogress
01/24/2025HVAC-R and service water heating system controlsFAHAD FATEHenergy_progress
01/24/2025Maintenance informationFAHAD FATEHenergy_progress
01/24/2025HVAC-R and service water piping design and insulationFAHAD FATEHenergy_progress
01/24/2025HVAC-R and service water heating equipmentFAHAD FATEHenergy_progress
11/22/2024Fire-Resistant Penetrations and Joints—special
11/22/2024Structural Stability – Alterations of existing buildings—special
11/22/2024Energy Code Compliance Inspections—progress
11/22/2024Fire-Resistance Rated Construction—progress
11/22/2024Final—progress
11/22/2024Exterior lighting power—energy_progress
11/22/2024Lighting controls—energy_progress
11/22/2024Lighting in dwelling units—energy_progress
11/22/2024Interior lighting power—energy_progress
11/22/2024Maintenance information—energy_progress
▾Documents — 17 on file (BIS + DOB NOW)
▸Plans & Drawings4
▸DOB NOWPlans/Sketch4
08/23/2026B01146534-I1Request digital key ↗
08/23/2026B01149022-S2Request digital key ↗
08/23/2026B01149022-S1Request digital key ↗
Showing 3 of 4 on file for this type
▸Seals & Professional Certifications10
▸DOB NOWDPL-1: Design Professional Seal & Signature4
08/23/2026B01146534-I1Open ↗
08/13/2026B01149022-S2Open ↗
08/13/2026B01149022-S1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWProgress Inspector Seal & Signature4
09/01/2026B01149022-S2Open ↗
09/01/2026B01149022-S2Open ↗
08/28/2026B01149022-S1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature2
09/01/2026B01149022-S2Open ↗
08/28/2026B01149022-S1Open ↗
▸Environmental & Asbestos3
▸DOB NOWDEP ACP-5: Asbestos Assessment Report3
08/13/2026B01149022-S2Open ↗
08/13/2026B01149022-S1Open ↗
08/13/2026B01149022-I1Open ↗