| Firm | Filings | Most Recent |
|---|---|---|
| Unisolar | 2 | 01/02/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| Centurion Solar Energy | General Contractor | 3 | 03/21/2026 |
| Berger Quality Electrical Con | Electrical | 1 | 03/22/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| Centurion Solar Energy | 9475 | 2 | 01/02/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Solar | Signed-off | Centurion Solar Energy | 06/30/2025 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/14/2025 | Complete | Berger Quality Electrical Con | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/02/2026 | Signed-off | Centurion Solar Energy | — |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 05/12/2026 | Fire-Resistant Penetrations and Joints | Andres Arias Londono | special |
| 05/12/2026 | Flood Zone Compliance (attach FEMA elevation/dry floodproofing certificate where applicable) | Andres Arias Londono | special |
| 05/12/2026 | Energy Code Compliance Inspections | Andres Arias Londono | progress |
| 05/12/2026 | Final | Andres Arias Londono | progress |
| 05/12/2026 | Air barrier - visual inspection | Andres Arias Londono | energy_progress |
| 01/02/2026 | Fire-Resistant Penetrations and Joints | Andres Arias Londono | special |
| 01/02/2026 | Flood Zone Compliance (attach FEMA elevation/dry floodproofing certificate where applicable) | Andres Arias Londono | special |
| 01/02/2026 | Energy Code Compliance Inspections | Andres Arias Londono | progress |
| 01/02/2026 | Final | Andres Arias Londono | progress |
| 01/02/2026 | Air barrier - visual inspection | Andres Arias Londono | energy_progress |