← Back
One family attached or semi-detached
239-38 65 AVENUE
QUEENS · BIN 4172249
💬 Discuss this project
1975Year Built
2Stories
A5Building Class
R4Zoning
1,368 sfGross Floor Area
1Units
One family attached or semi-detached · 1,827 sf lot · 0.75 FAR built · Flood zone X
Locations of Work
Electrical
Roof1 filing · 8 docs
1 job · most recent 08/27/2025
FiledStatusContractorScope
08/27/2025CompleteREDLINE ELECTRIC INC—
1 job · most recent 09/03/2025
FiledStatusContractorScope
09/03/2025Permit IssuedTRINITY SOLAR LLC27 panels, 11.07 kw, 680 roof_area_sqft
Building Lifecycle
All (7)Filed (1)Permit Issued (1)Special Inspection (5)
09/05/2025
Permit issued — Solar
Q01280210-I1-SL
09/03/2025
Filed — Alteration
Installation of solar system on the roof as per plan. No change in use, egress or occupancy
Q01280210-I1
09/02/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
KAMRUL AHSAN
09/02/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
KAMRUL AHSAN
09/02/2025
Special inspection requirement — Energy Code Compliance Inspections
Ayracon Almaraz
09/02/2025
Special inspection requirement — Final
Ayracon Almaraz
09/02/2025
Special inspection requirement — Air barrier - visual inspection
Ayracon Almaraz
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
06/03/2019$843K—— → —$616/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
TRINITY SOLAR LLC109/03/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
ACA ASSOCIATES103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
TRINITY SOLAR LLCGeneral Contractor303/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
BITOPI CONSULTANTS LLC7036109/03/2025
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarPermit IssuedTRINITY SOLAR LLC09/05/2025
▾Special Inspection Requirements (DOB NOW) — 5
DateRequirementInspectorRole
09/02/2025Fire-Resistant Penetrations and JointsKAMRUL AHSANspecial
09/02/2025Structural Stability – Alterations of existing buildingsKAMRUL AHSANspecial
09/02/2025Energy Code Compliance InspectionsAyracon Almarazprogress
09/02/2025FinalAyracon Almarazprogress
09/02/2025Air barrier - visual inspectionAyracon Almarazenergy_progress
▾Documents — 8 on file (BIS + DOB NOW)
▸Plans & Drawings1
▸DOB NOWPlans/Sketch1
08/19/2026Q01280210-I1Request digital key ↗
▸Seals & Professional Certifications6
▸DOB NOWProgress Inspector Seal & Signature3
08/25/2026Q01280210-I1Open ↗
08/25/2026Q01280210-I1Open ↗
08/25/2026Q01280210-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature2
08/25/2026Q01280210-I1Open ↗
08/25/2026Q01280210-I1Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature1
08/19/2026Q01280210-I1Open ↗
▸Environmental & Asbestos1
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/19/2026Q01280210-I1Open ↗