← Back
Two stories - detached, small or mid-size
240-45 POPLAR STREET
QUEENS · Douglaston-Little Neck · BIN 4168806
💬 Discuss this project
1950Year Built
2Stories
A1Building Class
R1-2Zoning
2,129 sfGross Floor Area
1Units
Two stories - detached, small or mid-size · 10,000 sf lot · 0.21 FAR built · Flood zone X
Locations of Work
ArchitecturePlumbing
Floor 13p · 1 filing · 11 docs
Cellar4p · 1 filing · 11 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
DADRAS ARCHITECTS303/01/2021
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
ARJUNE DESING STUDIO303/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
TOP DOG PLBG & HTG CORPPlumbing207/08/2026
Building Lifecycle
All (5)Filed (3)Permit Issued (2)
05/06/2021
Permit issued — Plumbing
Q00227569-I1-PL
03/01/2021
Filed — Alteration
RESPECTFULLY REQUEST A PAA TO CORRECT PLUMBING FIXTURES SCHEDULE B FOR APPLICATION Q00227569 I1. HEREWITH FILING REVISED FORMS & NO PLAN CHANGES. NO CHANGE IN USE OR OCCUPANCY.
Q00227569-P2
12/18/2020
Filed — Alteration
RESPECTFULLY REQUEST A PAA TO CORRECT PLUMBING FIXTURES SCHEDULE B FOR APPLICATION Q00227569 I1. HEREWITH FILING REVISED FORMS & NO PLAN CHANGES. NO CHANGE IN USE OR OCCUPANCY.
Q00227569-P1
10/26/2020
Permit issued — Plumbing
Q00227569-I1-PL
11/27/2019
Filed — Alteration
RESPECTFULLY REQUEST A PAA TO CORRECT PLUMBING FIXTURES SCHEDULE B FOR APPLICATION Q00227569 I1. HEREWITH FILING REVISED FORMS & NO PLAN CHANGES. NO CHANGE IN USE OR OCCUPANCY.
Q00227569-I1
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingSigned-offTOP DOG PLBG & HTG CORP05/06/2021
DOB NOWPlumbingSigned-offTOP DOG PLBG & HTG CORP10/26/2020
BISOTISSUEDHARMONY ENTERPRISES NY IN04/28/2021
BISOTISSUEDHARMONY ENTERPRISES NY IN10/09/2020
BISOTISSUEDHARMONY ENTERPRISES NY IN09/29/2020
BISOTISSUED770 ELECTRIC CORP04/05/2016
BISOTISSUEDAUTHENTIC REM03/07/1996
1 project · most recent 03/01/2021
Gas Water/Sanitary
FiledStatusContractorScope
03/01/2021Signed-offTOP DOG PLBG & HTG CORPGas, Water/Sanitary
1 project · most recent 06/14/2021
General Wiring
FiledStatusContractorScope
06/14/2021Permit IssuedRAY JAY & A ELECTRIC CORPGeneral Wiring
Nothing on file for this building.
▾Documents — 96 on file (BIS + DOB NOW)
▸Plans & Drawings3
▸DOB NOWPlans/Sketch - Plumbing3
08/27/2026Q00227569-I1Request digital key ↗
08/27/2026Q00227569-P1Request digital key ↗
08/15/2026Q00227569-P2Request digital key ↗
▸Applications & Permits9
▸BISPLAN / WORK APPROVAL APPLICATION5
04/07/2021421915155Open ↗
01/15/2020421915155Open ↗
01/14/2020421915155Open ↗
Showing 3 of 5 on file for this type
▸BISWORK PERMIT APPLICATION2
10/29/2020421915155Open ↗
04/01/2016440300014Open ↗
▸BISNon-Directive 14 Construction Sign Off Including Sign Applications1
05/18/2021421915155Open ↗
▸BISPARTIAL DEMO: 10-DAY NOTICE (FOR AL/EW-OT PERMITS)1
09/25/2020421915155Open ↗
▸Zoning, Tax Lot & Property Records1
▸BISZONING DIAGRAM1
01/09/2020421915155Open ↗
▸Seals & Professional Certifications13
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION7
01/15/2020421915155Open ↗
01/15/2020421915155Open ↗
01/15/2020421915155Open ↗
Showing 3 of 7 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature3
08/27/2026Q00227569-P2Open ↗
08/27/2026Q00227569-I1Open ↗
08/27/2026Q00227569-P1Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT1
04/01/2016440300014Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
04/01/2016440300014Open ↗
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION1
04/01/2016440300014Open ↗
▸Safety & Tenant Protection9
▸DOB NOWTenant Protection Plan3
08/13/2026Q00227569-P2Open ↗
08/13/2026Q00227569-P1Open ↗
08/13/2026Q00227569-I1Open ↗
▸BISSTREET TREE CHECKLIST2
01/15/2020421915155Open ↗
01/14/2020421915155Open ↗
▸BISEXCAVATION OR DEMOLITION: 5-DAY NOTICE1
09/25/2020421915155Open ↗
▸BISSTREET TREES: RECEIPT OF STREET TREES SITE PLAN1
09/29/2020421915155Open ↗
▸BISTENANT PROTECTION PLAN AND NOTES1
04/01/2016440300014Open ↗
▸BISEXCAVATION - SHEETING, SHORING, AND BRACING1
09/25/2020421915155Open ↗
▸Environmental & Asbestos3
▸BISASBESTOS: CERTIFICATION (DEP ACP5)1
04/01/2016440300014Open ↗
▸BISASBESTOS: COMPLETION OR CLOSEOUT (ACP20/21/5)1
09/29/2020421915155Open ↗
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form1
08/27/2026Q00227569-I1Open ↗
▸Energy Compliance22
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY4
05/18/2021421915155Open ↗
05/11/2021421915155Open ↗
10/17/2016440300014Open ↗
Showing 3 of 4 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS3
05/18/2021421915155Open ↗
05/11/2021421915155Open ↗
10/17/2016440300014Open ↗
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS3
01/15/2020421915155Open ↗
01/14/2020421915155Open ↗
09/16/2019421915155Open ↗
▸BISAIR SEALING AND INSULATION - VISUAL1
09/15/2020421915155Open ↗
▸BISINSULATION PLACEMENT & R VALUES1
09/15/2020421915155Open ↗
▸BISINTERIOR LIGHTING POWER1
09/15/2020421915155Open ↗
▸BISAS-BUILT ENERGY ANALYSIS (EN2)1
05/11/2021421915155Open ↗
▸BISFENESTRATION AREAS1
09/15/2020421915155Open ↗
▸BISFENESTRATION U-FACTOR & PRODUCT RATING1
09/15/2020421915155Open ↗
▸BISPTA4: SOLAR TAX ABATEMENT APPLICATION (PRELIMINARY)1
04/01/2016440300014Open ↗
▸BISPTA4: SOLAR TAX ABATEMENT APPLICATION (FINAL)1
10/17/2016440300014Open ↗
▸BISLIGHTING IN DWELLING UNITS1
09/15/2020421915155Open ↗
▸BISENERGY CODE COMPLIANCE INSPECTIONS1
09/15/2020421915155Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS1
04/01/2016440300014Open ↗
▸BISFENESTRATION AIR LEAKAGE1
09/15/2020421915155Open ↗
▸Inspections & Test Reports13
▸BISTECHNICAL REPORT: RESPONSIBILITY6
05/18/2021421915155Open ↗
05/18/2021421915155Open ↗
05/11/2021421915155Open ↗
Showing 3 of 6 on file for this type
▸BISTECHNICAL REPORT: SOIL INSPECTION2
01/15/2020421915155Open ↗
01/14/2020421915155Open ↗
▸BISFIRE-RESISTANT PENETRATIONS AND JOINTS (FIRESTOP)1
09/15/2020421915155Open ↗
▸BISFOOTING AND FOUNDATION INSPECTION1
09/15/2020421915155Open ↗
▸BISSTRUCTURAL STABILITY - EXISTING BUILDINGS1
09/15/2020421915155Open ↗
▸BISFRAME (2008)/STRUCTURAL WOOD FRAME (2014) INSPECTION1
09/15/2020421915155Open ↗
▸BISCONCRETE - CAST-IN-PLACE1
09/15/2020421915155Open ↗
▸Approvals, Objections & Sign-offs6
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST2
05/18/2021421915155Open ↗
10/17/2016440300014Open ↗
▸BISLETTERS - SUPPORTING DOCUMENTATION2
01/15/2020421915155Open ↗
10/17/2016440300014Open ↗
▸BISUtility Company PV System Interconnection Acknowledgement Letter1
10/17/2016440300014Open ↗
▸BISSUSTAINABLE ROOF ZONE FORM (SIGNOFF)1
05/11/2021421915155Open ↗
▸Cost, Insurance & Ownership7
▸BISCOST AFFIDAVIT7
05/18/2021421915155Open ↗
05/11/2021421915155Open ↗
01/15/2020421915155Open ↗
Showing 3 of 7 on file for this type
▸Filing & Intake Forms7
▸BISADDITIONAL INFORMATION4
04/13/2021421915155Open ↗
01/14/2020421915155Open ↗
01/14/2020421915155Open ↗
Showing 3 of 4 on file for this type
▸BISBOROUGH INTAKE FORM1
10/29/2020421915155Open ↗
▸BISEFILING COVER SHEET1
09/16/2019421915155Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET1
04/01/2016440300014Open ↗
▸Other Documents3
▸BISPLOT DIAGRAM2
01/15/2020421915155Open ↗
01/14/2020421915155Open ↗
▸BISPROTECTION OF EXPOSED FOUNDATION INSULATION1
09/15/2020421915155Open ↗