| Owner | Filings | Most Recent |
|---|---|---|
| 100 UNITED NATIONS PLAZA CONDOMINIU | 4 | 07/08/2026 |
| SACKS REAL ESTATE MANAGEMENT | 18 | 07/08/2026 |
| 17 AND 24 CORPORATION | 31 | 03/22/2026 |
| 1724 CORP/RNDD MANAGEMENT | 1 | 03/22/2026 |
| 102008E2436B03 | 1 | 03/22/2026 |
| 17 AND 27 CORP | 1 | 03/22/2026 |
| COLEMAN | 1 | 03/21/2026 |
| DAVID TURNER ARCHITECT P C | 2 | 03/21/2026 |
| 17 24 CORPORATION ROCKEFELLER AP | 11 | 03/21/2026 |
| 17 24 OWNERS | 2 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| NEWTEC ENGINEERING | 1 | 08/07/2026 |
| JACK GREEN ASSOCIATES | 4 | 07/15/2026 |
| SARAH GORDON DRAKE ARCHITECT, LLC | 6 | 07/14/2026 |
| ALLEN STRASEN ARCHITECT PC | 2 | 06/04/2026 |
| DARIO PASQUARIELLO ARCHITECT | 1 | 09/12/2025 |
| PIRO STUDIO LLC | 4 | 05/16/2025 |
| GREENWICH DESIGN ARCHITECTS, INC. | 1 | 07/15/2024 |
| ABS ENGINEERING, PLLC | 3 | 04/05/2024 |
| DAVID TURNER ARCHITECT PC | 1 | 11/19/2023 |
| CORTNEY WALLESTON ARCHITECT, PC | 1 | 07/21/2021 |
| STEPHANIE GELB, ARCHITECT | 1 | 06/16/2021 |
| ALTIERI SEBOR WIEBER LLC | 1 | 03/15/2021 |
| VINCENT J. LIOTTA P.E. | 1 | 02/06/2020 |
| PCS ENGINEERING | 2 | 09/11/2019 |
| Representative | Filings | Most Recent |
|---|---|---|
| DOMANI CONSULTING | 6 | 03/21/2026 |
| DJL ARCHITECT | 1 | 03/21/2026 |
| DI DIO ARCHITECTURE, PC | 8 | 03/21/2026 |
| CONVERSANO ASSOCIATES, INC. | 6 | 03/21/2026 |
| SALVUS GROUP | 2 | 03/21/2026 |
| ENIGMA EXPEDITING | 4 | 03/21/2026 |
| J A EXPEDITING | 2 | 03/21/2026 |
| MARYCLARE NEPOGODA EXPEDITER | 2 | 03/21/2026 |
| VINCENT J. LIOTTA P.E. | 1 | 03/21/2026 |
| VINCENT J. LIOTTA P. E. | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| GOLDEN HVAC INC | General Contractor | 10 | 07/08/2026 |
| AMSTERDAM RESTORATION LLC | General Contractor | 4 | 07/08/2026 |
| BEDNARZ CONSTRUCTION LLC | General Contractor | 4 | 07/08/2026 |
| BLUE CITY CONSTRUCTION | General Contractor | 3 | 03/21/2026 |
| MACREDDIN PLBG & HTG INC | Plumbing | 2 | 07/08/2026 |
| SYED-NAQVI ALTAF | Electrical | 2 | 03/21/2026 |
| SYED-NAQVI, ALTAF | Electrical | 2 | 03/21/2026 |
| AIR DEPOT COMM. REFR. COR | General Contractor | 2 | 03/21/2026 |
| HANJO CONTRACTORS INC | General Contractor | 2 | 03/21/2026 |
| LIEBHABER COMPANY INC | General Contractor | 2 | 03/21/2026 |
| THINK CONSTRUCTION LLC | General Contractor | 2 | 04/09/2026 |
| THE METRO GROUP ELECTRIC | Electrical | 1 | 03/22/2026 |
| VINCENT AMATO | Electrical | 1 | 03/21/2026 |
| VINCENT VERDEROSA | Electrical | 1 | 03/21/2026 |
| VMA ELECTRICAL CORP. | Electrical | 1 | 03/22/2026 |
| 4IR IDEAL INC | General Contractor | 1 | 08/20/2026 |
| AMATO VINCENT | Electrical | 1 | 03/21/2026 |
| HAS, MEHMET | Electrical | 1 | 03/21/2026 |
| AVALAIR COOLING CORP | General Contractor | 1 | 07/08/2026 |
| DARDIS, JOHN | Electrical | 1 | 03/21/2026 |
| BRENDAN REILLY | Electrical | 1 | 03/21/2026 |
| EGNATIA CONSTRUCTION INC | General Contractor | 1 | 07/08/2026 |
| AVALON ELECTRIC CORP. | Electrical | 1 | 03/22/2026 |
| ARCON PLBG SOLUTIONS | Plumbing | 1 | 07/08/2026 |
| HONEY HAMMER CORP | General Contractor | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| OBAID MIAN | 849 | 1 | 08/07/2026 |
| JACK GREEN ASSOCIATES | 422 | 2 | 07/15/2026 |
| SARAH GORDON DRAKE ARCHIT | 4744 | 4 | 07/14/2026 |
| JSPECS,INC | 9429 | 1 | 10/15/2025 |
| DARIO ARCHITECTURE &DESIG | 6878 | 1 | 09/12/2025 |
| PIRO STUDIO LLC | 7503 | 4 | 05/16/2025 |
| STEEL CORE ENGINEERING PL | 1098 | 3 | 04/05/2024 |
| DAVID TURNER ARCHITECT PC | 3829 | 1 | 11/19/2023 |
| CORTNEY WALLESTON ARCHITE | 3881 | 1 | 07/21/2021 |
| P.A.COLLINS INSPECTIONS P | 2168 | 2 | 05/19/2021 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Permit Issued | 4IR IDEAL INC | 08/19/2026 |
| DOB NOW | General Construction | Permit Issued | HONEY HAMMER CORP | 06/11/2026 |
| DOB NOW | Plumbing | Permit Issued | ARCON PLBG SOLUTIONS | 01/21/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | THINK CONSTRUCTION LLC | 01/20/2026 |
| DOB NOW | General Construction | Permit Issued | THINK CONSTRUCTION LLC | 01/20/2026 |
| DOB NOW | General Construction | Permit Issued | KING ROSE OF NY, INC | 11/14/2025 |
| DOB NOW | General Construction | Signed-off | RAKA PAINTING INC | 10/03/2025 |
| DOB NOW | Plumbing | Signed-off | MACREDDIN PLBG & HTG INC | 06/27/2025 |
| DOB NOW | Mechanical Systems | Signed-off | BEDNARZ CONSTRUCTION LLC | 06/17/2025 |
| DOB NOW | Mechanical Systems | Signed-off | STANLEY RUTH CO LLC | 12/13/2024 |
| DOB NOW | Plumbing | Signed-off | DELTA-SIGMA MECH CORP | 06/21/2024 |
| DOB NOW | General Construction | Signed-off | HANJO CONTRACTORS | 06/21/2024 |
| DOB NOW | Plumbing | Signed-off | MACREDDIN PLBG & HTG INC | 06/04/2024 |
| DOB NOW | General Construction | Signed-off | BEDNARZ CONSTRUCTION LLC | 06/03/2024 |
| DOB NOW | General Construction | Signed-off | LIEBHABER COMPANY | 07/18/2023 |
| DOB NOW | General Construction | Signed-off | EGNATIA CONSTRUCTION | 04/21/2022 |
| DOB NOW | General Construction | Signed-off | BLUE CITY CONSTRUCTION | 08/05/2021 |
| DOB NOW | Mechanical Systems | Signed-off | AIR DEPOT COMM REFR COR | 06/24/2021 |
| DOB NOW | Mechanical Systems | Signed-off | AVALAIR COOLING CORP | 05/18/2021 |
| DOB NOW | Mechanical Systems | Signed-off | GOLDEN HVAC INC | 03/03/2021 |
| DOB NOW | Mechanical Systems | Signed-off | GOLDEN HVAC INC | 09/14/2020 |
| DOB NOW | Mechanical Systems | Signed-off | GOLDEN HVAC INC | 07/29/2020 |
| DOB NOW | Mechanical Systems | Signed-off | GOLDEN HVAC INC | 02/10/2020 |
| DOB NOW | Sidewalk Shed | Signed-off | AMSTERDAM RESTORATION LLC | 08/02/2019 |
| DOB NOW | Supported Scaffold | Signed-off | AMSTERDAM RESTORATION LLC | 08/02/2019 |
| BIS | OT | ISSUED | AMSTERDAM RESTORATION LLC | 02/05/2021 |
| BIS | PL | ISSUED | ZONE PLUMBING & HEATING C | 12/01/2020 |
| BIS | OT | ISSUED | BUILD NOW NYC INC | 10/20/2020 |
| BIS | OT | ISSUED | AMSTERDAM RESTORATION LLC | 06/04/2020 |
| BIS | OT | ISSUED | AMSTERDAM RESTORATION LLC | 09/18/2019 |
| BIS | PL | ISSUED | ZONE PLUMBING & HEATING C | 05/10/2019 |
| BIS | OT | ISSUED | BUILD NOW NYC INC | 05/08/2019 |
| BIS | OT | ISSUED | LIEBHABER COMPANY INC | 04/23/2019 |
| BIS | MH | ISSUED | STANLEY RUTH CO LLC | 09/28/2018 |
| BIS | OT | ISSUED | EAST SIDE INTERIORS INC | 05/23/2017 |
| BIS | PL | ISSUED | SUPERB PLUMBING & HEATING | 04/27/2017 |
| BIS | OT | ISSUED | PH CUSTOM HOME IMPROVEMEN | 04/25/2017 |
| BIS | MH | ISSUED | STANLEY RUTH CO INC | 12/23/2016 |
| BIS | PL | ISSUED | P.S.I. MECHANICAL | 08/19/2016 |
| BIS | MH | ISSUED | EAST SIDE INTERIORS INC | 08/19/2016 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 08/07/2026 | Permit Issued | 4IR IDEAL INC | Air Conditioning Systems | Cooling Daikin FXZA07AAVJU 300 CFM · Vrf Indoor ×7 FXMA48AAVJU 1,377 CFM · Vrf Indoor ×1 RXYA96AATJA 96,000 BTU · Vrf Outdoor ×1 Mitsubishi Electric PLFY-EL24NEMU-A 812 CFM · Vrf Indoor ×2 MXZ-SM48NL 48,000 BTU · Condensing Unit ×1 |
| 07/15/2026 | Permit Issued | THINK CONSTRUCTION LLC | Air Conditioning Systems | Cooling Mitsubishi Electric PEFY-P12MNSU-ER2 12,000 BTU · Vrf Indoor ×4 MXZ-SM60NAM2-U1 60,000 BTU · Condensing Unit ×2 PUY-AK12NL 12,200 BTU · Condensing Unit ×2 PUY-AL12NL 12,000 BTU · Heat Pump Outdoor ×2 PVFY-P36NAMU-E1 36,000 BTU · Vrf Indoor ×2 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/15/2026 | Permit Issued | ARCON PLBG SOLUTIONS | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/18/2026 | Permit Issued | THE METRO GROUP ELECTRIC | General Wiring |
| 04/16/2026 | Complete | E & M ELECTRICAL NY CORP | General Wiring |
| 04/09/2026 | Complete | AUJLA ELECTRIC CORP | — |
| 01/23/2026 | Permit Issued | FINESSE ELECTRIC LLC | General Wiring |
| 12/15/2025 | Permit Issued | ESSEX ELECTRIC INC | General Wiring |
| 10/14/2025 | Complete | SOURCE ELECTRIC INC | General Wiring, Lighting |
| 08/23/2025 | Permit Issued | VMA ELECTRICAL CORP. | General Wiring |
| 06/02/2025 | Complete | MARKS ELECTRIC CORP | General Wiring |
| 05/26/2025 | Complete | JUMPER ELECTRIC CORP | General Wiring |
| 05/21/2025 | Complete | IP2 ELECTRIC LLC | General Wiring |
| 05/01/2025 | Complete | THE METRO GROUP ELECTRIC | General Wiring |
| 02/06/2025 | Complete | THE METRO GROUP ELECTRIC | General Wiring |
| 11/07/2024 | Complete | THE METRO GROUP ELECTRIC | General Wiring |
| 04/10/2024 | Complete | THE METRO GROUP ELECTRIC | General Wiring |
| 03/14/2024 | Complete | AUJLA ELECTRIC CORP | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/15/2026 | Permit Issued | ARCON PLBG SOLUTIONS | Tenant Protection Plan 72 Hour |
| 09/12/2025 | Signed-off | RAKA PAINTING INC | Tenant Protection Plan 72 Hour |
| Date | Type | Result | Report |
|---|---|---|---|
| 08/12/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 06/02/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 05/05/2026 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 03/27/2026 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 06/16/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 06/13/2025 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 05/08/2025 | Fail-Final PL - Up to 9 Requested Floors | Fail | View ↗ |
| 11/07/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 11/06/2024 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 11/01/2024 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 09/13/2022 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/03/2026 | Final | LAWRENCE GREEN | progress |
| 08/03/2026 | Mechanical Systems | LAWRENCE GREEN | special |
| 07/09/2026 | Fire-Resistant Penetrations and Joints | Sarah Drake | special |
| 07/09/2026 | Fire-Resistance Rated Construction | Sarah Drake | progress |
| 07/09/2026 | Final | Sarah Drake | progress |
| 06/18/2026 | HVAC-R and service water piping design and insulation | Obaid Mian | energy_progress |
| 06/18/2026 | HVAC-R and service water heating system controls | Obaid Mian | energy_progress |
| 06/18/2026 | HVAC-R and service water heating equipment | Obaid Mian | energy_progress |
| 06/18/2026 | Maintenance information | Obaid Mian | energy_progress |
| 06/18/2026 | Mechanical Systems | Obaid Mian | special |
| 06/18/2026 | Tenant Protection Plan Compliance | Obaid Mian | special |
| 06/18/2026 | Final | Obaid Mian | progress |
| 06/09/2026 | Final | ALLEN STRASEN | progress |
| 06/09/2026 | Lighting in dwelling units | ALLEN STRASEN | energy_progress |
| 06/02/2026 | Lighting in dwelling units | ALLEN STRASEN | energy_progress |
| 06/02/2026 | Final | ALLEN STRASEN | progress |
| 07/27/2025 | Fire-Resistant Penetrations and Joints | Dario Pasquariello | special |
| 07/27/2025 | Lighting in dwelling units | Dario Pasquariello | energy_progress |
| 05/29/2025 | Fire-Resistant Penetrations and Joints | PIETRO ROSATO | special |
| 05/12/2025 | Fire-Resistant Penetrations and Joints | PIETRO ROSATO | special |
| 06/05/2024 | Energy Code Compliance Inspections | Vitaly Sonkin | progress |
| 04/05/2024 | Final | Vitaly Sonkin | progress |
| 04/02/2024 | Ventilation and air distribution system | Alexander Sheyman | energy_progress |
| 04/02/2024 | HVAC-R and service water piping design and insulation | Alexander Sheyman | energy_progress |
| 04/02/2024 | Maintenance information | Alexander Sheyman | energy_progress |