| Firm | Filings | Most Recent |
|---|---|---|
| MORALI ARCHITECTURE | 2 | 03/17/2026 |
| ATOZ CONSULTING ENGINEERS, PC | 4 | 03/16/2026 |
| SDG ENGINEERING PC | 3 | 08/27/2025 |
| Representative | Filings | Most Recent |
|---|---|---|
| ANTHONY MORALI ARCHITECT PLLC | 10 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| M.N.C. GENERAL CONTR CORP | General Contractor | 5 | 04/11/2026 |
| EMPIRE STATE FIRE SPRINKL | Fire Protection | 2 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| REGIONAL TESTING CORP. | 394 | 9 | 03/17/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Sprinklers | Signed-off | EMPIRE STATE FIRE SPRINKL | 01/29/2026 |
| DOB NOW | Support of Excavation | Signed-off | MNC GENERAL CONTR CORP | 12/24/2025 |
| DOB NOW | Mechanical Systems | Signed-off | MNC GENERAL CONTR CORP | 12/24/2025 |
| DOB NOW | Sprinklers | Signed-off | EMPIRE STATE FIRE SPRINKL | 12/23/2025 |
| DOB NOW | Foundation | Signed-off | MNC GENERAL CONTR CORP | 10/10/2025 |
| DOB NOW | Structural | Signed-off | MNC GENERAL CONTR CORP | 10/10/2025 |
| DOB NOW | General Construction | Signed-off | MNC GENERAL CONTR CORP | 09/04/2025 |
| BIS | EQ | ISSUED | LUIGI CALIENDO & SONS,INC | 11/20/2008 |
| BIS | EQ | ISSUED | PERIMETER BRIDGE & SCAFFOLD | 09/24/2008 |
| BIS | OT | ISSUED | LUIGI CALIENDO & SONS,INC | 09/10/2008 |
| BIS | EQ | ISSUED | LUIGI CALIENDO & SONS,INC | 09/10/2008 |
| BIS | OT | ISSUED | APPLE RESTORATION & WATERPROOF | 09/04/2007 |
| BIS | OT | ISSUED | DEIDAN INDUSTRIES LTD. | 01/04/1996 |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 03/18/2026 | Fire-Resistant Penetrations and Joints | Paul Raymond | special |
| 03/18/2026 | Energy Code Compliance Inspections | Paul Raymond | progress |
| 03/18/2026 | Final | Paul Raymond | progress |
| 03/18/2026 | Fenestration areas | Paul Raymond | energy_progress |
| 03/18/2026 | Lighting controls | Paul Raymond | energy_progress |
| 03/18/2026 | Air barrier - visual inspection | Paul Raymond | energy_progress |
| 03/18/2026 | Exterior Insulation and Finish Systems (EIFS) | Paul Raymond | special |
| 03/18/2026 | Interior lighting power | Paul Raymond | energy_progress |
| 03/18/2026 | Exterior lighting power | Paul Raymond | energy_progress |
| 03/18/2026 | Fenestration and door U-factor and product ratings | Paul Raymond | energy_progress |
| 03/18/2026 | Fenestration air leakage | Paul Raymond | energy_progress |
| 03/17/2026 | Fenestration areas | Paul Raymond | energy_progress |
| 03/17/2026 | Exterior Insulation and Finish Systems (EIFS) | Paul Raymond | special |
| 03/17/2026 | Fire-Resistant Penetrations and Joints | Paul Raymond | special |
| 03/17/2026 | Energy Code Compliance Inspections | Paul Raymond | progress |
| 03/17/2026 | Final | Paul Raymond | progress |
| 03/17/2026 | Fenestration and door U-factor and product ratings | Paul Raymond | energy_progress |
| 03/17/2026 | Exterior lighting power | Paul Raymond | energy_progress |
| 03/17/2026 | Air barrier - visual inspection | Paul Raymond | energy_progress |
| 03/17/2026 | Fenestration air leakage | Paul Raymond | energy_progress |
| 03/17/2026 | Lighting controls | Paul Raymond | energy_progress |
| 03/17/2026 | Interior lighting power | Paul Raymond | energy_progress |
| 03/16/2026 | Shutoff dampers | Paul Raymond | energy_progress |
| 03/16/2026 | Mechanical Systems | Paul Raymond | special |
| 03/16/2026 | Fire-Resistant Penetrations and Joints | Paul Raymond | special |