| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 10/20/2022 | $2.2M | — | — → — | $727/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| ZPROEKT ARCHITECTURE | 2 | 09/06/2024 |
| Representative | Filings | Most Recent |
|---|---|---|
| HM CONSULTING EXPEDITING | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| KADAR ELITE CONSTRUCTION | General Contractor | 1 | 04/09/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| AA BUILDING & INSPECTION | 1519 | 2 | 09/06/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Permit Issued | KADAR ELITE CONSTRUCTION | 09/25/2023 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/06/2024 | Complete | CMY ELECTRICAL CORP | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/06/2024 | Permit Issued | KADAR ELITE CONSTRUCTION | Concrete |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 09/25/2024 | Final | NAVEEN KUMAR | progress |
| 09/25/2024 | Concrete - Cast-In-Place | Younes Abouyaala | special |
| 09/25/2024 | Footing and Foundation | Younes Abouyaala | progress |
| 09/25/2024 | Lowest Floor Elevation | Younes Abouyaala | progress |
| 09/06/2024 | Concrete - Cast-In-Place | Younes Abouyaala | special |
| 09/06/2024 | Final | NAVEEN KUMAR | progress |
| 09/06/2024 | Footing and Foundation | Younes Abouyaala | progress |
| 09/06/2024 | Lowest Floor Elevation | Younes Abouyaala | progress |