Issued Permit Scope
Boiler Equipment · Mechanical Systems · Plumbing · Sprinklers · Structural
This application is filed for a temporary use permit for a sales office pursuant to section AC 28-111 and BB 2010-002. Temporary use permit is for 90 days.
On file for this project
9 documents
Floor 3Under Construction1p · 1 filing
ArchitectureCivilElectricalFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
Boiler Equipment · General Construction · Mechanical Systems · Plumbing · Sprinklers · Structural
This application is filed for a temporary use permit for a sales office pursuant to section AC 28-111 and BB 2010-002. Temporary use permit is for 90 days.
On file for this project
9 documents · 1 drawing sheet
Floor 2Under Construction1 filing
ArchitectureCivilElectricalFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
Boiler Equipment · General Construction · Mechanical Systems · Plumbing · Sprinklers · Structural
This application is filed for a temporary use permit for a sales office pursuant to section AC 28-111 and BB 2010-002. Temporary use permit is for 90 days.
On file for this project
9 documents
Floor 1Under Construction1p · 1 filing
ArchitectureCivilElectricalFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
Boiler Equipment · General Construction · Mechanical Systems · Plumbing · Sprinklers · Structural
This application is filed for a temporary use permit for a sales office pursuant to section AC 28-111 and BB 2010-002. Temporary use permit is for 90 days.
On file for this project
9 documents · 1 drawing sheet
Site & exterior1 filing
Fire ProtectionGeneralPlumbingStructural
Issued Permit Scope
Foundation · Plumbing · Support of Excavation
INSTALL 8' HIGH PLYWOOD CONSTRUCTION FENCE