← Back
Two family frame
24-35 BEACH CHANNEL DRIVE
QUEENS · BIN 4300948
💬 Discuss this project
2022Year Built
2Stories
B2Building Class
R4-1Zoning
2,484 sfGross Floor Area
2Units
0 Open ViolationsFDNY Report ↗
Two family frame · 2,886 sf lot · 0.86 FAR built · Flood zone X500
Locations of Work
ArchitecturePlumbing
Floor 22p · 1 filing · 3 docs
Floor 1
1 job · most recent 09/28/2021
General Wiring
FiledStatusContractorScope
09/28/2021CompleteSKY ELECTRIC LLCGeneral Wiring
Building Lifecycle
All (46)Filed (4)Permit Issued (4)Signed Off (4)Violation (7)Inspection (6)Objection (12)Special Inspection (9)
11/30/2021
Signed off — Alteration
Q00350435-I1
10/13/2021
Signed off — Alteration
installation of a new mechanical system, in conjunction with NB 421763906
Q00350437-I1
10/13/2021
Signed off — Alteration
installation of 8'3" temporary construction fence
Q00383169-I1
10/13/2021
Signed off — Alteration
installation of a shared 10'-0" CC
Q00583281-I1
10/04/2021
Inspection — Pass-Final Curb Cut Non-Directive 14
Pass
View inspection ↗
09/03/2021
Permit issued — Curb Cut
Q00583281-I1-CC
09/02/2021
Filed — Alteration
installation of a shared 10'-0" CC
Q00583281-I1
06/04/2021
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
06/04/2021
Inspection — Certified Storm Drainage-ST-Piping-Roughing
Certified
View inspection ↗
06/04/2021
Inspection — Certified Storm Drainage-ST-Piping-Underground
Certified
View inspection ↗
06/04/2021
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
06/04/2021
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
06/01/2021
Permit issued — Plumbing
Q00350435-I1-PL
04/22/2021
Permit issued — Mechanical Systems
Q00350437-I1-MS
01/25/2021
Permit issued — Construction Fence
Q00383169-I1-FN
11/24/2020
Objection raised — Other
11/24/2020
Objection resolved — Addressed
11/24/2020
Objection raised — Scope
11/24/2020
Objection resolved — Addressed
11/24/2020
Objection raised — Other
11/24/2020
Objection resolved — Addressed
09/23/2020
Filed — Alteration
installation of 8'3" temporary construction fence
Q00383169-I1
08/31/2020
Objection raised — Fire_Protection
08/31/2020
Objection resolved — Addressed
08/31/2020
Objection raised — Fire_Protection
08/31/2020
Objection resolved — Addressed
08/31/2020
Objection raised — Other
08/31/2020
Objection resolved — Addressed
08/24/2020
Filed — Alteration
Q00350435-I1
08/20/2020
Filed — Alteration
installation of a new mechanical system, in conjunction with NB 421763906
Q00350437-I1
08/20/2020
Special inspection requirement — Fire-Resistant Penetrations and Joints
PIROOZ SOLTANIZADEH
08/20/2020
Special inspection requirement — Heating Systems
PIROOZ SOLTANIZADEH
08/20/2020
Special inspection requirement — HVAC insulation and sealing
PIROOZ SOLTANIZADEH
08/20/2020
Special inspection requirement — HVAC and service water heating system controls
PIROOZ SOLTANIZADEH
08/20/2020
Special inspection requirement — Energy Code Compliance Inspections
PIROOZ SOLTANIZADEH
08/20/2020
Special inspection requirement — HVAC and service water heating equipment
PIROOZ SOLTANIZADEH
08/20/2020
Special inspection requirement — Shutoff dampers
PIROOZ SOLTANIZADEH
05/19/2020
Special inspection requirement — Mechanical Systems
PIROOZ SOLTANIZADEH
05/19/2020
Special inspection requirement — Final
JAN PEREZ
04/03/2017
Violation issued (ECB, closed)
Construction
04/03/2017
Violation issued (ECB, closed)
Construction
04/16/2013
Violation issued (ECB, closed)
Construction
04/17/2012
Violation issued (ECB, closed)
Construction
08/15/2008
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
10/31/2006
Violation issued (ECB, closed)
Site Safety
07/21/2006
Violation issued (ECB, closed)
Site Safety
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
UNITED DEVELOPERS LLC503/22/2026
ASHER HOME DEVELOPMENT403/22/2026
DOC FAR ROCKAWAY LLC OWNE103/22/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
01/18/2022$853K—BCD EQUITIES LLC → Private party$344/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
ARC CONSULTING ENGINEERS109/02/2021
PIROOZ ENGINEERING, P.C.309/23/2020
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
YAFE MEOD CORPGeneral Contractor407/08/2026
RAVI CONSTRUCTION AND EXPGeneral Contractor107/08/2026
INFINITI ESC PLUMBING CORPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
IP CONCRETE TESTING AND I6252108/24/2020
PIROOZ ENGINEERING P.C7177208/24/2020
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWCurb CutSigned-offYAFE MEOD CORP09/03/2021
DOB NOWPlumbingSigned-offINFINITI ESC PLUMBING COR06/01/2021
DOB NOWMechanical SystemsSigned-offYAFE MEOD CORP04/22/2021
DOB NOWConstruction FenceSigned-offRAVI CONSTRUCTION AND EXP01/25/2021
BIS—ISSUEDYAFE MEOD CORP08/23/2021
BIS—ISSUEDYAFE MEOD CORP07/23/2021
BIS—ISSUEDYAFE MEOD CORP03/15/2021
BIS—ISSUEDYAFE MEOD CORP03/10/2021
BIS—ISSUEDYAFE MEOD CORP03/05/2021
BISEQISSUEDKDK CONSTRUCTION CORP02/11/2010
BISEQISSUEDCARIBBEAN CONTRACTING COR08/18/2009
BISEQISSUEDBRH CONSTR & REST CORP08/06/2008
BIS—ISSUEDBRH CONSTR & REST CORP08/06/2008
BISEQISSUEDFIRST CLASS WRECKING INC06/08/2006
BIS—ISSUEDFIRST CLASS WRECKING INC06/08/2006
▾Field Inspections (DOB CAP) — 6
DateTypeResultReport
10/04/2021Pass-Final Curb Cut Non-Directive 14PassView ↗
06/04/2021Certified Gas-Gas-Piping-RoughingCertifiedView ↗
06/04/2021Certified Storm Drainage-ST-Piping-RoughingCertifiedView ↗
06/04/2021Certified Storm Drainage-ST-Piping-UndergroundCertifiedView ↗
06/04/2021Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
06/04/2021Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 9
DateRequirementInspectorRole
08/20/2020Fire-Resistant Penetrations and JointsPIROOZ SOLTANIZADEHspecial
08/20/2020Heating SystemsPIROOZ SOLTANIZADEHspecial
08/20/2020HVAC insulation and sealing PIROOZ SOLTANIZADEHenergy_progress
08/20/2020HVAC and service water heating system controls PIROOZ SOLTANIZADEHenergy_progress
08/20/2020Energy Code Compliance InspectionsPIROOZ SOLTANIZADEHprogress
08/20/2020HVAC and service water heating equipment PIROOZ SOLTANIZADEHenergy_progress
08/20/2020Shutoff dampersPIROOZ SOLTANIZADEHenergy_progress
05/19/2020Mechanical SystemsPIROOZ SOLTANIZADEHspecial
05/19/2020FinalJAN PEREZprogress
▾Documents — 62 on file (BIS + DOB NOW)
▸Plans & Drawings4
▸DOB NOWPlans/Sketch - Mechanical Systems1
08/14/2026Q00350437-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Construction Fence1
08/15/2026Q00383169-I1Request digital key ↗
▸DOB NOWPlans/Sketch1
08/27/2026Q00583281-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Plumbing1
08/28/2026Q00350435-I1Request digital key ↗
▸Applications & Permits6
▸BISPLAN / WORK APPROVAL APPLICATION3
06/17/2021421763906Open ↗
01/14/2021421763906Open ↗
05/11/2020421763906Open ↗
▸BISWORK PERMIT APPLICATION2
07/02/2021421763906Open ↗
03/16/2021421763906Open ↗
▸BISCERTIFICATE OF OCCUPANCY: APPLICATION1
08/12/2021421763906Open ↗
▸Zoning, Tax Lot & Property Records8
▸BISZONING EXHIBIT I: CERTIFICATION2
01/20/2021421763906Open ↗
11/23/2020421763906Open ↗
▸BISTAX LOT: TENTATIVE LOT NUMBER ISSUED1
05/21/2020421763906Open ↗
▸BISZONING EXHIBIT III:DESC. & OWNRSHP.STMNT1
11/23/2020421763906Open ↗
▸BISVERIFY TAX LOT1
10/22/2021421763906Open ↗
▸BISADDRESS: NEW HOUSE NUMBER APPROVED1
05/21/2020421763906Open ↗
▸BISCO OBJ: VERIFY ADDRESS-TOPO STAMP1
10/22/2021421763906Open ↗
▸BISZONING DIAGRAM1
02/03/2021421763906Open ↗
▸Seals & Professional Certifications8
▸DOB NOWDPL-1: Design Professional Seal & Signature4
08/28/2026Q00350435-I1Open ↗
08/28/2026Q00383169-I1Open ↗
08/27/2026Q00583281-I1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWProgress Inspector Seal & Signature3
08/25/2026Q00350437-I1Open ↗
08/25/2026Q00350437-I1Open ↗
08/25/2026Q00350437-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature1
08/25/2026Q00350437-I1Open ↗
▸Trade Schedules & Equipment3
▸BISDETECTOR:SMOKE-CERT. OF INSTALLATION1
10/22/2021421763906Open ↗
▸BISDETECTOR:CARBON MONOXIDE-CERT.OF INSTALL1
10/22/2021421763906Open ↗
▸BIS* SEWER CONNECTION: DEP SD1 & SD21
11/23/2020421763906Open ↗
▸Safety & Tenant Protection5
▸BISSTREET TREE CHECKLIST2
11/23/2020421763906Open ↗
05/21/2020421763906Open ↗
▸BISSTREET TREES: RECEIPT OF STREET TREES SITE PLAN1
02/18/2021421763906Open ↗
▸BISSTREET TREE SIGNOFF1
11/20/2021421763906Open ↗
▸BISSTREET TREES SITE PLAN1
10/22/2021421763906Open ↗
▸Energy Compliance8
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY5
10/22/2021421763906Open ↗
02/18/2021421763906Open ↗
01/20/2021421763906Open ↗
Showing 3 of 5 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS (EN2)1
11/20/2021421763906Open ↗
▸BISENERGY CODE COMPLIANCE INSPECTIONS1
12/13/2021421763906Open ↗
▸DOB NOWEN2: As Built Energy Analysis.1
08/13/2026Q00350435-I1Open ↗
▸Inspections & Test Reports8
▸BISTECHNICAL REPORT: RESPONSIBILITY5
10/22/2021421763906Open ↗
08/27/2021421763906Open ↗
02/18/2021421763906Open ↗
Showing 3 of 5 on file for this type
▸BISTR3: CONCRETE DESIGN MIX TECHNICAL REPORT1
02/22/2021421763906Open ↗
▸BISSOIL REPORT1
11/23/2020421763906Open ↗
▸BISTR2: CONCRETE FIELD TESTING TECHNICAL REPORT1
12/16/2021421763906Open ↗
▸Approvals, Objections & Sign-offs3
▸BISSCHEDULE A - OCCUPANCY / USE2
01/14/2021421763906Open ↗
05/11/2020421763906Open ↗
▸BISLETTERS - SUPPORTING DOCUMENTATION1
11/23/2020421763906Open ↗
▸Filing & Intake Forms5
▸BISBOROUGH INTAKE FORM2
07/02/2021421763906Open ↗
05/11/2020421763906Open ↗
▸BISADDITIONAL INFORMATION2
08/27/2021421763906Open ↗
11/23/2020421763906Open ↗
▸BISEFILING COVER SHEET1
05/11/2020421763906Open ↗
▸Other Documents4
▸BISCONSTRUCTION - SUPPORTING DOCUMENTATION1
03/16/2021421763906Open ↗
▸BISPLOT DIAGRAM1
05/21/2020421763906Open ↗
▸BISELECTRIC VEHICLE SERVICE EQUIPMENT REQUIREMENTS1
12/13/2021421763906Open ↗
▸BISSUSTAINABLE ROOF ZONE FORM1
11/23/2020421763906Open ↗