← Back
Zoned commercial or Manhattan residential
24-00 SEAGIRT BOULEVARD
QUEENS · Far Rockaway-Bayswater · BIN 4625560
💬 Discuss this project
0Year Built
—Stories
V1Building Class
R5Zoning
0 sfGross Floor Area
0Units
0 Open ViolationsFDNY Report ↗
Zoned commercial or Manhattan residential · Owner of record: SEAGIRT BUYER LLC · 26,524 sf lot · 0 FAR built · Flood zone X500
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbingFire ProtectionEquipmentLandscapeCivilGeneralOther
Roof91p · 2 filings · 20 docs
Floor 590p · 1 filing · 20 docs
Floor 492p · 1 filing · 20 docs
Floor 397p · 1 filing · 20 docs
Floor 299p · 1 filing · 20 docs
Floor 1118p · 1 filing · 20 docs
Site & exterior112p · 4 filings · 20 docs
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
02/25/2025$2.8M—Private party → SEAGIRT BUYER LLC— not available
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
LEANDRO NILS DICKSON ARCHITECT, LLC907/01/2026
VASILIOS ARTEMIOU PE604/30/2026
LEANDRO DICKSON103/31/2026
BLACK SHEEP ENGINEERING GROUP703/30/2026
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
EXPRESS FILING INC2203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
INNOVATIVE CONSTR NYC LLCGeneral Contractor1106/27/2026
PRECISION HOIST & SCAFFO*General Contractor304/09/2026
PRIME PIPING & HEATING INFire Protection206/28/2026
PRIME PIPING & HEATING INPlumbing106/02/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
HRF SERVICES CORP56161004/30/2026
Building Lifecycle
All (107)Filed (23)Permit Issued (13)Signed Off (10)Violation (18)Inspection (6)Objection (4)Special Inspection (30)Tax Incentive (3)
12/24/2026
485-x construction completed
08/04/2026
Signed off — New Building
SPRINKLER SPECIFICATIONS FILED IN CONJUNCTION WITH GC APPLICATION Q01207697-I1
Q01207697-S6
07/27/2026
Special inspection requirement — Air barrier — testing
SHAHRIAR QUAYYUM
07/27/2026
Special inspection requirement — Fenestration and door U-factor and product ratings
SHAHRIAR QUAYYUM
07/27/2026
Special inspection requirement — Maintenance information
SHAHRIAR QUAYYUM
07/27/2026
Special inspection requirement — Exterior Insulation and Finish Systems (EIFS)
SHAHRIAR QUAYYUM
07/27/2026
Special inspection requirement — Fenestration air leakage
SHAHRIAR QUAYYUM
07/27/2026
Special inspection requirement — Protection of exposed foundation insulation
SHAHRIAR QUAYYUM
07/27/2026
Special inspection requirement — Insulation placement and R values
SHAHRIAR QUAYYUM
07/27/2026
Special inspection requirement — Interior lighting power
SHAHRIAR QUAYYUM
07/27/2026
Special inspection requirement — Lighting in dwelling units
SHAHRIAR QUAYYUM
07/27/2026
Special inspection requirement — Fenestration areas
SHAHRIAR QUAYYUM
07/27/2026
Special inspection requirement — Air barrier - visual inspection
SHAHRIAR QUAYYUM
07/27/2026
Special inspection requirement — Lighting controls
SHAHRIAR QUAYYUM
07/27/2026
Special inspection requirement — Metering
SHAHRIAR QUAYYUM
07/27/2026
Special inspection requirement — Electrical motors and elevators
SHAHRIAR QUAYYUM
07/27/2026
Special inspection requirement — Exterior lighting power
SHAHRIAR QUAYYUM
07/22/2026
Objection resolved — Addressed
07/22/2026
Objection resolved — Addressed
07/15/2026
Objection raised — Other
07/15/2026
Objection raised — Other
07/01/2026
Filed — New Building
SPRINKLER SPECIFICATIONS FILED IN CONJUNCTION WITH GC APPLICATION Q01207697-I1
Q01207697-A4
06/30/2026
Special inspection requirement — Exterior Insulation and Finish Systems (EIFS)
SHAHRIAR QUAYYUM
06/30/2026
Special inspection requirement — Air barrier - visual inspection
SHAHRIAR QUAYYUM
06/30/2026
Special inspection requirement — Fenestration areas
SHAHRIAR QUAYYUM
06/30/2026
Special inspection requirement — Exterior lighting power
SHAHRIAR QUAYYUM
06/30/2026
Special inspection requirement — Air barrier — testing
SHAHRIAR QUAYYUM
06/30/2026
Special inspection requirement — Metering
SHAHRIAR QUAYYUM
06/30/2026
Special inspection requirement — Protection of exposed foundation insulation
SHAHRIAR QUAYYUM
06/30/2026
Special inspection requirement — Interior lighting power
SHAHRIAR QUAYYUM
06/30/2026
Special inspection requirement — Fenestration air leakage
SHAHRIAR QUAYYUM
06/30/2026
Special inspection requirement — Electrical motors and elevators
SHAHRIAR QUAYYUM
06/30/2026
Special inspection requirement — Lighting controls
SHAHRIAR QUAYYUM
06/30/2026
Special inspection requirement — Fenestration and door U-factor and product ratings
SHAHRIAR QUAYYUM
06/30/2026
Special inspection requirement — Maintenance information
SHAHRIAR QUAYYUM
06/30/2026
Special inspection requirement — Lighting in dwelling units
SHAHRIAR QUAYYUM
06/30/2026
Special inspection requirement — Insulation placement and R values
SHAHRIAR QUAYYUM
06/29/2026
Signed off — New Building
SPRINKLER SPECIFICATIONS FILED IN CONJUNCTION WITH GC APPLICATION Q01207697-I1
Q01207697-S4
06/05/2026
Signed off — New Building
SPRINKLER SPECIFICATIONS FILED IN CONJUNCTION WITH GC APPLICATION Q01207697-I1
Q01207697-S5
05/28/2026
Inspection — Certified StandPipe-SD-Fixtures-Finish-SD
Certified
View inspection ↗
05/21/2026
Signed off — New Building
SPRINKLER SPECIFICATIONS FILED IN CONJUNCTION WITH GC APPLICATION Q01207697-I1
Q01207697-S2
05/21/2026
Signed off — New Building
SPRINKLER SPECIFICATIONS FILED IN CONJUNCTION WITH GC APPLICATION Q01207697-I1
Q01207697-S1
05/18/2026
Signed off — New Building
SPRINKLER SPECIFICATIONS FILED IN CONJUNCTION WITH GC APPLICATION Q01207697-I1
Q01207697-S7
05/18/2026
Signed off — New Building
SPRINKLER SPECIFICATIONS FILED IN CONJUNCTION WITH GC APPLICATION Q01207697-I1
Q01207697-S8
05/18/2026
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
05/15/2026
Inspection — Certified StandPipe-SD-Piping-Hydrostatic Test
Certified
View inspection ↗
05/04/2026
Signed off — Alteration
Installation of temporary overhead protection per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.
Q01318275-I1
05/04/2026
Signed off — Alteration
Installation of temporary sidewalk shed per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.
Q01318251-I1
05/04/2026
Signed off — Alteration
Installation of temporary supported scaffold per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.
Q01318261-I1
04/30/2026
Filed — New Building
SPRINKLER SPECIFICATIONS FILED IN CONJUNCTION WITH GC APPLICATION Q01207697-I1
Q01207697-A3
04/22/2026
Permit issued — General Construction
Q01207697-I1-GC
04/17/2026
Violation issued (ECB, closed)
Construction
04/17/2026
Violation issued (ECB, closed)
Unknown
03/31/2026
Filed — New Building
SPRINKLER SPECIFICATIONS FILED IN CONJUNCTION WITH GC APPLICATION Q01207697-I1
Q01207697-A1
03/31/2026
Filed — New Building
SPRINKLER SPECIFICATIONS FILED IN CONJUNCTION WITH GC APPLICATION Q01207697-I1
Q01207697-P5
03/31/2026
Filed — New Building
SPRINKLER SPECIFICATIONS FILED IN CONJUNCTION WITH GC APPLICATION Q01207697-I1
Q01207697-P9
03/30/2026
Filed — Alteration
Installation of temporary supported scaffold per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.
Q01318261-P1
03/27/2026
Violation issued (ECB, closed)
Unknown
03/26/2026
Violation issued (ECB, closed)
Construction
03/26/2026
Violation issued (ECB, closed)
Construction
Latest 60 of 107 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionPermit IssuedINNOVATIVE CONSTR NYC LLC04/22/2026
DOB NOWGeneral ConstructionPermit IssuedINNOVATIVE CONSTR NYC LLC12/30/2025
DOB NOWStructuralSigned-offINNOVATIVE CONSTR NYC LLC12/23/2025
DOB NOWPlumbingSigned-offPRIME PIPING & HEATING IN12/22/2025
DOB NOWEarth WorkSigned-offINNOVATIVE CONSTR NYC LLC12/22/2025
DOB NOWSprinklersSigned-offA M B MECHANICAL INC12/19/2025
DOB NOWStandpipeSigned-offA M B MECHANICAL INC12/19/2025
DOB NOWMechanical SystemsSigned-offINNOVATIVE CONSTR NYC LLC12/19/2025
DOB NOWProtection and Mechanical MethodsSigned-offPRECISION HOIST & SCAFFO*11/14/2025
DOB NOWSidewalk ShedSigned-offPRECISION HOIST & SCAFFO*11/14/2025
DOB NOWSupported ScaffoldSigned-offPRECISION HOIST & SCAFFO*11/14/2025
DOB NOWSupport of ExcavationSigned-offINNOVATIVE CONSTR NYC LLC10/30/2025
DOB NOWConstruction FenceSigned-offINNOVATIVE CONSTR NYC LLC10/27/2025
1 project · most recent 07/01/2026
Heating and Air Conditioning Systems
FiledStatusContractorScopeMake / Model / Capacity
07/01/2026Permit IssuedINNOVATIVE CONSTR NYC LLCHeating and Air Conditioning Systems
Heat / Cool
Amana PTH073J30 7,000 BTU · Ptac ×114
PTH153J30 14,400 BTU · Ptac ×54
PTH123J30 11,600 BTU · Ptac ×12
Samsung AM036FCMDCG 37,000 BTU · Vrf Indoor ×2
AC018DXSCCG 10,000 BTU · Vrf Indoor ×1
AJ020DXJ2CG 21,600 BTU · Vrf Outdoor ×1
AR18DXFAMWKXCV 20,000 BTU · Heat Pump Outdoor ×1
1 project · most recent 07/01/2026
Sprinkler System
FiledStatusContractorScope
07/01/2026Signed-offPRIME PIPING & HEATING INSprinkler System
1 project · most recent 07/01/2026
Gas Storm Water/Sanitary
FiledStatusContractorScope
07/01/2026Signed-offPRIME PIPING & HEATING INGas, Storm, Water/Sanitary
4 projects · most recent 01/13/2026
General Wiring
FiledStatusContractorScope
01/13/2026CompleteINTELOGIC ELECTRIC, INC.—
11/11/2025CompleteNASH ELECTRIC SERVICES IN—
07/01/2025Permit IssuedHIVOLTS ELECTRICAL INCGeneral Wiring
07/01/2025Permit IssuedHIVOLTS ELECTRICAL INC—
2 projects · most recent 03/30/2026
Scaffold Sidewalk Shed
FiledStatusContractorScope
03/30/2026Signed-offPRECISION HOIST & SCAFFO*Scaffold
02/24/2026Signed-offPRECISION HOIST & SCAFFO*Sidewalk Shed
▾Field Inspections (DOB CAP) — 6
DateTypeResultReport
05/28/2026Certified StandPipe-SD-Fixtures-Finish-SDCertifiedView ↗
05/18/2026Pass-Final CND-Occupancy InspectionPassView ↗
05/15/2026Certified StandPipe-SD-Piping-Hydrostatic TestCertifiedView ↗
03/09/2026Certified Gas-Gas-Piping-RoughingCertifiedView ↗
01/30/2026Certified Storm Drainage-ST-Piping-UndergroundCertifiedView ↗
01/30/2026Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 73
DateRequirementInspectorRole
07/27/2026Exterior lighting powerSHAHRIAR QUAYYUMenergy_progress
07/27/2026MeteringSHAHRIAR QUAYYUMenergy_progress
07/27/2026Electrical motors and elevatorsSHAHRIAR QUAYYUMenergy_progress
07/27/2026Protection of exposed foundation insulationSHAHRIAR QUAYYUMenergy_progress
07/27/2026Fenestration and door U-factor and product ratingsSHAHRIAR QUAYYUMenergy_progress
07/27/2026Exterior Insulation and Finish Systems (EIFS)SHAHRIAR QUAYYUMspecial
07/27/2026Lighting in dwelling unitsSHAHRIAR QUAYYUMenergy_progress
07/27/2026Insulation placement and R valuesSHAHRIAR QUAYYUMenergy_progress
07/27/2026Interior lighting powerSHAHRIAR QUAYYUMenergy_progress
07/27/2026Fenestration air leakageSHAHRIAR QUAYYUMenergy_progress
07/27/2026Lighting controlsSHAHRIAR QUAYYUMenergy_progress
07/27/2026Air barrier — testing SHAHRIAR QUAYYUMenergy_progress
07/27/2026Fenestration areasSHAHRIAR QUAYYUMenergy_progress
07/27/2026Air barrier - visual inspectionSHAHRIAR QUAYYUMenergy_progress
07/27/2026Maintenance informationSHAHRIAR QUAYYUMenergy_progress
06/30/2026Insulation placement and R valuesSHAHRIAR QUAYYUMenergy_progress
06/30/2026Exterior Insulation and Finish Systems (EIFS)SHAHRIAR QUAYYUMspecial
06/30/2026Air barrier - visual inspectionSHAHRIAR QUAYYUMenergy_progress
06/30/2026Air barrier — testing SHAHRIAR QUAYYUMenergy_progress
06/30/2026Interior lighting powerSHAHRIAR QUAYYUMenergy_progress
06/30/2026Fenestration air leakageSHAHRIAR QUAYYUMenergy_progress
06/30/2026Electrical motors and elevatorsSHAHRIAR QUAYYUMenergy_progress
06/30/2026Maintenance informationSHAHRIAR QUAYYUMenergy_progress
06/30/2026Lighting controlsSHAHRIAR QUAYYUMenergy_progress
06/30/2026Fenestration and door U-factor and product ratingsSHAHRIAR QUAYYUMenergy_progress
Latest 25 of 73.
▾Documents — 97 on file (BIS + DOB NOW)
▸Plans & Drawings20
▸DOB NOWPlans/Sketch20
08/17/2026Q01318251-I1Request digital key ↗
08/17/2026Q01318251-P1Request digital key ↗
08/17/2026Q01318275-P1Request digital key ↗
Showing 3 of 20 on file for this type
▸Applications & Permits2
▸BISBPP-5 - Authorization to the Department of Transportation1
07/03/2025440824057Open ↗
▸BISPLAN / WORK APPROVAL APPLICATION1
07/03/2025440824057Open ↗
▸Zoning, Tax Lot & Property Records8
▸DOB NOWZD1: DOB Zoning Diagram3
08/17/2026Q01207697-I1Open ↗
08/15/2026Q01207697-A4Open ↗
08/13/2026Q01207697-P5Open ↗
▸DOB NOWZoning Exhibit form (1-5)3
08/17/2026Q01207697-I1Open ↗
08/15/2026Q01207697-A4Open ↗
08/13/2026Q01207697-P5Open ↗
▸DOB NOWHouse Number Verification: TOPO Stamp2
08/17/2026Q01207697-I1Open ↗
08/13/2026Q01207697-P5Open ↗
▸Seals & Professional Certifications41
▸DOB NOWDPL-1: Design Professional Seal & Signature20
08/17/2026Q01318275-P2Open ↗
08/17/2026Q01318275-I1Open ↗
08/17/2026Q01318261-P1Open ↗
Showing 3 of 20 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature10
09/20/2026Q01207697-P3Open ↗
09/01/2026Q01207697-S5Open ↗
09/01/2026Q01207697-A3Open ↗
Showing 3 of 10 on file for this type
▸DOB NOWProgress Inspector Seal & Signature9
09/20/2026Q01207697-P3Open ↗
09/01/2026Q01207697-S5Open ↗
09/01/2026Q01207697-S5Open ↗
Showing 3 of 9 on file for this type
▸BISAPPLICANT OWNER SIGNATURE1
07/03/2025440824057Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
07/03/2025440824057Open ↗
▸Trade Schedules & Equipment1
▸DOB NOWDEP: Sewer Certification (Sanitary/Storm)1
08/17/2026Q01207697-I1Open ↗
▸Safety & Tenant Protection7
▸DOB NOWStreet Tree Checklist2
08/17/2026Q01207697-I1Open ↗
08/15/2026Q01207697-A4Open ↗
▸BISBPP: STREET TREES SITE PLAN1
09/03/2025440824057Open ↗
▸BISSTREET TREE CHECKLIST1
07/03/2025440824057Open ↗
▸DOB NOWStreet Tree Sign Off1
08/17/2026Q01207697-I1Open ↗
▸DOB NOWStreet Trees Site Plan1
08/17/2026Q01207697-I1Open ↗
▸DOB NOWParks Department Acknowledgment Letter for Street Trees Plan1
08/17/2026Q01207697-I1Open ↗
▸Energy Compliance1
▸DOB NOWPreliminary Commissioning Report Certification1
08/17/2026Q01207697-S6Open ↗
▸Approvals, Objections & Sign-offs1
▸BISDOT APPROVAL FOR APEX CORNER PEDRAMP1
09/03/2025440824057Open ↗
▸Filing & Intake Forms2
▸BISEFILING JOB APPLICATION COVER SHEET1
07/03/2025440824057Open ↗
▸BISBPP: CHECKLIST IN LIEU OF PLANS-ALT31
07/03/2025440824057Open ↗
▸Other Documents14
▸DOB NOWSite Survey: Initial3
08/17/2026Q01207697-I1Open ↗
08/15/2026Q01207697-A4Open ↗
08/13/2026Q01207697-P5Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone3
08/17/2026Q01207697-I1Open ↗
08/15/2026Q01207697-A4Open ↗
08/13/2026Q01207697-P5Open ↗
▸DOB NOWAdjoining Owners Notification2
08/13/2026Q01207697-S2Open ↗
08/13/2026Q01207697-S8Open ↗
▸DOB NOWProperty Ownership Certification2
08/17/2026Q01207697-I1Open ↗
08/15/2026Q01207697-A4Open ↗
▸BISBPP: PHOTOS-SIGNED/SEALED BY APPLICANT1
09/03/2025440824057Open ↗
▸BISRECORDS MGMT FEE PAYMENT RECEIPT1
09/03/2025440824057Open ↗
▸BISBPP - SUPPORTING DOCUMENTATION1
07/03/2025440824057Open ↗
▸DOB NOWFinal Survey1
08/17/2026Q01207697-I1Open ↗