| Firm | Filings | Most Recent |
|---|---|---|
| STANLEY M. KREBUSHEVSKI, R.A. | 1 | 10/31/2023 |
| Representative | Filings | Most Recent |
|---|---|---|
| APRILE BONAMO FILING REP | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| STATCON DEVELOPMENT LLC | General Contractor | 12 | 03/21/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| C&P DESIGN CONSULTANT | 8472 | 1 | 10/31/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Permit Issued | STATCON DEVELOPMENT LLC | 08/02/2024 |
| DOB NOW | Foundation | Permit Issued | STATCON DEVELOPMENT LLC | 04/01/2024 |
| DOB NOW | Foundation | Signed-off | STATCON DEVELOPMENT LLC | 04/01/2024 |
| DOB NOW | Foundation | Signed-off | STATCON DEVELOPMENT LLC | 04/01/2024 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/27/2024 | Complete | D AND H ELECTRICAL CONST | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/31/2023 | Permit Issued | STATCON DEVELOPMENT LLC | Masonry, Wood |
| Date | Type | Result | Report |
|---|---|---|---|
| 02/12/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 02/04/2025 | Fail-Final CND-Occupancy Inspection | Fail | View ↗ |
| 08/13/2024 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 08/09/2024 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 08/09/2024 | Certified Sprinkler - SP - Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/23/2023 | Subgrade Inspections | Stanislav Pilipenko | special |
| 08/23/2023 | Flood Zone Compliance (attach FEMA elevation/dry floodproofing certificate where applicable) | Stanislav Pilipenko | special |
| 08/23/2023 | Interior lighting power | Stanislav Pilipenko | energy_progress |
| 08/18/2023 | Subsurface Investigations (Borings/Test Pits) | WILLIAM MONTAGUE | special |
| 08/18/2023 | Masonry | Stanislav Pilipenko | special |
| 08/18/2023 | Concrete - Cast-In-Place | Stanislav Pilipenko | special |
| 08/18/2023 | Fire-Resistant Penetrations and Joints | Stanislav Pilipenko | special |
| 08/18/2023 | Energy Code Compliance Inspections | Stanislav Pilipenko | progress |
| 08/18/2023 | Fire-Resistance Rated Construction | Stanislav Pilipenko | progress |
| 08/18/2023 | Structural Wood Frame | Stanislav Pilipenko | progress |
| 08/07/2023 | Lowest Floor Elevation | Stanislav Pilipenko | progress |
| 08/07/2023 | Footing and Foundation | Stanislav Pilipenko | progress |
| 08/07/2023 | Final | Stanislav Pilipenko | progress |