← Back
General warehouse
411 3 AVENUE
BROOKLYN · BIN 3330541
💬 Discuss this project
1931Year Built
1Stories
E1Building Class
M1-4Zoning
22,183 sfGross Floor Area
6Units
1 Open Violation 0 unresolved · 1 paperwork only ▸FDNY Report ↗
General warehouse · 23,075 sf lot · 0.96 FAR built · Flood zone X
Locations of Work
ArchitecturePlumbingFire Protection
Floor 21p · 1 filing · 3 docs
Floor 124p · 3 filings · 20 docs
Mezzanine25p · 3 filings · 20 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
SERDAR CEYLAN ARCHITECT, PC703/25/2025
CQ&J CORPORATION105/08/2024
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
JAM CONSULTANTS, INC.103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
P & D MECHANICAL CORPFire Protection107/08/2026
MKNK WASTE REMOVAL INCGeneral Contractor107/08/2026
CROWN PLUMBING INCPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
RYAN DESIGN ARCHITECTURE7159303/25/2025
CEYLAN DESIGN AND CONSULT8422209/09/2024
WELLDONE INSPECTION INC.8628105/08/2024
Building Lifecycle
All (121)Filed (8)Permit Issued (3)Violation (2)Inspection (4)Objection (74)Special Inspection (30)
08/22/2025
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
08/15/2025
Inspection — Fail-Final CND-Occupancy Inspection
Fail
View inspection ↗
06/12/2025
Special inspection requirement — Public Assembly Emergency Lighting
SERDAR CEYLAN
06/02/2025
Objection resolved — Addressed
06/02/2025
Objection resolved — Addressed
05/21/2025
Objection resolved — Addressed
04/29/2025
Objection resolved — Addressed
04/29/2025
Objection resolved — Addressed
04/29/2025
Objection resolved — Addressed
04/29/2025
Objection resolved — Addressed
04/16/2025
Objection raised — Scope
04/16/2025
Objection raised — Structural
04/16/2025
Objection raised — Structural
04/16/2025
Objection raised — Admin
04/16/2025
Objection raised — Mechanical
04/16/2025
Objection raised — Fire_Protection
04/16/2025
Objection raised — Structural
04/07/2025
Objection resolved — Addressed
04/07/2025
Objection resolved — Addressed
04/04/2025
Objection raised — Inspections
04/04/2025
Objection raised — Structural
04/01/2025
Special inspection requirement — Fenestration and door U-factor and product ratings
SERDAR CEYLAN
04/01/2025
Special inspection requirement — Interior lighting power
SERDAR CEYLAN
04/01/2025
Special inspection requirement — Mechanical Systems
Daniel Ryan
04/01/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Daniel Ryan
04/01/2025
Special inspection requirement — Energy Code Compliance Inspections
SERDAR CEYLAN
04/01/2025
Special inspection requirement — Final
SERDAR CEYLAN
04/01/2025
Special inspection requirement — Fire-Resistance Rated Construction
SERDAR CEYLAN
04/01/2025
Special inspection requirement — HVAC-R and service water heating equipment
SERDAR CEYLAN
04/01/2025
Special inspection requirement — Lighting controls
SERDAR CEYLAN
04/01/2025
Special inspection requirement — HVAC-R and service water heating system controls
SERDAR CEYLAN
04/01/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
SERDAR CEYLAN
04/01/2025
Special inspection requirement — Fenestration areas
SERDAR CEYLAN
03/25/2025
Filed — Alteration CO
CONVERT EXISTING STEEL SHOP INTO EATING AND DRINKING STABLISHMENT AS PER PLANS SUBMITTED. ALSO FILED FOR NEW KITCHEN EXHAUST HOOD AND DUCT SYSTEM FOR COMMERCIAL KITCHEN. APPLICATION FILED TO REQUEST NEW CERTIFICATE OF OCCUPANCY.
B00894940-P3
03/25/2025
Filed — No Work
B00960028-P1
02/26/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Daniel Ryan
02/26/2025
Special inspection requirement — Fenestration and door U-factor and product ratings
SERDAR CEYLAN
02/26/2025
Special inspection requirement — HVAC-R and service water heating equipment
SERDAR CEYLAN
02/26/2025
Special inspection requirement — HVAC-R and service water heating system controls
SERDAR CEYLAN
02/26/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
SERDAR CEYLAN
02/26/2025
Special inspection requirement — Lighting controls
SERDAR CEYLAN
02/26/2025
Special inspection requirement — Public Assembly Emergency Lighting
SERDAR CEYLAN
02/26/2025
Special inspection requirement — Mechanical Systems
Daniel Ryan
02/26/2025
Special inspection requirement — Energy Code Compliance Inspections
SERDAR CEYLAN
02/26/2025
Special inspection requirement — Final
SERDAR CEYLAN
02/26/2025
Special inspection requirement — Fire-Resistance Rated Construction
SERDAR CEYLAN
02/26/2025
Special inspection requirement — Fenestration areas
SERDAR CEYLAN
02/26/2025
Special inspection requirement — Interior lighting power
SERDAR CEYLAN
02/01/2025
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
12/20/2024
Objection resolved — Addressed
12/11/2024
Objection resolved — Addressed
12/11/2024
Objection resolved — Addressed
12/02/2024
Objection resolved — Addressed
11/12/2024
Objection resolved — Addressed
11/01/2024
Objection raised — Mechanical
11/01/2024
Objection resolved — Addressed
11/01/2024
Objection resolved — Addressed
10/22/2024
Objection resolved — Addressed
10/10/2024
Objection raised — Fire_Protection
10/10/2024
Objection raised — Fire_Protection
Latest 60 of 121 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSprinklersPermit IssuedP & D MECHANICAL CORP07/05/2024
DOB NOWPlumbingPermit IssuedCROWN PLUMBING INC04/29/2024
DOB NOWGeneral ConstructionPermit IssuedMKNK WASTE REMOVAL INC03/08/2024
BISOTISSUEDMETROPOLITAN HEAT & POWER CO08/14/2003
1 project · most recent 03/25/2025
Heating and Air Conditioning Systems Ventilation Systems
FiledStatusContractorScopeMake / Model / Capacity
03/25/2025Permit IssuedMKNK WASTE REMOVAL INCHeating and Air Conditioning Systems, Ventilation Systems
Heat / Cool
Mitsubishi Electric MXZ-4C36KA7 36,000 BTU · Condensing Unit ×15
MSZ-GL18NA 18,000 BTU · Split System ×5
PCA A36KA7 36,000 BTU · Split System ×6
PCA A36NKA7 36,000 BTU · Vrf Indoor ×3
PVA A36AA7 36,000 BTU · Ahu ×2
MSZ-GL12NA 12,000 BTU · Fan Coil Indoor ×1
MUZ MF12NA U1 12,000 BTU · Rooftop Unit ×1
Heatcraft CEL0060AS6AMAB0000 6,500 BTU · Refrigeration Unit ×12
Mrcool DIY-12-HP-C-1158 6,500 BTU · Condensing Unit ×12
Rheem RGEDZT150ACG15BAA 12 tons · Ahu ×10
Ventilation
Floaire BDU20 5,500 CFM · Kitchen Exhaust ×5
Pennbarry MU4012 1,800 CFM · Makeup Air ×5
Captiveaire NCA18FA 3,375 CFM · Kitchen Exhaust ×1
PVA-A36AA7 2,700 CFM · Makeup Air ×1
1 project · most recent 09/09/2024
Water/Sanitary
FiledStatusContractorScope
09/09/2024Permit IssuedCROWN PLUMBING INCWater/Sanitary
2 projects · most recent 04/16/2024
General Wiring
FiledStatusContractorScope
04/16/2024CompleteMAC ELECT'L CONTR. INC.General Wiring
05/15/2018CompleteRM ELECTRIC CO., INC.2 meters, 2 new_meters
▾Field Inspections (DOB CAP) — 4
DateTypeResultReport
08/22/2025Pass-Final CND-Occupancy InspectionPassView ↗
08/15/2025Fail-Final CND-Occupancy InspectionFailView ↗
02/01/2025Pass-Final CND-Occupancy InspectionPassView ↗
05/06/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
▾Special Inspection Requirements (DOB NOW) — 32
DateRequirementInspectorRole
06/12/2025Public Assembly Emergency LightingSERDAR CEYLANprogress
04/01/2025Fenestration and door U-factor and product ratingsSERDAR CEYLANenergy_progress
04/01/2025Interior lighting powerSERDAR CEYLANenergy_progress
04/01/2025Mechanical SystemsDaniel Ryanspecial
04/01/2025Fire-Resistant Penetrations and JointsDaniel Ryanspecial
04/01/2025Energy Code Compliance InspectionsSERDAR CEYLANprogress
04/01/2025FinalSERDAR CEYLANprogress
04/01/2025Fire-Resistance Rated ConstructionSERDAR CEYLANprogress
04/01/2025HVAC-R and service water heating equipmentSERDAR CEYLANenergy_progress
04/01/2025Lighting controlsSERDAR CEYLANenergy_progress
04/01/2025HVAC-R and service water heating system controlsSERDAR CEYLANenergy_progress
04/01/2025HVAC-R and service water piping design and insulationSERDAR CEYLANenergy_progress
04/01/2025Fenestration areasSERDAR CEYLANenergy_progress
02/26/2025Fire-Resistant Penetrations and JointsDaniel Ryanspecial
02/26/2025Fenestration and door U-factor and product ratingsSERDAR CEYLANenergy_progress
02/26/2025HVAC-R and service water heating equipmentSERDAR CEYLANenergy_progress
02/26/2025HVAC-R and service water heating system controlsSERDAR CEYLANenergy_progress
02/26/2025HVAC-R and service water piping design and insulationSERDAR CEYLANenergy_progress
02/26/2025Lighting controlsSERDAR CEYLANenergy_progress
02/26/2025Public Assembly Emergency LightingSERDAR CEYLANprogress
02/26/2025Mechanical SystemsDaniel Ryanspecial
02/26/2025Energy Code Compliance InspectionsSERDAR CEYLANprogress
02/26/2025FinalSERDAR CEYLANprogress
02/26/2025Fire-Resistance Rated ConstructionSERDAR CEYLANprogress
02/26/2025Fenestration areasSERDAR CEYLANenergy_progress
Latest 25 of 32.
▾Documents — 49 on file (BIS + DOB NOW)
▸Plans & Drawings8
▸DOB NOWPlans/Sketch6
08/26/2026B00894940-P3Request digital key ↗
08/25/2026B00955235-I1Request digital key ↗
08/24/2026B00922298-P1Request digital key ↗
Showing 3 of 6 on file for this type
▸DOB NOWPlans/Sketch - Place of Assembly2
08/15/2026B00960028-P1Request digital key ↗
08/15/2026B00960028-I1Request digital key ↗
▸Seals & Professional Certifications24
▸DOB NOWProgress Inspector Seal & Signature10
08/30/2026B00960028-P1Open ↗
08/27/2026B00960028-I1Open ↗
08/26/2026B00894940-I1Open ↗
Showing 3 of 10 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature8
08/26/2026B00894940-I1Open ↗
08/26/2026B00894940-P1Open ↗
08/26/2026B00894940-P3Open ↗
Showing 3 of 8 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature6
08/26/2026B00894940-I1Open ↗
08/26/2026B00894940-I1Open ↗
08/23/2026B00894940-P3Open ↗
Showing 3 of 6 on file for this type
▸Safety & Tenant Protection3
▸DOB NOWStreet Tree Checklist3
08/26/2026B00894940-P3Open ↗
08/15/2026B00894940-P1Open ↗
08/14/2026B00894940-I1Open ↗
▸Environmental & Asbestos11
▸DOB NOWDEP ACP-5: Asbestos Assessment Report6
08/26/2026B00894940-P3Open ↗
08/25/2026B00955235-I1Open ↗
08/15/2026B00894940-P1Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWOER: Notice to Proceed5
08/13/2026B00922298-P1Open ↗
08/13/2026B00894940-P3Open ↗
08/13/2026B00894940-P1Open ↗
Showing 3 of 5 on file for this type
▸Other Documents3
▸DOB NOWProperty Ownership Certification3
08/26/2026B00894940-P3Open ↗
08/15/2026B00894940-P1Open ↗
08/14/2026B00894940-I1Open ↗