Two stories - detached, small or mid-size
24 HEUSDEN STREET
STATEN ISLAND · Mariner's Harbor-Arlington-Graniteville · BIN 5027157
💬 Discuss this project
1920Year Built
2Stories
A1Building Class
R3AZoning
1,276 sfGross Floor Area
1Units
Two stories - detached, small or mid-size · 3,300 sf lot · 0.39 FAR built · Flood zone X
Locations of Work
Electrical
Roof1 filing · 7 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
MOMENTUM SOLAR101/23/2024
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
MXV SIA LLC9281101/23/2024
Building Lifecycle
All (17)Filed (1)Permit Issued (1)Objection (10)Special Inspection (5)
04/09/2024
Permit issued — Solar
S00992198-I1-SL
04/02/2024
Objection resolved — Addressed
03/19/2024
Objection resolved — Addressed
03/18/2024
Objection raised — Other
03/14/2024
Objection resolved — Addressed
03/14/2024
Objection resolved — Addressed
03/14/2024
Objection resolved — Addressed
03/08/2024
Objection raised — Other
02/20/2024
Objection raised — Other
01/26/2024
Objection raised — Other
01/26/2024
Objection raised — Other
01/23/2024
Filed — Alteration
Installation of solar panels; Rooftop, Railed, Grid tied, 22 Panels, 8.8 kW
S00992198-I1
01/18/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
Mina Makar
01/18/2024
Special inspection requirement — Structural Stability – Alterations of existing buildings
Mina Makar
01/18/2024
Special inspection requirement — Energy Code Compliance Inspections
Mina Makar
01/18/2024
Special inspection requirement — Final
Mina Makar
01/18/2024
Special inspection requirement — Air barrier - visual inspection
Mina Makar
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarPermit IssuedMOMENTUM SOLAR04/09/2024
1 project · most recent 01/18/2024
FiledStatusContractorScope
01/18/2024Permit IssuedISLAND ELECTRIC CORP—
1 project · most recent 01/23/2024
FiledStatusContractorScope
01/23/2024Permit IssuedMOMENTUM SOLAR22 panels, 8.8 kw, 387 roof_area_sqft
▾Special Inspection Requirements (DOB NOW) — 5
DateRequirementInspectorRole
01/18/2024Fire-Resistant Penetrations and JointsMina Makarspecial
01/18/2024Structural Stability – Alterations of existing buildingsMina Makarspecial
01/18/2024Energy Code Compliance InspectionsMina Makarprogress
01/18/2024FinalMina Makarprogress
01/18/2024Air barrier - visual inspectionMina Makarenergy_progress
▾Documents — 7 on file (BIS + DOB NOW)
▸Plans & Drawings1
▸DOB NOWPlans/Sketch1
08/21/2026S00992198-I1Request digital key ↗
▸Seals & Professional Certifications4
▸DOB NOWProgress Inspector Seal & Signature2
08/23/2026S00992198-I1Open ↗
08/23/2026S00992198-I1Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature1
08/13/2026S00992198-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature1
08/23/2026S00992198-I1Open ↗
▸Environmental & Asbestos1
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/13/2026S00992198-I1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/13/2026S00992198-I1Open ↗