← Back
One story - permanent living quarter
238-11 149 AVENUE
💬 Discuss this project
1950Year Built
2Stories
A2Building Class
R3XZoning
2,050 sfGross Floor Area
1Units
One story - permanent living quarter · 4,000 sf lot · 0.51 FAR built · Flood zone X500
Locations of Work
ElectricalGeneral
Roof1p · 1 filing · 7 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
GREEN RIVER ENVIRONMENTAL ENGINEERI103/31/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
NY State Solar LLC203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
NYSS LLCGeneral Contractor303/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
GREEN RIVER ENVIRONMENTAL7841103/31/2025
Building Lifecycle
All (8)Filed (1)Permit Issued (1)Signed Off (1)Special Inspection (5)
07/03/2025
Signed off — Alteration
INSTALLATION OF PHOTOVOLTAIC SOLAR ARRAY ON EXISTING ROOF SYSTEM AS PER PLANS
Q01203511-I1
04/02/2025
Permit issued — Solar
Q01203511-I1-SL
03/31/2025
Filed — Alteration
INSTALLATION OF PHOTOVOLTAIC SOLAR ARRAY ON EXISTING ROOF SYSTEM AS PER PLANS
Q01203511-I1
03/31/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
ROBERT MASONE
03/31/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
ROBERT MASONE
03/31/2025
Special inspection requirement — Energy Code Compliance Inspections
ROBERT MASONE
03/31/2025
Special inspection requirement — Final
ROBERT MASONE
03/31/2025
Special inspection requirement — Air barrier - visual inspection
ROBERT MASONE
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offNYSS LLC04/02/2025
BISPLISSUEDPETRONE PLBG & HTG CORP09/16/1993
BIS—ISSUEDCNETRAL HM. REM. INC.08/10/1993
1 project · most recent 03/31/2025
FiledStatusContractorScope
03/31/2025CompleteNY SOLAR ELECTRICAL LLC—
▾Special Inspection Requirements (DOB NOW) — 5
DateRequirementInspectorRole
03/31/2025Fire-Resistant Penetrations and JointsROBERT MASONEspecial
03/31/2025Structural Stability – Alterations of existing buildingsROBERT MASONEspecial
03/31/2025Energy Code Compliance InspectionsROBERT MASONEprogress
03/31/2025FinalROBERT MASONEprogress
03/31/2025Air barrier - visual inspectionROBERT MASONEenergy_progress
▾Documents — 7 on file (BIS + DOB NOW)
▸Plans & Drawings1
▸DOB NOWPlans/Sketch1
08/20/2026Q01203511-I1Request digital key ↗
▸Seals & Professional Certifications4
▸DOB NOWProgress Inspector Seal & Signature2
08/25/2026Q01203511-I1Open ↗
08/25/2026Q01203511-I1Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature1
08/13/2026Q01203511-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature1
08/25/2026Q01203511-I1Open ↗
▸Environmental & Asbestos1
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/13/2026Q01203511-I1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/13/2026Q01203511-I1Open ↗