| Owner | Filings | Most Recent |
|---|---|---|
| NYC SCHOOL CONSTRUCTION AUTHORITY | 56 | 08/29/2026 |
| NYC DEPARTMENT OF EDUCATION | 1 | 03/22/2026 |
| DOE PS 84 040 | 7 | 03/22/2026 |
| DEPARTMENT OF EDUCATION | 12 | 03/22/2026 |
| DEPT OF EDUCATION P.S.084 | 2 | 03/22/2026 |
| ADAMS EUROPEAN CONTRACTIN | 1 | 03/22/2026 |
| DOE 040 | 1 | 03/22/2026 |
| P.S. 84 DEPT. OF EDUCATIO | 2 | 03/22/2026 |
| P.S. 84 D.O.E. | 3 | 03/22/2026 |
| BD. OF EDUCATION 040 | 2 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| DSENY ENGINEERING SERVICES, PC | 2 | 06/09/2026 |
| 360 ENGINEERING P.C. | 4 | 11/25/2025 |
| AK CONSULTING SERVICES, INC | 3 | 12/28/2022 |
| NYMS CONSULTING, LLC | 4 | 09/08/2022 |
| CPL ARCHITECTURE ENGINEERING AND PL | 6 | 08/25/2022 |
| THE LIRO GROUP | 1 | 01/30/2020 |
| Representative | Filings | Most Recent |
|---|---|---|
| CPL ARCHITECTURE | 7 | 03/21/2026 |
| DSENY ENGINEERING SERVICES | 2 | 03/21/2026 |
| LIRO ARCHITECTS + PLANNER | 1 | 03/21/2026 |
| AK CONSULTING SERVICES | 6 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| KORDUN CONSTRUCTION CORP | General Contractor | 11 | 07/08/2026 |
| FRANCIS RICHARDS | Electrical | 9 | 03/21/2026 |
| ALLIANCE TRI-STATE CONSTR | General Contractor | 8 | 07/08/2026 |
| NEHAL CONTRACTING INC | General Contractor | 6 | 07/08/2026 |
| ADAM'S EUROPEAN CONTRACTING | General Contractor | 5 | 07/08/2026 |
| YARKS NYC INC | General Contractor | 2 | 07/08/2026 |
| CORE ELECTRIC MEP INDS LL | Electrical | 1 | 03/22/2026 |
| MAR-SAL PLBG & HTG, INC | Plumbing | 1 | 05/23/2026 |
| JAMES MAGRIPLES | Electrical | 1 | 03/21/2026 |
| MAGRIPLES JAMES | Electrical | 1 | 03/21/2026 |
| SAMCO ELECTRIC CORP. | Electrical | 1 | 03/22/2026 |
| ENVIROTRAC LTD | General Contractor | 1 | 06/27/2026 |
| R.A.M.S. MECHANICAL INC | General Contractor | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| TWIN PEAKS INC. | 317 | 7 | 11/25/2025 |
| MUNICIPAL TESTING LABORAT | 230 | 1 | 12/28/2022 |
| FUTURE TECH CONSULTANTS O | 589 | 3 | 09/08/2022 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Construction Fence | Permit Issued | ENVIROTRAC LTD | 06/23/2026 |
| DOB NOW | Plumbing | Permit Issued | MAR-SAL PLBG & HTG, INC | 05/21/2026 |
| DOB NOW | General Construction | Permit Issued | NEHAL CONTRACTING INC | 05/18/2026 |
| DOB NOW | Foundation | Permit Issued | NEHAL CONTRACTING INC | 05/18/2026 |
| DOB NOW | Structural | Permit Issued | NEHAL CONTRACTING INC | 05/18/2026 |
| DOB NOW | General Construction | Permit Issued | NEHAL CONTRACTING INC | 05/15/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | R.A.M.S. MECHANICAL INC | 05/15/2026 |
| DOB NOW | Supported Scaffold | Permit Issued | YARKS NYC INC | 04/21/2026 |
| DOB NOW | Support of Excavation | Permit Issued | NEHAL CONTRACTING INC | 03/25/2026 |
| DOB NOW | Sidewalk Shed | Permit Issued | YARKS NYC INC | 03/25/2026 |
| DOB NOW | Construction Fence | Permit Issued | NEHAL CONTRACTING INC | 02/11/2026 |
| DOB NOW | Sidewalk Shed | Signed-off | ALLIANCE TRI-STATE CONSTR | 10/08/2024 |
| DOB NOW | Construction Fence | Signed-off | ALLIANCE TRI-STATE CONSTR | 10/08/2024 |
| DOB NOW | Supported Scaffold | Signed-off | ALLIANCE TRI-STATE CONSTR | 10/08/2024 |
| DOB NOW | Sidewalk Shed | Signed-off | KORDUN CONSTRUCTION CORP | 04/08/2024 |
| DOB NOW | Mechanical Systems | Permit Issued | KORDUN CONSTRUCTION CORP | 04/02/2024 |
| DOB NOW | Mechanical Systems | Signed-off | KORDUN CONSTRUCTION CORP | 11/27/2023 |
| DOB NOW | Sidewalk Shed | Signed-off | KORDUN CONSTRUCTION CORP | 11/27/2023 |
| DOB NOW | Sidewalk Shed | Signed-off | KORDUN CONSTRUCTION CORP | 10/20/2023 |
| DOB NOW | Supported Scaffold | Signed-off | ALLIANCE TRI-STATE CONSTR | 10/13/2023 |
| DOB NOW | Sidewalk Shed | Signed-off | ALLIANCE TRI-STATE CONSTR | 10/11/2023 |
| DOB NOW | Construction Fence | Signed-off | ALLIANCE TRI-STATE CONSTR | 10/06/2023 |
| DOB NOW | Sidewalk Shed | Permit Issued | ADAM'S EUROPEAN CONTRACTING | 08/24/2023 |
| DOB NOW | Construction Fence | Signed-off | KORDUN CONSTRUCTION CORP | 11/23/2022 |
| DOB NOW | Mechanical Systems | Signed-off | KORDUN CONSTRUCTION CORP | 11/23/2022 |
| DOB NOW | Sidewalk Shed | Permit Issued | ADAM'S EUROPEAN CONTRACTING | 08/23/2022 |
| DOB NOW | Mechanical Systems | Signed-off | KORDUN CONSTRUCTION CORP | 08/18/2022 |
| DOB NOW | Sidewalk Shed | Signed-off | KORDUN CONSTRUCTION CORP | 06/17/2022 |
| DOB NOW | Boiler Equipment | Signed-off | CHAMPION COMBUSTION CORP | 06/17/2022 |
| DOB NOW | Construction Fence | Signed-off | KORDUN CONSTRUCTION CORP | 06/07/2022 |
| DOB NOW | Sidewalk Shed | Permit Issued | ADAM'S EUROPEAN CONTRACTING | 06/21/2021 |
| DOB NOW | Sidewalk Shed | Permit Issued | ADAM'S EUROPEAN CONTRACTING | 04/21/2020 |
| BIS | OT | ISSUED | ALLIANCE TRI-STATE CONSTR | 04/30/2025 |
| BIS | OT | ISSUED | KORDUN CONSTRUCTION CORP | 11/21/2024 |
| BIS | OT | ISSUED | KORDUN CONSTRUCTION CORP | 11/21/2024 |
| BIS | BL | ISSUED | KORDUN CONSTRUCTION CORP | 11/21/2024 |
| BIS | PL | ISSUED | KORDUN CONSTRUCTION CORP | 11/21/2024 |
| BIS | PL | ISSUED | VARSITY PLBG AND HTG INC | 10/09/2024 |
| BIS | OT | ISSUED | ALLIANCE TRI-STATE CONSTR | 04/17/2024 |
| BIS | OT | ISSUED | KORDUN CONSTRUCTION CORP | 11/20/2023 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/24/2026 | Permit Issued | LIT MODE ELECL CONTG INC | — |
| 12/18/2025 | Permit Issued | MILAD CONTRACTING CORP. | General Wiring, Lighting |
| 05/17/2024 | Complete | TRIBECA ELECTRICAL CORP | General Wiring |
| 02/01/2024 | Complete | CORE ELECTRIC MEP INDS LL | General Wiring |
| 12/04/2023 | Complete | PACIFIC ELEC'L CONTR'G IN | — |
| 10/06/2023 | Complete | J&H ELECTRICAL CONT INC | — |
| 06/13/2022 | Complete | TRIBECA ELECTRICAL CORP | — |
| 05/04/2022 | Complete | CHARAN ELEC'L ENTERP'S IN | — |
| 04/25/2022 | Permit Issued | WINDSOR ELEC CONT'G INC. | General Wiring |
| 11/23/2021 | Complete | ZIGGY'S ELECL CONTNG CORP | — |
| 05/27/2021 | Permit Issued | A & S ELECTRIC INC. | General Wiring |
| 03/01/2019 | Complete | CHARAN ELEC'L ENTERP'S IN | — |
| 02/19/2019 | Permit Issued | SAMCO ELECTRIC CORP. | — |
| 10/23/2018 | Complete | CHARAN ELEC'L ENTERP'S IN | — |
| 08/15/2018 | Permit Issued | A & S ELECTRIC INC. | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/25/2025 | Permit Issued | NEHAL CONTRACTING INC | 1 scope_items |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/09/2026 | Permit Issued | ENVIROTRAC LTD | Fence |
| 11/05/2025 | Permit Issued | NEHAL CONTRACTING INC | Fence |
| 11/05/2025 | Permit Issued | YARKS NYC INC | Sidewalk Shed |
| Date | Type | Result | Report |
|---|---|---|---|
| 06/12/2026 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 06/12/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 06/12/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 09/20/2022 | Pass-Final Boiler Equipment Inspection | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/06/2025 | Excavations - Sheeting, Shoring, and Bracing | MAXIM KORNGOLD | special |
| 08/06/2025 | Post-installed Anchors | MAXIM KORNGOLD | special |
| 09/13/2022 | Subsurface Investigations (Borings/Test Pits) | MARK STIER | special |
| 09/13/2022 | Energy Code Compliance Inspections | MAXIM KORNGOLD | progress |
| 09/12/2022 | Lighting controls | MAXIM KORNGOLD | energy_progress |
| 09/12/2022 | Maintenance information | MAXIM KORNGOLD | energy_progress |
| 09/12/2022 | HVAC-R and service water heating system controls | MAXIM KORNGOLD | energy_progress |
| 09/12/2022 | HVAC-R and service water heating equipment | MAXIM KORNGOLD | energy_progress |
| 09/12/2022 | Interior lighting power | MAXIM KORNGOLD | energy_progress |
| 09/08/2022 | Fuel-Oil Storage and Fuel-Oil Piping Systems | Michael Marchese | special |
| 09/06/2022 | Insulation placement and R values | — | energy_progress |
| 09/06/2022 | Protection of exposed foundation insulation | — | energy_progress |
| 08/04/2022 | Protection of exposed foundation insulation | MAXIM KORNGOLD | energy_progress |
| 08/04/2022 | Insulation placement and R values | MAXIM KORNGOLD | energy_progress |
| 08/04/2022 | Fenestration and door U-factor and product ratings | MAXIM KORNGOLD | energy_progress |
| 08/04/2022 | Air barrier - visual inspection | MAXIM KORNGOLD | energy_progress |
| 08/04/2022 | Fenestration air leakage | MAXIM KORNGOLD | energy_progress |
| 08/04/2022 | Fenestration areas | MAXIM KORNGOLD | energy_progress |
| 08/02/2022 | Post-installed Anchors | MAXIM KORNGOLD | special |
| 08/02/2022 | Fire-Resistant Penetrations and Joints | MAXIM KORNGOLD | special |
| 07/19/2022 | Post-installed Anchors | MAXIM KORNGOLD | special |
| 07/19/2022 | Maintenance information | MAXIM KORNGOLD | energy_progress |
| 07/19/2022 | Structural Steel - High Strength Bolting | MAXIM KORNGOLD | special |
| 07/19/2022 | Shutoff dampers | MAXIM KORNGOLD | energy_progress |
| 07/19/2022 | Subsurface Conditions – Fill Placement & In-Place Density | MAXIM KORNGOLD | special |