← Back
Elevator apt, semi-fireproof with stores
Stuy Town Peter Cooper Village
240 1 AVENUE · BIN 1082852
💬 Discuss this project
1945Year Built
13Stories
D7Building Class
R7-2Zoning
8,942,176 sfGross Floor Area
8,812Units
LL97 CoveredRent Stabilized18 Open Violations ▸FISP: SAFE
Elevator apt, semi-fireproof with stores · Owner of record: BPP ST OWNER LLC · 2,675,000 sf lot · 3.34 FAR built · Flood zone AE
Locations of Work
ArchitectureEquipment
Roof1p · 1 filing · 11 docs
Bulkhead2p · 2 filings · 16 docs
25 jobs · most recent 04/29/2026
General Wiring
FiledStatusContractorScope
04/29/2026Permit IssuedELECTRICAL SOLUTIONS LLCGeneral Wiring
10/21/2025CompleteELECTRICAL SOLUTIONS LLCGeneral Wiring
05/15/2025CompleteELECTRICAL SOLUTIONS LLCGeneral Wiring
05/10/2025CompleteWCK ELECTRIC CORP.—
04/03/2025CompleteGRX EURO ELECTRIC CORP—
08/22/2024CompleteELECTRICAL SOLUTIONS LLCGeneral Wiring
08/15/2024CompleteELECTRICAL SOLUTIONS LLCGeneral Wiring
05/17/2024CompleteELECTRICAL SOLUTIONS LLCGeneral Wiring
11/27/2023Permit IssuedELECTRICAL SOLUTIONS LLCGeneral Wiring
11/06/2023CompleteELECTRICAL SOLUTIONS LLCGeneral Wiring
07/19/2023CompleteELECTRICAL SOLUTIONS LLCGeneral Wiring
03/03/2023CompleteELECTRICAL SOLUTIONS LLCGeneral Wiring
02/22/2023CompleteELECTRICAL SOLUTIONS LLCGeneral Wiring
01/23/2023CompleteELECTRICAL SOLUTIONS LLCGeneral Wiring
01/17/2023CompleteELECTRICAL SOLUTIONS LLCGeneral Wiring
1 job · most recent 04/06/2026
FiledStatusContractorScope
04/06/2026Signed-offSUPER G CONSTRUCTION CORP1 scope_items
1 job · most recent 02/25/2026
Sidewalk Shed
FiledStatusContractorScope
02/25/2026Signed-offPJP INSTALLERS INCSidewalk Shed
1 job · most recent 05/08/2025
Suspended Scaffold (SC)
FiledStatusContractorScope
05/08/2025Signed-offTC ZONE INCSuspended Scaffold (SC)
Building Lifecycle
All (139)Filed (15)Permit Issued (11)Signed Off (11)Facade (FISP) (15)Violation (55)Objection (2)Special Inspection (30)
07/07/2026
Signed off — Alteration
General construction for interior renovation of Apartment 10E on the 11th floor as shown on drawings filed herewith. No change in use, egress or occupancy.
M01380347-I1
05/28/2026
Signed off — Alteration
General construction for interior renovation of Apartment 4H on the 5th floor as shown on drawings filed herewith. No change in use, egress or occupancy.
M01382157-I1
05/18/2026
Cycle 9 facade report signed — SAFE
05/08/2026
Signed off — Alteration
INSTALLATION OF OUTRIGGER SCAFFOLD AS PER DESIGN DRAWING. NO CHANGE IN USE, OCCUPANCY, OR EGRESS UNDER THIS APPLICATION.
M01219981-I1
05/08/2026
Signed off — Alteration
Filing for limited facade repairs at 610 East 20th Street and 620 East 20th Street as shown on drawings filed herewith. No change in use, egress or occupancy.
M01219634-I1
05/07/2026
Cycle 9 facade report submitted
05/05/2026
Signed off — Alteration
STORAGE OF MATERIAL / EQUIPMENT ON TOP OF SIDEWALK SHED. STORAGE SHALL NOT EXCEED 25 PSF. SHED FILED UNDER SEPARATE APPLICATION. STORAGE SHALL COMPLY WITH CH#33 OF THE NYC BLDG CODE. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION
M01223404-I1
05/05/2026
Signed off — Alteration
INSTALLATION OF SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M01218243-I1
05/05/2026
Cycle 9 facade inspection completed
04/23/2026
Permit issued — General Construction
M01380347-I1-GC
04/21/2026
Filed — Alteration
General construction for interior renovation of Apartment 10E on the 11th floor as shown on drawings filed herewith. No change in use, egress or occupancy.
M01380347-I1
04/20/2026
Special inspection requirement — Energy Code Compliance Inspections
John Field
04/20/2026
Special inspection requirement — Lighting in dwelling units
John Field
04/17/2026
Special inspection requirement — Masonry
Sandeep Gunnala
04/17/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
Sandeep Gunnala
04/17/2026
Special inspection requirement — Post-installed Anchors
Sandeep Gunnala
04/17/2026
Special inspection requirement — Final
Sandeep Gunnala
04/17/2026
Special inspection requirement — Tenant Protection Plan Compliance
Sandeep Gunnala
04/15/2026
Filed — Alteration
Filing for limited facade repairs at 610 East 20th Street and 620 East 20th Street as shown on drawings filed herewith. No change in use, egress or occupancy.
M01219634-P1
04/07/2026
Permit issued — General Construction
M01382157-I1-GC
04/06/2026
Filed — Alteration
General construction for interior renovation of Apartment 4H on the 5th floor as shown on drawings filed herewith. No change in use, egress or occupancy.
M01382157-I1
04/02/2026
Special inspection requirement — Tenant Protection Plan Compliance
John Field
03/31/2026
Special inspection requirement — Final
John Field
02/25/2026
Filed — Alteration
INSTALLATION OF SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M01218243-P2
08/06/2025
Filed — Alteration
INSTALLATION OF SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M01218243-P1
07/02/2025
Signed off — Alteration
General construction for interior renovation of Apartment 9D on the 10th floor as shown on drawings filed herewith. No change in use, egress or occupancy.
M01212217-I1
06/02/2025
Permit issued — General Construction
M01219634-I1-GC
05/30/2025
Filed — Alteration
STORAGE OF MATERIAL / EQUIPMENT ON TOP OF SIDEWALK SHED. STORAGE SHALL NOT EXCEED 25 PSF. SHED FILED UNDER SEPARATE APPLICATION. STORAGE SHALL COMPLY WITH CH#33 OF THE NYC BLDG CODE. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION
M01223404-P1
05/20/2025
Filed — Alteration
Filing for limited facade repairs at 610 East 20th Street and 620 East 20th Street as shown on drawings filed herewith. No change in use, egress or occupancy.
M01219634-I1
05/20/2025
Permit issued — Suspended Scaffold
M01219981-I1-SC
05/16/2025
Objection resolved — Addressed
05/15/2025
Objection raised — Other
05/15/2025
Special inspection requirement — Alternative Materials - OTCR Buildings Bulletin Number
Sandeep Gunnala
05/14/2025
Permit issued — Protection and Mechanical Methods
M01223404-I1-PMM
05/13/2025
Filed — Alteration
STORAGE OF MATERIAL / EQUIPMENT ON TOP OF SIDEWALK SHED. STORAGE SHALL NOT EXCEED 25 PSF. SHED FILED UNDER SEPARATE APPLICATION. STORAGE SHALL COMPLY WITH CH#33 OF THE NYC BLDG CODE. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION
M01223404-I1
05/12/2025
Permit issued — General Construction
M01212217-I1-GC
05/08/2025
Filed — Alteration
INSTALLATION OF OUTRIGGER SCAFFOLD AS PER DESIGN DRAWING. NO CHANGE IN USE, OCCUPANCY, OR EGRESS UNDER THIS APPLICATION.
M01219981-I1
05/02/2025
Filed — Alteration
INSTALLATION OF SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M01218243-I1
05/02/2025
Permit issued — Sidewalk Shed
M01218243-I1-SH
05/02/2025
Special inspection requirement — Post-installed Anchors
Sandeep Gunnala
05/01/2025
Filed — Alteration
General construction for interior renovation of Apartment 9D on the 10th floor as shown on drawings filed herewith. No change in use, egress or occupancy.
M01212217-I1
05/01/2025
Special inspection requirement — Energy Code Compliance Inspections
John Field
05/01/2025
Special inspection requirement — Lighting in dwelling units
John Field
04/29/2025
Special inspection requirement — Tenant Protection Plan Compliance
John Field
04/17/2025
Special inspection requirement — Final
John Field
09/19/2023
Signed off — Alteration
General construction for interior renovation of Apartment 7H on the 8th floor as shown on drawings filed herewith. No change in use, egress or occupancy.
M00874136-I1
09/13/2023
Cycle 9 facade report signed — SWARMP
08/26/2023
Cycle 9 facade report submitted
08/10/2023
Cycle 9 facade inspection completed
07/17/2023
Permit issued — General Construction
M00874136-I1-GC
07/13/2023
Filed — Alteration
General construction for interior renovation of Apartment 7H on the 8th floor as shown on drawings filed herewith. No change in use, egress or occupancy.
M00874136-I1
05/17/2023
Special inspection requirement — Energy Code Compliance Inspections
John Field
05/17/2023
Special inspection requirement — Lighting in dwelling units
John Field
05/17/2023
Special inspection requirement — Tenant Protection Plan Compliance
John Field
05/12/2023
Special inspection requirement — Final
John Field
03/27/2023
Signed off — Alteration
M00816454-I1
03/16/2023
Signed off — Alteration
M00816433-I1
02/03/2023
Permit issued — General Construction
M00816433-I1-GC
02/03/2023
Permit issued — General Construction
M00816454-I1-GC
01/31/2023
Filed — Alteration
M00816454-I1
Latest 60 of 139 events.
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
BPP ST OWNER8009/01/2026
BPP OWNERS LLC103/22/2026
BPP PARKER TOWER PROPERTY OWNER103/22/2026
RELATED COMPANIES103/22/2026
ROSE ASSOCIATES1203/21/2026
EMPIRE CORE GROUP303/21/2026
COMPASS ROCK REAL ESTATE203/21/2026
ST OWNER1003/21/2026
ROSE ASSOCIATES INC MANAGER5703/21/2026
METROPOLITIAN LIFE INSURANCE1003/21/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
12/18/2015$4.1B—ST-DIL LLC → BPP ST OWNER LLC$460/sf building
06/03/2014$3.3B—— → —$372/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
BUILDING STUDIO ARCHITECTS704/21/2026
SANDEEP GUNNALA ENGINEERING PLLC204/15/2026
HC PEC502/25/2026
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
SANDEEP GUNNALA ENGINEERING203/21/2026
RIZZO GROUP603/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
SUPER G CONSTRUCTION CORPGeneral Contractor1307/08/2026
IRON WORKERS LOCAL 40Electrical403/21/2026
ASPESI, MARCELOElectrical403/21/2026
KAMA CONSTRUCTION CORPGeneral Contractor303/21/2026
VINCENT LOMBARDOZZIElectrical203/21/2026
PJP INSTALLERS INCGeneral Contractor207/08/2026
TORRES IVANElectrical103/21/2026
E-J ELEC. INSTALLATION COElectrical103/22/2026
HARVEY ISAACMANElectrical103/21/2026
ALBERTO SANCHEZElectrical103/22/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
BUILDING STUDIO ARCHITECT592604/21/2026
SANDEEP GUNNALA ENGINEERI8482304/15/2026
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionSigned-offSUPER G CONSTRUCTION CORP04/23/2026
DOB NOWGeneral ConstructionSigned-offSUPER G CONSTRUCTION CORP04/07/2026
DOB NOWGeneral ConstructionSigned-offKAMA CONSTRUCTION CORP06/02/2025
DOB NOWSuspended ScaffoldSigned-offTC ZONE INC05/20/2025
DOB NOWProtection and Mechanical MethodsSigned-offPJP INSTALLERS INC05/14/2025
DOB NOWGeneral ConstructionSigned-offSUPER G CONSTRUCTION CORP05/12/2025
DOB NOWSidewalk ShedSigned-offPJP INSTALLERS INC05/02/2025
DOB NOWGeneral ConstructionSigned-offSUPER G CONSTRUCTION CORP07/17/2023
DOB NOWGeneral ConstructionSigned-offSUPER G CONSTRUCTION CORP02/03/2023
DOB NOWGeneral ConstructionSigned-offSUPER G CONSTRUCTION CORP02/03/2023
DOB NOWGeneral ConstructionSigned-offSUPER G CONSTRUCTION CORP09/23/2022
BISOTISSUEDCRRE TOWN AND VILLAGE LLC09/25/2025
BISOTISSUEDCRRE TOWN AND VILLAGE LLC09/26/2024
BISOTISSUEDCRRE TOWN AND VILLAGE LLC09/26/2023
BISOTISSUEDCRRE TOWN AND VILLAGE LLC09/30/2022
BISOTISSUEDCRRE TOWN AND VILLAGE LLC10/07/2021
BISOTISSUEDCRRE TOWN AND VILLAGE LLC09/23/2020
BISOTISSUEDCRRE TOWN AND VILLAGE LLC06/15/2020
BISOTISSUEDCRRE TOWN AND VILLAGE LLC12/09/2019
BISPLISSUEDPACE PLUMBING CORP04/25/2019
BISOTISSUEDDELLAPEAK INTERIORS LLC04/22/2019
BISPLISSUEDPACE PLUMBING CORP02/11/2019
BISOTISSUEDCRRE TOWN AND VILLAGE LLC01/10/2019
BISOTISSUEDEMPIRE CORE GROUP LLC11/14/2018
BISOTISSUEDSOLAR ENERGY SYSTEMS INC01/09/2018
BISPLISSUEDPACE PLUMBING CORP01/08/2018
BISOTISSUEDCRRE TOWN AND VILLAGE LLC12/19/2017
BISEQISSUEDBAY RESTORATION CORP07/14/2017
BISPLISSUEDPACE PLUMBING CORP05/04/2017
BISPLISSUEDTHE PACE COMPANIES NY INC02/09/2017
BISOTISSUEDCRRE TOWN AND VILLAGE LLC12/13/2016
BISOTISSUEDEMPIRE CORE GROUP LLC09/27/2016
BISOTISSUEDEMPIRE CORE GROUP LLC09/22/2016
BISOTRE-ISSUEDEMPIRE CORE GROUP LLC06/29/2016
BISPLISSUEDTHE PACE COMPANIES NY INC03/07/2016
BISOTISSUEDCRRE TOWN AND VILLAGE LLC12/15/2015
BISPLISSUEDPACE PLUMBING CORP03/23/2015
BISOTISSUEDCRRE TOWN AND VILLAGE LLC01/09/2015
BISOTISSUEDCRRE TOWN AND VILLAGE LLC01/08/2015
BISOTRE-ISSUEDCRRE TOWN AND VILLAGE LLC11/05/2014
+ 21 more permits on file
▾Special Inspection Requirements (DOB NOW) — 30
DateRequirementInspectorRole
04/20/2026Energy Code Compliance InspectionsJohn Fieldprogress
04/20/2026Lighting in dwelling unitsJohn Fieldenergy_progress
04/17/2026MasonrySandeep Gunnalaspecial
04/17/2026Structural Stability – Alterations of existing buildingsSandeep Gunnalaspecial
04/17/2026Post-installed AnchorsSandeep Gunnalaspecial
04/17/2026FinalSandeep Gunnalaprogress
04/17/2026Tenant Protection Plan ComplianceSandeep Gunnalaspecial
04/02/2026Tenant Protection Plan ComplianceJohn Fieldspecial
03/31/2026FinalJohn Fieldprogress
05/15/2025Alternative Materials - OTCR Buildings Bulletin NumberSandeep Gunnalaspecial
05/02/2025Post-installed AnchorsSandeep Gunnalaspecial
05/01/2025Energy Code Compliance InspectionsJohn Fieldprogress
05/01/2025Lighting in dwelling unitsJohn Fieldenergy_progress
04/29/2025Tenant Protection Plan ComplianceJohn Fieldspecial
04/17/2025FinalJohn Fieldprogress
05/17/2023Energy Code Compliance InspectionsJohn Fieldprogress
05/17/2023Lighting in dwelling unitsJohn Fieldenergy_progress
05/17/2023Tenant Protection Plan ComplianceJohn Fieldspecial
05/12/2023FinalJohn Fieldprogress
01/31/2023Lighting in dwelling unitsJohn Fieldenergy_progress
01/31/2023Energy Code Compliance InspectionsJohn Fieldprogress
01/31/2023Lighting in dwelling unitsJohn Fieldenergy_progress
01/31/2023Tenant Protection Plan ComplianceJohn Fieldspecial
01/31/2023Tenant Protection Plan ComplianceJohn Fieldspecial
01/31/2023Energy Code Compliance InspectionsJohn Fieldprogress
Latest 25 of 30.
▾Documents — 1,038 on file (BIS + DOB NOW)
▸Plans & Drawings15
▸DOB NOWPlans/Sketch15
09/01/2026M08002411-I1Request digital key ↗
09/01/2026M00816433-I1Request digital key ↗
09/01/2026M00816454-I1Request digital key ↗
Showing 3 of 15 on file for this type
▸Applications & Permits164
▸BISPLAN / WORK APPROVAL APPLICATION83
07/30/2020102787085Open ↗
02/12/2020102787085Open ↗
04/19/2019123737983Open ↗
Showing 3 of 83 on file for this type
▸BISWORK PERMIT APPLICATION80
12/10/2019102787085Open ↗
04/25/2019123737983Open ↗
04/22/2019123737983Open ↗
Showing 3 of 80 on file for this type
▸BISNon-Directive 14 Construction Sign Off Including Sign Applications1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Seals & Professional Certifications311
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION133
01/28/2020123737983Open ↗
01/28/2020123737983Open ↗
08/23/2019123534906Open ↗
Showing 3 of 133 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST68
04/19/2019123737983Open ↗
11/14/2018123534906Open ↗
07/18/2017123332223Open ↗
Showing 3 of 68 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM56
11/10/2014122092859Open ↗
Showing 1 of 56 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature14
09/01/2026M08002411-I1Open ↗
09/01/2026M00816433-I1Open ↗
08/29/2026M00874136-I1Open ↗
Showing 3 of 14 on file for this type
▸DOB NOWProgress Inspector Seal & Signature13
09/08/2026M01219634-I1Open ↗
09/01/2026M08002411-I1Open ↗
09/01/2026M08002411-I1Open ↗
Showing 3 of 13 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT11
04/19/2019123737983Open ↗
11/14/2018123534906Open ↗
01/08/2018140723652Open ↗
Showing 3 of 11 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature11
09/08/2026M01219634-I1Open ↗
09/08/2026M01219634-I1Open ↗
09/08/2026M01219634-I1Open ↗
Showing 3 of 11 on file for this type
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION3
01/08/2018140723652Open ↗
09/30/2013140119752Open ↗
Showing 2 of 3 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY2
01/08/2018140723652Open ↗
09/30/2013140119752Open ↗
▸Trade Schedules & Equipment4
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE2
04/19/2019123737983Open ↗
11/14/2018123534906Open ↗
▸BISSCHEDULE B - PLUMBING1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISSELF-CERT PLUMBING NOTICE1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Safety & Tenant Protection4
▸BISTenant Protection Plan and Notes4
04/19/2019123737983Open ↗
11/14/2018123534906Open ↗
04/07/2016122755866Open ↗
Showing 3 of 4 on file for this type
▸Environmental & Asbestos94
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'68
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 68 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)16
04/19/2019123737983Open ↗
11/14/2018123534906Open ↗
01/08/2018140723652Open ↗
Showing 3 of 16 on file for this type
▸DOB NOWDEP ACP-5: Asbestos Assessment Report9
09/01/2026M08002411-I1Open ↗
09/01/2026M00816433-I1Open ↗
08/29/2026M00874136-I1Open ↗
Showing 3 of 9 on file for this type
▸BISACP5 ASBESTOS: CERTIFICATION (DEP ACP5)1
01/22/2015122239087Open ↗
▸Energy Compliance51
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS24
01/28/2020123737983Open ↗
01/28/2020123737983Open ↗
08/23/2019123534906Open ↗
Showing 3 of 24 on file for this type
▸BISTECHNICAL REPORT: ENERGY13
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 13 on file for this type
▸BISTR8: Energy Code Progress Inspections6
11/10/2014122092859Open ↗
Showing 1 of 6 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS4
01/28/2020123737983Open ↗
08/23/2019123534906Open ↗
03/18/2019140723652Open ↗
Showing 3 of 4 on file for this type
▸BISELECTRICAL APPLICATION FOR SIDEWALK SHED LIGHTING2
09/30/2013140119752Open ↗
Showing 1 of 2 on file for this type
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY1
01/08/2018140723652Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS1
01/08/2018140723652Open ↗
▸Inspections & Test Reports6
▸BISTECHNICAL REPORT: RESPONSIBILITY3
01/08/2018140723652Open ↗
01/08/2018140723652Open ↗
Showing 2 of 3 on file for this type
▸BISTECHNICAL REPORT: CONCRETE/TEST CYLINDER2
05/12/2017122755866Open ↗
07/01/2016122755866Open ↗
▸BISTECHNICAL REPORT: CONCRETE DESIGN MIX1
07/01/2016122755866Open ↗
▸Approvals, Objections & Sign-offs124
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST63
01/28/2020123737983Open ↗
08/23/2019123534906Open ↗
03/18/2019140723652Open ↗
Showing 3 of 63 on file for this type
▸BISADMINISTRATIVE OBJECTIONS56
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 56 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION4
01/08/2018140723652Open ↗
01/13/2014121744176Open ↗
Showing 2 of 4 on file for this type
▸BISSUPERSEDING LETTER1
05/26/2017102787085Open ↗
▸Cost, Insurance & Ownership179
▸BISCOST AFFIDAVIT124
01/28/2020123737983Open ↗
08/23/2019123534906Open ↗
04/19/2019123737983Open ↗
Showing 3 of 124 on file for this type
▸BISHIC LICENSE OR AFFIDAVIT55
01/22/2015122239087Open ↗
11/10/2014122092859Open ↗
07/29/2014122047962Open ↗
Showing 3 of 55 on file for this type
▸Filing & Intake Forms82
▸BISEFILING COVER SHEET62
04/19/2019123737983Open ↗
11/14/2018123534906Open ↗
07/18/2017123332223Open ↗
Showing 3 of 62 on file for this type
▸BISeFiling Job Application Cover Sheet9
01/08/2018140723652Open ↗
09/30/2013140119752Open ↗
Showing 2 of 9 on file for this type
▸BISBOROUGH INTAKE FORM8
02/12/2020102787085Open ↗
01/28/2020123737983Open ↗
08/23/2019123534906Open ↗
Showing 3 of 8 on file for this type
▸BISADDITIONAL INFORMATION3
04/19/2019123737983Open ↗
03/01/2017122755866Open ↗
Showing 2 of 3 on file for this type
▸Other Documents4
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION2
05/12/2017122755866Open ↗
Showing 1 of 2 on file for this type
▸DOB NOWManufacturer's Specifications1
08/13/2026M01219981-I1Open ↗
▸DOB NOWCalculations1
08/13/2026M01219981-I1Open ↗